Item | Estimation | Time Spent | Done Planning? | Completed? |
---|---|---|---|---|
Search general, fields, icons | 15 days | 1 day | ||
Building Show | 1-3 days | 6 days | ✔️ | |
Create .list-group-mobile and .list-group-item-mobile |
1 day | |||
NSD Contract (same as current but different schedule?) | 1 day | |||
Drop in Contract | 1 day | |||
Menu Design: Search/Dropdown | 14 days | 5 days | ✔️ | |
Childcare Finish
|
6 - 7 days | 1 day | ||
Facilities Finish
|
10 - 14 days | |||
Survey (mockup)
|
2-3 days | 1 day | ✔️ | |
Various mobile tweaks | 10 - 15 days | |||
Total Estimate (rounded up) | ~100 days (~4.5 months) |