Skip to content

Instantly share code, notes, and snippets.

@kuanb
Created August 23, 2021 02:26
Show Gist options
  • Star 0 You must be signed in to star a gist
  • Fork 0 You must be signed in to fork a gist
  • Save kuanb/65e681e2239a1c4008f826b1132791bc to your computer and use it in GitHub Desktop.
Save kuanb/65e681e2239a1c4008f826b1132791bc to your computer and use it in GitHub Desktop.
table from cal hsr change orders open data as usable csv
PROJECT CONTRACT NO. CHANGE ORDER NO. APPROVED DATE CONTRACTOR CATEGORY TITLE AMOUNT ($) DESCRIPTION AUTHORITY APPROVER CONTRACTOR COUNTERPARTY CONSULTANT SUPPORT
0 CP 1 HSR 13-06 00386 6/25/2021 Tutor Perini/Zachry/Parsons Differing Site Conditions AT&T Task 4, Phase II MH-769 Caltrans Water Service Relocation - Construction $36,061.19 This is a change to a contract for construction services in the Central Valley. The reason for the change is to fully compensate the Contractor for the work performed to relocate the existing Caltrans 2-inch irrigation water service line located at Ashlan Avenue across SR-99 on-ramp. This service line was in physical conflict with the proposed location of the AT&T intercept vault requiring the waterline relocation outside of the proposed AT&T intercept vault footprint location. Scott Kennedy - Senior Contract Manager Ghassan Ariqat - Project Manager/Director Eric Stassevitch - DB Oversight Manager
1 CP 1 HSR 13-06 00119.1 R1 4/2/2021 Tutor Perini/Zachry/Parsons Third Party Related Right of Entry and License Fees for Railroad Utility Crossings $510,000.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to capture addition of funds to the original Change Order 00119 to reimburse the Contractor for costs associated with reassignment of the Utility Crossing Application and license fee responsibility from the Authority to the Contractor per Directive Letter 00063 and 00067. The Change Order value is to be increased by $510,000.00 from $860,000.00 to $1,370,000.00. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Eric Stassevitch - DB Oversight Manager
2 CP 1 HSR 13-06 00369 4/14/2021 Tutor Perini/Zachry/Parsons Third Party Related Maintain and Repair Public Roads as Detour Haul Routes Surety Bonds $166,868.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the premiums for additional surety bonds required by the County of Madera as a condition for issuance of Encroachment Permits required for maintaining and repairing public roads used as haul and detour routes. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Eric Stassevitch - DB Oversight Manager
3 CP 1 HSR 13-06 00360 4/27/2021 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Striping Changes at SR-180 $33,930.00 This is a change to a contract for construction services in the Central Valley. The reason for this change is to compensate the Contractor for the following changes directed by the Authority to conform to Caltrans updated standards on SR-180: 1. Construct 6-inch wide thermoplastic traffic stripe instead of 4-1nch wide thermoplastic traffic stripe. 2. Construct Enhanced Wet Night Vision (EWNV) thermoplastic traffic stripe instead of non-EWNV thermoplastic traffic stripe. 3. Provide Black Contrast on Broken White Stripe Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Eric Stassevitch - DB Oversight Manager
4 CP 1 HSR 13-06 00233.6 3/8/2021 Tutor Perini/Zachry/Parsons Third Party Related MVWC Relocation at Road 27 - Extended Fee Agreement $5,719.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is for the supplemental Deposit and Reimbursement for Madera Valley Water Company (MVWC). This is the sixth supplemental Change Order. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Eric Stassevitch - DB Oversight Manager
5 CP 1 HSR 13-06 00048.6 3/9/2021 Tutor Perini/Zachry/Parsons Administrative Supplemental No. 6 Funding for Excluded Third Party Provisional Sum $78,004,971.31 This is a change to a contract for design and construction services in the Central Valley. The reason for the Supplemental Change Order is to increase the amount of the Provisional Sum described in Change Order 0048, 0048.1, 0048.2, 0048.3, 0048.4 and 0048.5 by $78,004,971.31. All other terms and conditions of the original Change Order Nos. 0048, 0048.1, 0048.2, 0048.3, 0048.4 and 0048.5 shall remain unchanged and in full force and effect. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Eric Stassevitch - DB Oversight Manager
6 CP 1 HSR 13-06 00363 3/12/2021 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Avenue 15 Changes - Construction $1,813,876.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the repositioning of Avenue 15 overpass to match the alignment of the existing Avenue 15 as required by County of Madera. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Eric Stassevitch - DB Oversight Manager
7 CP 1 HSR 13-06 00373 3/18/2021 Tutor Perini/Zachry/Parsons Adminisrtative Chinatown and Downtown Outreach $76,000.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to provide additional Chinatown and Downtown Outreach as requested and approved by the Authority authorized representative. This will include the purchasing of print, television, radio, social media ads as well as other community outreach events. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Eric Stassevitch - DB Oversight Manager
8 CP 1 HSR 13-06 00368 2/16/2021 Tutor Perini/Zachry/Parsons Differing Site Conditions FB-10-0044 Additional Demolition $29,909.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for extra demolition work of an additional building along with the associated parking lot outside the original footprint (HSR ROW) on Parcel FB-10-0044. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Eric Stassevitch - DB Oversight Manager
9 CP 1 HSR 13-06 00370 2/26/2021 Tutor Perini/Zachry/Parsons Third Party Related COF Temporary Backflow Preventors Water Tie-ins - Construction Only $1,784,591.00 This is a change to a contract for construction services in the Central Valley. The reason for this change is for the additional construction costs to incorporate COF requirement to comply with the American Water Works Association (AWWA) C651-14 and install temporary reduced pressure backflow assemblies when making connections to City potable water systems. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Eric Stassevitch - DB Oversight Manager
10 CP 1 HSR 13-06 00371 2/26/2021 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications UPRR Tulare St & Ventura St Steel Girders - Metric Bolts DL 00183 R1 $1,048,083.21 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the additional costs associated with replacing 3/4-inch size girder steel bolts with metric bolts at the Tulare and Ventura Street bridges as per the resolution agreement at Level 2 of the Issue Resolution Ladder protocol. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Eric Stassevitch - DB Oversight Manager
11 CP 1 HSR 13-06 342 1/8/2021 Tutor Perini/Zachry/Parsons Differing Site Conditions Clearing and Grubbing Change in Condition $78,623.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is for the additional clearing and grubbing of the identified parcels which were vacant in 2012 at bid time as enumerated in this Change Order. This Change Order excludes all environmental work. Raaid Abouzedan - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Clifford Wong - DB Oversight Manager
12 CP 1 HSR 13-06 6.2 1/11/2021 Tutor Perini/Zachry/Parsons Administrative Additional DRB Expenses $180,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to add funds to the original Change Order 00006 for reimbursement of 50 perent DRB and special services costs in accordance with the Contract. The current amount is hereby increased by $180,000.00 from $280,000.00 to $460,000.00. Raaid Abouzedan - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Clifford Wong - DB Oversight Manager
13 CP 1 HSR 13-06 233.5 1/17/2021 Tutor Perini/Zachry/Parsons Third-Party Related Madera Valley Water Company - Relocation at Road 27 - Extended Fee Agreement $22,876.00 This is a change to a contract for design services in the Central Valley. The reason for the change is for the supplemental deposit and reimbursement of funds for Madera Valley Water Company per Authority request for agreement review services. Raaid Abouzedan - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Clifford Wong - DB Oversight Manager
14 CP 1 HSR 13-06 88.10 1/29/2021 Tutor Perini/Zachry/Parsons Administrative CP1 Additional Environmental Services $16,795,000.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to add funds to the original change order No. 00088 for the performance of all Environmental Services on a time and material basis. The original amount is hereby increased $16,795,000.00, from $32,175,000.00 to $48,970,000.00. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Eric Stassevitch - DB Oversight Manager
15 CP 1 HSR 13-06 351 10/29/2020 Tutor Perini/Zachry/Parsons Third-Party Related DL 0041 Westside Shoofly Design Mod $33,101.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the design Subcontractor for continuing consultation and design efforts to address the new comments from Union Pacific Rail Road and San Joaquin Valley Railroad regarding the Contractor's 90% design submittal for the Westside Wye Shooflies. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Grant for Don Bullock - DB Oversight Manager
16 CP 1 HSR 13-06 88.9 10/3/2020 Tutor Perini/Zachry/Parsons Administrative Additional Environmental Services $2,175,000.00 This is a change to a contract for construction services in the Central Valley. This supplemental Change Order adds funds to Change Order No. 00088. The current amount is hereby increased $2,175,000.00, from $30,000,000.00 to $32,175,000.00. The work shall be performed in accordance with Section 17.9,"Changes - Time and Material Change Orders" of the Gerneal Provisions. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Clifford Wong - DB Oversight Manager
17 CP 1 HSR 13-06 354 9/22/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Redesign W1-042 Crossing Pine West $71,576.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for design efforts associated with the redesign of the City of Fresno water main W1-042 due to the Union Pacific Rail Road requirements regarding the location of the City of Fresno water main crossing under the Union Pacific Rail Road tracks. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Don Bullock - DB Oversight Manager
18 CP 1 HSR 13-06 343 9/10/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Scope Change Fresno Drainage - Design $220,633.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the redesign costs to take the drainage design from a conceptual level to 90% again based upon updated criteria from the California High Speed Rail Authority and the City of Fresno. Compensation also includes any reduction in design effort of the closed system. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
19 CP 1 HSR 13-06 355 9/10/2020 Tutor Perini/Zachry/Parsons Administrative DL-00164 Kinder Morgan Relocation $17,077.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the coordination efforts to incorporate design changes per Authority Directive Letter 0164. The Contractor coordinated with Union Pacific Rail Road to define the configuration for the pipeline relocation, Kinder Morgan performed the redesign. This Change Order does not include the design cost reimbursement for Kinder Morgan as well as the impacted construction costs. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
20 CP 1 HSR 13-06 349 8/26/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications SJVRR South Spur Fresno Trench Lid $334,106.00 This is a change in contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the redesign efforts of the Fresno Trench Lid in compliance to Authority Directive Letter 00133 including designing for the incorporation of the Cooper E-80 live load criteria of a passenger train. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
21 CP 1 HSR 13-06 328.01 8/19/2020 Tutor Perini/Zachry/Parsons Administrative Increase the Amount of the Utility Provisional Sum $7,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to increase the amount of the Utility Provisional Sums as defined by the Contract to compensate the Contractor for utility work. Elias Mahfoud - Director of Design and Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
22 CP 1 HSR 13-06 350 8/14/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications SJVRR South Spur Dry Creek Canal Box Increased Drawing - Design $71,983.00 This is a change to a contract for design services in the Central Valley. The reason for the change is for the additional design effort necessary to incorporate Directive Letter 0134 titled "Dry Creek Box Culvert". Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
23 CP 1 HSR 13-06 347 8/14/2020 Tutor Perini/Zachry/Parsons Third Party Related DL-0080 UPRR & BNSF Future Track Locations - Design $337,883.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for all additional redesign costs as a result of Directive Letter 0080, Union Pacific Rail Road and Burlington Northern Santa Fe Rail Road Future Track Locations. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
24 CP 1 HSR 13-06 346 8/14/2020 Tutor Perini/Zachry/Parsons Third Party Related DL-0087 Maintenance Setback for BNSF Right Of Way $1,170,936.06 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the design of all impacted overhead structure bent locations due to Directive Letter 0087 which mandated a 5-foot maintenance setback between all structural elements and the Burlington Northern Santa Fe Railway Right Of Way. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
25 CP 1 HSR 13-06 345 8/14/2020 Tutor Perini/Zachry/Parsons Administrative DL-0186 RM Tool Submital Specific RVTM & CIL Modules $106,154.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to compensate the implementation of all impacts related to the Requirements Management Tool Submittal, specific Requirements Verification Traceability Matrix and Critical Items List module Design Deliverables. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
26 CP 1 HSR 13-06 48.5 8/11/2020 Tutor Perini/Zachry/Parsons Administrative Supplementary No. 5 Funding for Excluded Third Party Provisional Sum $9,500,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the supplemental change is to increase the amount of the Provisional Sums to compensate the contractor to manage and subcontract all direct services required for the relocation of PG&E and AT&T Excluded Third Party Utilities. This Supplemental Change Order increases the total amount of the aforementioned Provisional Sums by $9,500,000.00. Elias Mahfoud - Director of Design and Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
27 CP 1 HSR 13-06 348 8/6/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications CPUC at Church Avenue - Construction $3,563,048.00 This is a change to a contract for construction services in the Central Valley. The reason for this change is to compensate the Contractor for construction costs in compliance with Directive Letter 0038 General Order and Settlement Agreement and Directive Letter 0038 R1 Installation of Spare Conduit and Pull Boxes, for the California Public Utilities Commission bridge deck and underground conduit installation at Church Avenue. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
28 CP 1 HSR 13-06 308.01 7/29/2020 Tutor Perini/Zachry/Parsons Third-Party Related Westside Shoofly Modifications - Construction $11,358,356.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for labor, material and equipment necessary to incorporate all revisions as a result of implementing two temporary Shooflys in order to allow construction on the Fresno Trench to proceed without interrupting Union Pacific Rail Road and San Joaquin Valley Rail Road operations. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
29 CP 1 HSR 13-06 344 7/10/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications DL-0179 Upgrade of Concrete Barriers on City of Fresno Bridges - Design $78,881.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the redesign costs of the traffic barriers for the City of Fresno bridges in accordance with Caltrans 2015 Standard Specifications and Standards Plan as per Authority Directive Letter 0179. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
30 CP 1 HSR 13-06 341 7/2/2020 Tutor Perini/Zachry/Parsons Third-Party Related Tuolumne Street Overhead Sign Removal $13,166.30 This is a change to a contract for construction services in the Central Valley. The reason for the change is for the removal of the City of Fresno overhead sign located on Tuolumne Street between O and P Streets, including the restoration of sidewalk. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
31 CP 1 HSR 13-06 338 7/2/2020 Tutor Perini/Zachry/Parsons Differing Site Conditions FB-10-0149 & 0140 Contaminated Materials at 1625 & 1626 Tulare Street $225,000.00 This is a change to a contract for construction services in the Central Valley. The reason for this change is to compensate the Contractor for the stockpiling and storing of approximately 12,000 cubic yards of contaminated soil generated from the excavation of Parcels FB-10-0149 and 0140 (1626 and 1625 Tulare Street) in order to comply with the Soil Management Plan that the Authority provided, including additional testing and backfill of material on site. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
32 CP 1 HSR 13-06 233.4 7/2/2020 Tutor Perini/Zachry/Parsons Third-Party Related Madera Valley Water Relocation at Road 27 - Extended Agreement Fee $28,595.00 This is a change to a contract for design services in the Central Valley. The reason for the change is for the initial deposit and reimbursement of funds for Madera Valley Water Company per Authority request for agreement review services. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
33 CP 1 HSR 13-06 265.02 6/25/2020 Tutor Perini/Zachry/Parsons Right-of-Way (ROW) Related Union Pacific Rail Road Homeless Encampment Clean-up $1,000,000.00 This is a change to a contract for the construction services in the Central Valley. The reason for this supplemental change is to add funds to the original CO 00265. The original amount including all supplemental is hereby increased by $1,000,000.00, from $600,000.00 to $1,600,000.00. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
34 CP 1 HSR 13-06 322 6/24/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Intrusion Protection Requirements, Added Quantity - Construction $198,513,186.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for all labor, material, equipment and mobilization necessary to incorporate all additional quantity of Intrusion Protection Barrier; 45,792.25 Linear Feet along with 395.97 Linear Feet at the North Extension. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
35 CP 1 HSR 13-06 320 6/24/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Intrusion Protection Requirements, Original Quantitiy Revisions - Construction $58,753,462.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for all labor, material and equipment necessary to incorporate all required revisions to the original quantity of Intrusion Protection Barrier; 22,309.50 Linear Feet. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
36 CP 1 HSR 13-06 331 6/23/2020 Tutor Perini/Zachry/Parsons Dispute Resolution Pedestrian Push Button Replacements $4,641.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the replacement of three damaged pedestrian push button plates along Tuolumne Street. There are two damaged pedestrian push buttons that are located at Tuolumne and F Street and one at Tuolumne and N Street. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
37 CP 1 HSR 13-06 337 6/18/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications City of Fresno Right of Way Lines $3,750,403.77 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the re-design efforts due to the adjustments of Right of Way limits for twelve design packages within the City of Fresno per Authority Directive Letter 0162. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
38 CP 1 HSR 13-06 326 6/18/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications McKinley Basin EE Pump Station - Pump Procurment and Installation $154,925.00 This change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the procurement and installation of pump station at the Fresno Metropolitan Flood Control District Basin EE pump station relocation site in accordance with Directive Letter 0024. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
39 CP 1 HSR 13-06 336 6/12/2020 Tutor Perini/Zachry/Parsons Differing Site Conditions Dry Well at Golden State Boulevard betweeen Cornelia and State Streets $6,361.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the removal of a dry well that was discovered during excavation at Golden State Boulevard between Cornelia and State Streets. This Change Order is based on the abandonment procedure specified by the City of Fresno. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
40 CP 1 HSR 13-06 335 6/12/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Shift City of Fresno at Jensen Avenue onto Authority Owned Parcels $364,356.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the additional costs to redesign the relocation of multiple utility design packages to reduce the need for additional Right of Way. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
41 CP 1 HSR 13-06 334 6/12/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Avenue 9 Retaining Wall Redesign to Avoid Additional Right of Way - Design $129,861.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the additional costs to redesign the southern embankments of Avenue 9 roadway by utilizing retaining walls instead of the existing fill slopes to avoid the need to acquire additional Right of Way for PG&E conflict GT1-005. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
42 CP 1 HSR 13-06 333 6/12/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications FMFCD Casing and Carrier Pipe under Union Pacific Rail Road $570,910.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for additional design costs in compliance with Authority Directive Letter 0152 R1 to design spare bypass casings to supplement the Fresno Metropolitan Flood Control District's existing facility relocations that are currently in design. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
43 CP 1 HSR 13-06 323 6/12/2020 Tutor Perini/Zachry/Parsons Right-of-Way (ROW) Related Immediate Demolition of Structures on Parcels FB-10-0200 and FB-10-0653 $58,798.84 This change to a contract for construction services in the Central Valley. The reason for this change is to compensate the Contractor for demolishing the structures on parcels FB-10-0200 and FB-10-0653 as outlined in the demolition plan due to safety concerns. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
44 CP 1 HSR 13-06 324 5/29/2020 Tutor Perini/Zachry/Parsons Differing Site Conditions Additional Labor and Equipment Cost for Installation of 16" COF Waterline Across Shaw Avenue Open Trench Installation $520,652.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the additional construction costs to proceed with the open trench installation of the waterline across Shaw Avenue under night time road closure in lieu of shifting traffic onto the Shaw detour due to delays in other utility relocations and subsequent availability of Right of Way. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
45 CP 1 HSR 13-06 300 5/29/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications DL-0174 City of Fresno Design Package SS1-066, 067 & 145 at Monterey Street $169,373.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate Contractor for the redesign of the sewer line that runs underneath the high-speed train and UPRR right of way at Monterey Street. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
46 CP 1 HSR 13-06 292 5/29/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications City of Fresno Design Package W1-073 Florence Avenue per DL-0174 - Design $72,292.00 This is a change to a contract for design services in the Central Valley. The reason for this change is to compensate the Contractor for the design modifications required by Directive Letter 0174 to redesign the utility to align with the UPRR preferences. The new design crosses the railroad at seventy one degrees and was approved at that angle through Design Variance Request 275. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
47 CP 1 HSR 13-06 332 5/28/2020 Tutor Perini/Zachry/Parsons Right-of-Way (ROW) Related Fambro Additional Demolition Credit - South Building ($12,451.48) This is a change to a contract for construction services in the Central Valley. The reason for the change is to provide credit to the Authority for Change Order 00246. The amount that the Contractor incurred in asbestos testing is deducted from the credit due to the demolition work of the south building at FAMBRO property being performed by the Authority's Property Management group instead of the Contractor. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
48 CP 1 HSR 13-06 330 5/26/2020 Tutor Perini/Zachry/Parsons Additional Scope Temporary Relocation of Herndon Yard Materials and Fencing for Fresno Metropolitan Flood Control District Construction Activities $422,860.72 This is a change to a contract for the construction services in the Central Valley. The reason for the change is to compensate the Contractor to relocate portions of the Contractor's Herndon storage yard and fencing in order to accommodate a 35-inch temporary construction easement for Fresno Metropolitan Flood Control District to construct a new drain from Golden State Boulevard to Basin EH per Authority requests. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
49 CP 1 HSR 13-06 329 5/26/2020 Tutor Perini/Zachry/Parsons Budget Adjustment Increase the Amount of the Construction Contract Work Provisional Sum $500,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to increase the amount of Construction Contract Work "Provisional Sums" as defined in the Contract to compensate the Contractor for Construction Contract Work. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
50 CP 1 HSR 13-06 328 5/26/2020 Tutor Perini/Zachry/Parsons Budget Adjustment Increase the Amount of the Utility Provisional Sum $2,500,000.00 This is a change to a contract for design and construction services for the Central Valley. The reason for the change is to increase the amount of the Utility "Provisional Sums" as defined by the Contract to compensate the Contractor for utility work. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
51 CP 1 HSR 13-06 327 5/26/2020 Tutor Perini/Zachry/Parsons Other FB-10-0233 Credit for Additional Demolition and Building Board-up on Excess Land ($16,707.10) This is a change to a contract for construction services in the Central Valley. The reason for the change is to credit the Authority for demolition work that was not performed and compensate the Contractor for incurred costs to board-up two buildings and perform asbestos testing in one of the buildings at parcel FB-10-0233. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
52 CP 1 HSR 13-06 321 5/26/2020 Tutor Perini/Zachry/Parsons Third party Requirements Belmont Switch 60% Revisions - Design $30,187.00 This is a change to a contract for design services in the Central Valley. The reason for this change is to compensate the Contractor for the design costs for revising the vertical alignment of Union Pacific Rail Road track 731 per design review comments to the 60% design of the Belmont Switch Relocation Package. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
53 CP 1 HSR 13-06 319 5/26/2020 Tutor Perini/Zachry/Parsons Third party Improvements Painting of Overhead Sign Structure at SR-180 - Construction $7,799.00 This is a change to a contract for construction services in the Central Valley. The reason for this change is to compensate the Contractor for painting an overhead sign structure at SR-180 as requested by Caltrans. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
54 CP 1 HSR 13-06 313 5/26/2020 Tutor Perini/Zachry/Parsons Third party Improvements Reinforced Concrete Pipe Casing or Restrained Joints for Union Pacific Railroad - Construction $261,880.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for construction costs for the installation of restrained joints on drainage pipes at eleven locations as required by Union Pacific Rail Road and directed by the Authority via Directive Letter 0171 R1. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
55 CP 1 HSR 13-06 309 5/26/2020 Tutor Perini/Zachry/Parsons Additional Scope Caltrans 2-Mile Section - Design $1,000,000.00 This is a change to a contract for design in the Central Valley. The reason for the change is for the advanced payment towards completion of the design of the Caltrans 2-mile guide way portion along SR-99 which was originally excluded from the Contract. Elias Mahfoud - Director of Design and Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
56 CP 1 HSR 13-06 303 5/26/2020 Tutor Perini/Zachry/Parsons Third party Improvements California Department of Fish and Wildlife Addition of Wildlife Crossings - Design $409,313.82 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the design of five Wildlife Crossings required by the California Department of Fish and Wildlife. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
57 CP 1 HSR 13-06 312 5/21/2020 Tutor Perini/Zachry/Parsons Design Revisions Intersection of West Avenue and Weber Avenue - Design $184,655.27 This is a change to a contract for design services in the Central Valley. The reason for the change to compensate the Contractor to design a controlled intersection of West and Weber Avenues that will provide a traffic signal in lieu of a roundabout within the existing City of Fresno Right of Way based on projected traffic flow data provided by High Speed Train and analyzed by the Contractor. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
58 CP 1 HSR 13-06 310 5/21/2020 Tutor Perini/Zachry/Parsons Design Revisions Golden State Boulevard Roadway City of Fresno Deal Points - Design $528,882.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for additional design to incorporate all changes pertaining to Golden State Boulevard between Ashlan and Herndon Avenues. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
59 CP 1 HSR 13-06 302 5/21/2020 Tutor Perini/Zachry/Parsons Additional Scope Design Impacts by Fresno Metropolitan Flood Control District at Multiple Locations $483,580.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for design impacts caused by Fresno Metropolitan Flood Control District request for additional submittals outside of the Master Agreement between the periods of March 3, 2019 to June 4, 2019. This is a pass-through claim for Blair Church and Flynn Consulting Engineers and respective Contractor administrative changes for processing submittals for impacted design packages. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
60 CP 1 HSR 13-06 301 5/21/2020 Tutor Perini/Zachry/Parsons Design Revisions City Of Fresno Water Line South of Shaw Avenue Full Length Jack & Bore Installation $126,296.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for all labor, material and equipment to perform the additional scope of full length jack & bore installation work for the City Of Fresno water line under Golden State Boulevard. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
61 CP 1 HSR 13-06 295 5/21/2020 Tutor Perini/Zachry/Parsons Third party Improvements DL-00174 Design Refinement for PG&E E1-189 (Shaw Avenue) - Design only $65,970.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the redesign of the Comcast line relocation under the High Speed Rail Right Of Way at Shaw Avenue as a result of the redesign of PG&E conflict E-1-189 per Directive Letter 0174. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
62 CP 1 HSR 13-06 294 5/21/2020 Tutor Perini/Zachry/Parsons Third party Improvements Design Refinement of Comcast at Mckinley Avenue due to PG&E E1-025 Relocation $65,970.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the redesign of the Comcast utility line due to the relocation of PG&E conflict E1-025 at McKinley Avenue. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
63 CP 1 HSR 13-06 283 5/21/2020 Tutor Perini/Zachry/Parsons Design Revisions Comcast DP T2-010 (Florence Avenue) DL-174 $49,500.00 This is a change to a contract for design services in the Central Valley. The reason for this change is to compensate the Contractor for additional design cost to relocate a Comcast Utility Telecom line (T2-010) at Florence Avenue to avoid additional design variance from Union Pacific Rail Road per Directive Letter 0174. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
64 CP 1 HSR 13-06 280 5/21/2020 Tutor Perini/Zachry/Parsons Design Revisions Comcast DP T2-024 California & Cherry Avenue Crossing Redesign $81,333.00 This is a change to a contract for design services in the Central Valley. The reason for the change is for the redesign costs of the relocations for Comcast utility T2-024 crossing at California and Cherry Avenues to bring them in line with Union Pacific Railroad standards and avoid additional design variance. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
65 CP 1 HSR 13-06 279 5/21/2020 Tutor Perini/Zachry/Parsons Design Revisions Tuolumne Basin Redesign due to Hazardous Material, Directive Letter 180 - Design $32,199.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to execute Authority Directive Letter 0180 in which the Contractor was directed to redesign two retention basins located in contaminated soil along G Street with a temporary 10-year High Density Polyethylene impermeable lining to prevent storm water from infiltrating through contaminated soil and potentially polluting groundwater. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
66 CP 1 HSR 13-06 318 5/12/2020 Tutor Perini/Zachry/Parsons Third party Improvements Level 3 Line T3-14 Conflict with Avenue 15 Abutment 3 Foundation $32,386.51 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the workaround in which the existing Level 3 line at Avenue 15 conflicts with the excavation of Abutment 3 foundation. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
67 CP 1 HSR 13-06 316 5/12/2020 Tutor Perini/Zachry/Parsons Additional Scope PCO 0864 DL 0175 Additional Scope Items (Elevated Structures & Trenches) - Design only $1,000,000.00 This is a change to a contract for design services in the Central Valley. The reason for the change is for the advanced payment towards the completion of the design of four additional scope items in connection to Type 1 elevated structures, trenches and cut and cover sections as identified in Directive Letter 0175, clarified at the scoping meeting held on 1/9/2020 and as documented in meeting minutes. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
68 CP 1 HSR 13-06 315 5/12/2020 Tutor Perini/Zachry/Parsons Additional Scope Fresno Trench Storm Drain Workaround - Construction $106,999.06 This is a change to a contract for construction services in the Central Valley. The reason for the change compensates the Contractor for the construction of the temporary connection between the scuppers on SR-180 and the existing storm drain line running in the Fresno Trench into Fresno Metropolitan Flood Control District systems to dispose runoff water from the overhead highway systems as mandated by Caltrans. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
69 CP 1 HSR 13-06 314 5/12/2020 Tutor Perini/Zachry/Parsons Other Reimbursement for Right Of Way Easement from Parallamo LLC at Mono Street $27,294.92 This is a change to a contract for construction services in the Central Valley. The reason for the change is to reimburse the Contractor for cost to obtain the Right Of Way easement from Parallamo LLC at Mono Street. The Authority directed the Contractor to make a one-time payment to Parallamo LLC in order to dedicate parcel FB-10-0170-001 to the City of Fresno for roadway purposes. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
70 CP 1 HSR 13-06 48.4 5/7/2020 Tutor Perini/Zachry/Parsons Administrative Additional Supplemental Funding for Excluded Third Party Provisional Sum $19,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the additional supplemental funding is to compensate the contractor to manage and subcontract all direct services required for the relocation of PG&E and AT&T Excluded Third Party Utilities. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
71 CP 1 HSR 13-06 308 5/6/2020 Tutor Perini/Zachry/Parsons Third party Improvements Westside Shoofly Modifications - Trackwork Material and Installation Only $1,646,984.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for a portion of work associated with the construction of the Westside Shoofly and to proceed with procurement and installation of all track material necessary to construct tracks TK# 114-SH, 115-SH, 114-SH(Final), 115-SH(Final) and 736(Final). Elias Mahfoud - Director of Design and Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
72 CP 1 HSR 13-06 290 4/30/2020 Tutor Perini/Zachry/Parsons Design Revisions Directive Letter 0171 R1 Reinforced Concrete Pipe Casing or Restrained Joints $340,195.34 This is a change to a contract for design services in the Central Valley. The reason for this change is for the design modification required by Union Pacific Rail Road due to the change to their design and construction standards which require solutions to protect the railroad Right of Way against leakage from storm and sewer applications installed in Union Pacific Rail Road right of way within CP1 project limits per Directive Letter 0171 R1 (11 locations). Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
73 CP 1 HSR 13-06 287 4/30/2020 Tutor Perini/Zachry/Parsons Third party Improvements Kern and Mono Cul-de-Sacs - Design $136,659.97 This is a change to a contract for design services in the Central Valley. The reason for this change is to compensate the Contractor for the design efforts to reconstruct both Kern and Mono Street terminations as standard Cul-de-Sacs with sidewalks for local residential streets as specified in this Change Order. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
74 CP 1 HSR 13-06 317 4/29/2020 Tutor Perini/Zachry/Parsons Third party Improvements Road 27 Fiber Optic Relocation for Level 3 - Construction $2,312,446.85 This is a change to a contract for construction services in the Central Valley. The reason for this change is to compensate the Contractor to relocate Level 3 line at Road 27 in accordance with Directive Letter 0137 R2. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
75 CP 1 HSR 13-06 311 4/29/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Under Track Conduits, Changes to Design Criteria - Design $116,240.61 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the design services necessary to incorporate all revisions to the design criteria as defined in the Design Criteria Manual for track system conduits and as modified per Directive Letter 0141. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
76 CP 1 HSR 13-06 289 4/29/2020 Tutor Perini/Zachry/Parsons Design Revisions Merced Sewer Realignment - Design $16,315.33 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the re-design of the sewer line that runs underneath the high-speed train right of way at Merced Street due to a change of construction sequence which resulted in a requirement to modify the City of Fresno sewer and other impacted designs. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
77 CP 1 HSR 13-06 278 4/29/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Church Avenue Basin Redesign due to Hazardous Material - Design $42,737.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the redesign efforts associated with Directive Letter 0182 in which the Contractor was directed to relocate the retention basins from contaminated soil along Railroad Avenue, north of Church Avenue and include an impermeable concrete lining to prevent storm water from infiltrating through contaminated soil and potentially impacting groundwater. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
78 CP 1 HSR 13-06 284 R1 4/27/2020 Tutor Perini/Zachry/Parsons Additional Scope Burlington Northern Santa Fe Railway Access Plan - Design $305,592.36 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor to prepare a Burlington Northern Santa Fe Railway Access Plan, inclusive of designing physical improvements for the purpose of providing access as was stipulated in the Authority/ Burlington Northern Santa Fe Railway "Relocation and Construction Agreement" dated 12/10/16. Directive Letter 135 authorized the Contractor to proceed with aforementioned scope of work. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
79 CP 1 HSR 13-06 70.01 4/27/2020 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Fresno Street Underpass UPRR Utilities - Design $141,348.31 This is a change to a contract for design services in the Central Valley. The reason for the change is for the supplementary design costs for the relocation of existing underground utilities (Level 3 and Sprint) in conflict with future shoring for the new grade separation of the Union Pacific Rail Road bridge over Fresno Street. The original CO 00070 excluded all utility design work in it's scope. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
80 CP 1 HSR 13-06 299 4/23/2020 Tutor Perini/Zachry/Parsons Third party Improvements Road 27 Waterline Replacement for Madera Valley Water Company $1,773,899.40 This is a change to a contract for construction services in the Central Valley. The reason for the change is for the additional costs to relocate the Madera Valley Water Company water line at Road 27 as part of the roadway improvements required to allow the reopening of Road 27 for vehicular and pedestrian use in the North Extension segment. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
81 CP 1 HSR 13-06 306 4/8/2020 Tutor Perini/Zachry/Parsons Additional Scope Additional shoring at Fresno Trench Headwall Construction at Westside Wye South Leg - Construction $73,033.36 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the additional construction cost for the vertical shoring to construct the Fresno Metropolitan Flood Control District Headwalls on the Westside Wye south leg. Work was performed on Time & Material basis. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
82 CP 1 HSR 13-06 298 4/8/2020 Tutor Perini/Zachry/Parsons Additional Scope Import from Authority Borrow Site Avenue 7 Guideway Construction $4,937,881.74 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for all labor, material and equipment costs necessary to excavate, load, haul and provide a rough grade of the basin slopes without finished work, as well as supporting operations such as traffic control, securing the cut sites with temporary fence, storm water pollution control requirements to be installed as needed and agreed upon. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
83 CP 1 HSR 13-06 297 4/8/2020 Tutor Perini/Zachry/Parsons Additional Scope Topographic Survey for Caltrans 99 Section $78,459.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is for the Contractor to conduct a topographic survey on a 2-mile section within the high-speed rail Construction Package 1 project known as "Caltrans Project Section." Scope includes additional cost for the effort to import and process survey data into MicroStation. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
84 CP 1 HSR 13-06 307 3/31/2020 Tutor Perini/Zachry/Parsons Design Revisions California Department of Fish and Wildlife Addition of Wildlife Crossings $3,517,264.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the construction of five Wildlife Crossings at locations identified in this Change Order. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
85 CP 1 HSR 13-06 305 3/31/2020 Tutor Perini/Zachry/Parsons Design Revisions Intrusion Protection Barrier Addition and Revision - Design $13,898,322.64 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to compensate the Contractor for all additional design effort necessary to incorporate all required revisions to the Intrusion Protection Barrier. It also includes compensation for Extra Work as stipulated in this Change Order in a Time & Material basis per Contract. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
86 CP 1 HSR 13-06 304 3/31/2020 Tutor Perini/Zachry/Parsons Other Madera Irrigation District Lateral 6.2 Box Culvert Divrsion $1,218,221.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is for the construction of the canal diversion for the Madera Irrigation District Lateral 6.2 to allow the completion of the proposed Box Culvert outside of the normal non-irrigation season. The diversion work was accelerated to be completed prior to the start of the next irrigation season, February 22, 2021. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
87 CP 1 HSR 13-06 296 3/19/2020 Tutor Perini/Zachry/Parsons Right-of-Way (ROW) Related North Extension Security Cost Through April 30, 2017 $62,845.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for additional security services cost for thirty-six (36) North Extension parcels from October 16, 2016 through April 30, 2017 that were not able to be demolished due to not being environmentally permitted. This service was not included in Change Orders 00089, 00240 & 00234. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
88 CP 1 HSR 13-06 291 3/19/2020 Tutor Perini/Zachry/Parsons Right-of-Way (ROW) Related PG&E Future Franchise Shape File Submission $501,727.00 This is a change to a contract for design services in the Central Valley. The reason for the change is for Contractor to provide .DGN files (shape files) for all PG&E facilities requiring interim rights in future franchise Right Of Way. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
89 CP 1 HSR 13-06 233.3 3/19/2020 Tutor Perini/Zachry/Parsons Right-of-Way (ROW) Related Deposit and Reimbursement for Madera Valley Water Company $5,459.00 This is a change to a contract for design services in the Central Valley. The reason for the change is for the initial deposit and reimbursement of funds for Madera Valley Water Company (MVWC) design review services per Authority request. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
90 CP 1 HSR 13-06 281 2/27/2020 Tutor Perini/Zachry/Parsons Differing Site Conditions Issue Resolution - Potential Change Orders 374, 518 and 543 $21,260.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the Settlement Agreement between the Authority and Contractor for the following Potential Change Orders: 0374, 0518 and 0543. This Change Order compensates the Contractor for providing all services, labor, material, equipment, tools and incidentals including all markups. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
91 CP 1 HSR 13-06 89.01 2/27/2020 Tutor Perini/Zachry/Parsons Scope Changes North Extension Revised Alignment $33,107,436.93 This is a change to a contract for construction services in the Central Valley. The reason for the change is to supplement Change Order 00089, North Extension Design and Construction executed on April 8, 2016, in order to compensate the Contractor for the supplemental construction costs on the North Extension. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
92 CP 1 HSR 13-06 228 2/26/2020 Tutor Perini/Zachry/Parsons Design Criteria/Specification Change Settlement of Cost for Mechanically Stabilized Earth to Cast In Place $35,345,236.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to settle all cost related to conversion of 15 structures from Mechanically Stabilized Earth to Cast-In-Place concrete abutments and the Burlington North Santa Fe wing walls to protect Mechanically Stabilized Earth walls. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
93 CP 1 HSR 13-06 288 2/10/2020 Tutor Perini/Zachry/Parsons Third party Improvements Fresno Street Road Classification Change $6,265.67 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for design efforts to change the road classification at Fresno Street from Collector to Arterial. Change include revising plans to reflect the new classification and thickness of pavement. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
94 CP 1 HSR 13-06 231.02 2/4/2020 Tutor Perini/Zachry/Parsons Impacts due to relocations of facilities owned by Third Parties City Of Fresno Utility Relocation Herndon to Carnegie $3,197,461.00 This is a change to a contract for construction services in the Central Valley. The reason for this change is to compensate the Contractor to construct water and sewer mains at Golden State Boulevard between Herndon and Carnegie Avenues per City of Fresno plans. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
95 CP 1 HSR 13-06 252.01 1/31/2020 Tutor Perini/Zachry/Parsons Impacts due to relocations of facilities owned by Third Parties Parcels MF-20-0901, 0902, 0903 Irrigation Line Supply Change $213,513.94 This is a change to a contract for construction services in the Central Valley. The reason for the change is to provide supplemental compensation to the Contractor for construction to install six (6) 24-inch casings instead of the initial three (3) 36-inch casings at parcels MF-20-0901, 0902 and 0903. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
96 CP 1 HSR 13-06 286 1/17/2020 Tutor Perini/Zachry/Parsons Scope Changes Authority Additional Bizhub C558 Copiers $41,421.07 This is a change to a contract for project management services in the Central Valley. The reason for the change is to authorize a 48-month lease for three additional Bizhub C558 copiers from Caltronics for use by Authority during the CP1 Project. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
97 CP 1 HSR 13-06 282 1/17/2020 Tutor Perini/Zachry/Parsons Impacts due to relocations of facilities owned by Third Parties Calfifornia and Cherry Water Relocation $52,488.91 This is a change to a contract for design services in the Central Valley. The reason for this change is to redesign City of Fresno waterline as part of the California and Cherry water line relocation design packages. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
98 CP 1 HSR 13-06 285 1/8/2020 Tutor Perini/Zachry/Parsons Impacts due to relocations of facilities owned by Third Parties Third Party Property Rights Verification $5,956,386.19 This is a change to a contract for construction administration services in the Central Valley. The reason for the change is to compensate the Contractor for providing general administration services in support of Authority Right-of-Way engineering. Compensation covers all work that has been completed or is "In progress" as of the agreed cut-off date of July 26, 2019. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
99 CP 1 HSR 13-06 133.03 1/8/2020 Tutor Perini/Zachry/Parsons Scope Changes Avenue 12 High Speed Train Overhead Structure - Release For Construction to Aproved For Construction $2,306,730.21 This is a change in contract for design and construction services in the Central Valley. The reason for the change is to compensate the Contractor for the change in scope of work between Release For Construction to Aproved For Construction drawings at Avenue 12 High Speed Train Overcrossing. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
100 CP 1 HSR 13-06 272 12/20/2019 Tutor Perini/Zachry/Parsons Differing Site Conditions Tank and Well Removal $24,514.84 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the removal of septic tank and two wells located in the right of way of parcel FB-10-0503. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
101 CP 1 HSR 13-06 165.1 12/6/2019 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Solid Barrier on Type 2 Overhead - Design $37,900.43 This is a change to a contract for design services in the Central Valley. The reason for the change is for additional redesign efforts to change the Overhead Structure Barrier design to a rigid traffic barrier with Access Deterrent Fence (AD) on all roadway and pedestrian overhead structures per Directive Letter DL-084 R3. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
102 CP 1 HSR 13-06 5.1 11/27/2019 Tutor Perini/Zachry/Parsons Administrative Local and Long Distance Phone Charges $50,410.40 This is a change to a contract for construction management services in the Central Valley. The reason for this change is for the reimbursement of additional local and long distance phone calls from April 15, 2018 to September 15, 2019 and includes projected costs through the end of the Contract. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
103 CP 1 HSR 13-06 277 11/22/2019 Tutor Perini/Zachry/Parsons Environmental Westside Wye Shoofly Dirt Contamination Testing $14,970.81 This is a change to a contract for materials testing in the Central Valley. The reason for the change is to compensate the Contractor to test and report on potential contaminated materials at the Westside Wye Shoofly, as well as recommendations from a registered geologist. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
104 CP 1 HSR 13-06 274 11/22/2019 Tutor Perini/Zachry/Parsons Third-Party Related Left Turn Channelization at Golden State Boulevard - Construction Only $886,440.91 This is a change to a contract for construction services in the Central Valley. The reason for this change is for the construction of the median opening and left turn channelization for southbound Golden State Boulevard, south of East Avenue, for California Legal Truck access to the relocated main driveway of Weir Floway (parcel FB-10-0220). The work is based on plan set for City of Fresno Public Works Department Weir Floway Median Opening Plans C-001-WFC. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
105 CP 1 HSR 13-06 177.1 11/22/2019 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Transfer of Funds Contingency to Construction Contract Work $500,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to increase the amount of "Provisional Sums" as defined in the Contract special provisions to compensate the Contractor for Construction Contract Work (CCW). Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
106 CP 1 HSR 13-06 275 11/15/2019 Tutor Perini/Zachry/Parsons Third-Party Related Mono Street - San Joaquin Valley Railroad Track 118 Materi $110,320.59 This is a change to a contract for construction services in the Central Valley. The reason for this change is for the procurement and delivery of track, crossing panels and stockpiling of ballast rock necessary to allow Union Pacific Railroad to raise the existing San Joaquin Valley Railroad Spur Track #118 at the Mono Street at-grade crossing. (Installation of materials to be performed by Union Pacific Railroad) Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
107 CP 1 HSR 13-06 273 11/15/2019 Tutor Perini/Zachry/Parsons Third-Party Related McKinley Avenue Storm Drain United Parcel Service (UPS) Tie-In $13,717.08 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design a new required storm drain manhole within the vicinity of the proposed Golden State Blvd. and McKinley Ave. near HSR STA 10845+00, per Authority Letter PCM-TPZP-04005. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
108 CP 1 HSR 13-06 87.3 11/8/2019 Tutor Perini/Zachry/Parsons Third-Party Related Top Down Construction at State Route 180 Supplemental 3 $1,794,094.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for additional unforeseen Third Party scope of work to execute Alternate Technical Concept #1A (top/down construction methodology) at Fresno Trench construction beneath highway State Route 180. This Change Order is a supplement to CO 00087 dated April 5,2016. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
109 CP 1 HSR 13-06 271 10/25/2019 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Emergency Closure State Route 180 West Bound $12,079.76 This is a change to a contract for construction services in the Central Valley. The reason for this change is to compensate the Contractor for completing an emergency closure of the SR-180 West bound #3 lane at the Fulton Street onramp for the purpose of installing K-Rail protection with crash barriers on June 19, 2019. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
110 CP 1 HSR 13-06 265.1 10/25/2019 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Union Pacific Railroad Homeless Encampment Cleanup $500,000.00 This is a change to a contract for construction services in the Central Valley. The reason for this change is to add funds to original CO 00265. The original amount including the supplemental is hereby increased by $500,000.00, from $100,000.00 to $600,000.00, as well as funding for cleanup for a homeless encampment. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
111 CP 1 HSR 13-06 262 10/25/2019 Tutor Perini/Zachry/Parsons Third-Party Related United States Bureau of Reclamation Agreement for Siphon Maintenance $144,920.04 This is a change to a contract for maintenance services in the Central Valley. The reason for this change is to compensate the United States Bureau of Reclamation for the cost involved in maintaining and cleaning proposed new siphon at Madera Irrigation District (MID) facility, Lateral 6.2 in perpetuity. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
112 CP 1 HSR 13-06 266 10/24/2019 Tutor Perini/Zachry/Parsons Right-of-Way (ROW) Related FB-10-0176 Secure Fresno Rescue Mission Structure $2,642.59 This is a change in contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for securing the Fresno Rescue Mission structure on parcel FB-10-0176. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
113 CP 1 HSR 13-06 270 10/22/2019 Tutor Perini/Zachry/Parsons Differing Site Conditions MF-10-0058 Keith's Automotive Sewer Leak $5,061.49 This is a change in contract for construction services in the Central Valley. The reason for the change is to provide compensation to the Contractor for performing sewer investigation work at Keith's Automotive at 5355 North Golden State Boulevard, parcel MF-10-0058, to determine the cause of a sewer leak. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
114 CP 1 HSR 13-06 233.2 10/22/2019 Tutor Perini/Zachry/Parsons Third-Party Related Deposit and Reimbursement for Madera Valley Water Company $5,447.50 This is a change to a contract for design services in the Central Valley. The reason for the change is to provide initial deposit and reimbursement of funds for Madera Valley Water Company per Authority request for agreement review services. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
115 CP 1 HSR 13-06 260 10/10/2019 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Herndon Avenue - Construction $76,583,809.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is compensate the Contractor for additional construction costs as a result of the approval of Alternate Technical Concept #8 for the Herndon Ave area development. Joe Hedges - Chief Operating Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
116 CP 1 HSR 13-06 149.1 10/4/2019 Tutor Perini/Zachry/Parsons Utility Relocation Credit from Change Order 00149 ($3,494.75) This is a change to a contract for construction services in the Central Valley. The reason for this change is to provide a credit to the Authority for the difference equivalent to -$3,494.75 due to a summation error in the Subcontractor's bid proposal for Change Order 00149, dated March 9, 2017. John Neri - Senior Contract Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
117 CP 1 HSR 13-06 265 8/19/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UPRR Safety and Security $100,000.00 This is a change to the contract for design and construction services in the Central Valley. This change order allows the contractor to complete activities within the Union Pacific Railroad right of way. John Neri - Senior Contract Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
118 CP 1 HSR 13-06 264 8/6/2019 Tutor Perini / Zachry/Parsons Utility Relocation Sprint Utility Work Subtask 1.05 $727,099.61 This is a change to the contract for design and construction services in the Central Valley. This change order allows for completion of the relocation of telecommunications facilities. John Neri - Senior Contract Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
119 CP 1 HSR 13-06 261 8/6/2019 Tutor Perini / Zachry/Parsons Utility Relocation Switch Relo for UPRR Siding 729 $102,271.87 This is a change to the contract for design and construction services in the Central Valley. This change order designs the relocation of Union Pacific Railroad infrastructure to enable subsequent relocation of utilities. John Neri - Senior Contract Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
120 CP 1 HSR 13-06 99.2 8/6/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Completion Deadline Ext / Resolution $126,000,000.00 This is a change to the contract for design and construction services in the Central Valley. The change order is to resolve all delays, claims and disputes from January 1, 2016 through May 1, 2019 and revise the date to complete the work to August 31, 2021. Joe Hedges - Chief Operating Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
121 CP 1 HSR 13-06 88.8 8/6/2019 Tutor Perini / Zachry/Parsons Environmental Environmental Staffing - Supplemental No 8 $9,000,000.00 This is a change to a contract for design and construction services in the Central Valley. This change order continues to provide environmental services to ensure the future high-speed rail system work complies with environmental requirements. William Grimsley - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
122 CP 1 HSR 13-06 48.3 8/5/2019 Tutor Perini / Zachry/Parsons Utility Relocation PG&E & AT&T Facilities Relocation S3 $19,000,000.00 This is a change to the contract for design and construction services in the Central Valley. The change order enables utilities of PG&E and AT&T to be moved out of the way of the future high-speed rail system. Joe Hedges - Chief Operating Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
123 CP 1 HSR 13-06 263 7/31/2019 Tutor Perini / Zachry/Parsons Utility Relocation Utility Relocations to Accommodate UPRR - CCS - Sprint - Construction $77,064.23 This is a change to a contract for design and construction services in the Central Valley. The reason for the change order is for Sprint, a telecommunications company, to inspect, monitor, protect and verify if their services will need to be moved for the high-speed rail system. This work is being coordinated by the general contractor in Fresno responsible for designing and constructing the future system. John Neri - Senior Contract Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
124 CP 1 HSR 13-06 231.1 7/12/2019 Tutor Perini / Zachry/Parsons Utility Relocation City of Fresno Utility Relocations Package 2 and 3 $4,221,684.30 This is a change to a contract for design and construction services in the Central Valley. The reason for the change order is for the City of Fresno to move its services out of the way of future high-speed rail system. The work is being coordinated by the general contractor in Fresno responsible for designing and constructing the future system. Joe Hedges - Chief Operating Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
125 CP 1 HSR 13-06 258 7/11/2019 Tutor Perini / Zachry/Parsons Third-party Related HSR CP1 - JMA Railroad Review and Consultation $88,755.50 This is a change to a contract for design and construction services in the Central Valley. The reason for the change order is to expedite all railroad related submittals and improve overall communication between Union Pacific Railroad, San Joaquin Valley Railroad, Tutor/Perini/Zachry/Parsons JV and the Authority. John Neri - Senior Contract Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
126 CP 1 HSR 13-06 48.2 7/11/2019 Tutor Perini/Zachry/Parsons Utility Relocation PG&E & AT&T Facilities Relocation S2 $5,000,000.00 This is a change to the contract for design and construction services in the Central Valley. This Supplemental change order increases the amount of the "Provisional Sums" as defined in Book 2, Part A, Subpart 2, Special Provisional, Section 6 Provisional Sums to compensate the contractor to manage and subcontract all direct services required for the relocation of Excluded Third Party Utilities. William Grimsley - Director of Design and Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
127 CP 1 HSR 13-06 236 6/24/2019 Tutor Perini/Zachry/Parsons Third Party Requirements Reimbursement to City of Fresno for remaining project work $1,817,000.00 This is a change to a contract for design services in the Central Valley. The reason for the change is for the additional compensation for the required City Of Fresno review fees on all current and anticipated California High-Speed Rail Authority directed changes. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
128 CP 1 HSR 13-06 10.1 6/19/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Weed Abatement - North Ext. CO 00089 $- This is a change to a contract for design and construction services in the Central Valley and authorizes the clearance of weeds, grass, trash and debris from Authority owned properties in an area of construction north of Fresno. The reason for this change is to authorize these clearance activities in an area known as the "Northern Extension", which was added to the construction contract in March, 2016. The original clearance activities authorized for $300,000 in change order 10 did not include the Northern Extension. John Neri, Senior Contract Manager Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
129 CP 1 HSR 13-06 259 6/12/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related MF-20-0948 Two Conc. Slabs Ave 15.5 $4,105.88 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish two concrete slabs at a property acquired by the Authority near Avenue 15 and a half in Madera County. John Neri, Senior Contract Manager Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
130 CP 1 HSR 13-06 88.7 6/7/2019 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $1,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to provide environmental services to ensure the future high-speed rail system work complies with environmental requirements. John Neri, Senior Contract Manager Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
131 CP 1 HSR 13-06 257 5/21/2019 Tutor Perini / Zachry/Parsons Utility Relocation UNI: Fresno Bridge Relo Costs DL0078 $87,165.44 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for Sprint, a telecommunications company, to move its services out of the way of the future high-speed rail system. This work is coordinated by the general contractor in Fresno responsible for designing and constructing the future system. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
132 CP 1 HSR 13-06 254 5/13/2019 Tutor Perini / Zachry/Parsons Utility Relocation UNI: ATT Wrkarnd Carnegie & Cornelia $39,241.64 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to temporarily move AT&T facilities and a fire hydrant until they can be installed in their permanent locations to enable the re-alignment of Golden State Boulevard in Fresno. Joe Hedges - Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
133 CP 1 HSR 13-06 235 5/9/2019 Tutor Perini / Zachry/Parsons Third-party Related Fresno Trench IPB - Construction $8,350,000.00 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to do construction work in the Fresno trench associated with the new standards required to keep conventional trains out of the future high-speed rail system. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
134 CP 1 HSR 13-06 255 5/7/2019 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: SR-180 S Slope Unknwn Obstruct $114,486.53 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove an unexpected obstruction found during the work at the State Route 180. Joe Hedges - Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
135 CP 1 HSR 13-06 253 5/2/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: MF-20-0935 Irr & Com Ln Ave 12 $83,876.44 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to install an irrigation pipeline and a communication line across Avenue 12, to complete property acquisition requirements. Joe Hedges - Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
136 CP 1 HSR 13-06 252 5/2/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: MF-20-0901, 0902, 0903 Irrig Ln $243,225.06 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to install three 36-inch irrigation casings as part of the construction work to enable the future high-speed rail system to be built. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
137 CP 1 HSR 13-06 233.1 5/2/2019 Tutor Perini / Zachry/Parsons Utility Relocation UNI: MVWC Waterline Relocation Rd 27 $2,179.00 This is a change to a contract for design and construction services in the Central Valley. The change is additional to change 233 and is for the inclusion of Federal flow down conditions into work performed by Giersch & Associates related to moving the water line owned by the Madera Valley Water Company. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
138 CP 1 HSR 13-06 250 4/24/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: MF-20-0917 Irrgtn Pipe & Condt $239,060.74 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to install irrigation pipelines and conduits in three locations, to complete property acquisition requirements. Joe Hedges - Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
139 CP 1 HSR 13-06 248 4/24/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: FB-10-0233 Additional Demo $20,814.14 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete additional demolition of a building on an Authority-owned property at South Railroad Avenue. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
140 CP 1 HSR 13-06 249 4/17/2019 Tutor Perini / Zachry/Parsons Third-party Related UNI: Basin EE Rcycld Irrigtn Pmp Mod $17,884.82 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional design to an irrigation water pump. This includes replacing the power and control cables and relocating the irrigation line. William Grimsley - Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
141 CP 1 HSR 13-06 246 4/17/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: FB-10-0256 South Bldg Addl Demo $13,147.48 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete additional demolition of a building on an Authority-owned property at South Cedar Avenue. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
142 CP 1 HSR 13-06 244 4/17/2019 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: Rdside Barriers at OC Deal Pts $31,265.62 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design modifications related to structures and roadways at Central, Church, Tuolumne, Belmont, Olive, McKinley, and Shaw in the City of Fresno. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
143 CP 1 HSR 13-06 239 4/15/2019 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: North Ext Rescoping 2 - Design $10,649,178.47 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete additional design work in the area known as the "Northern Extension", north of Fresno. This design work will move third party facilities and utilities out of the way of the future high-speed rail system. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
144 CP 1 HSR 13-06 242 4/11/2019 Tutor Perini / Zachry/Parsons Utility Relocation UNI: American Ave Facility Plan $224,384.33 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design modifications to the new locations of PG&E and Comcast facilities at American Avenue. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
145 CP 1 HSR 13-06 247 4/9/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: MF-10-0083 Addtl. Mobilization $24,015.30 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to re-start construction work at a specific property at West Shaw Avenue due to delays in receiving correct data on a fire service line. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
146 CP 1 HSR 13-06 243 4/4/2019 Tutor Perini / Zachry/Parsons Third-party Related UNI: Dry Creek Canal Culvert Redsgn $51,641.30 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design modifications to the Dry Creek Canal culvert, over which the future high-speed rail system will travel. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
147 CP 1 HSR 13-06 241 4/4/2019 Tutor Perini / Zachry/Parsons Third-party Related UNI: McKinley & Basin EE Refinements $552,350.18 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete additional design work related to road way work at McKinley Avenue in Fresno and a nearby drainage basin. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
148 CP 1 HSR 13-06 240 4/4/2019 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: North Ext Supplement 1 - Design $3,573,973.79 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete additional design work in the area known as the "Northern Extension", north of Fresno. This additional design work was triggered by changes initiated by the Authority to the final alignment of the future high-speed rail system. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
149 CP 1 HSR 13-06 237 4/4/2019 Tutor Perini / Zachry/Parsons Third-party Related UNI: Church Ave Overcrossing Sunland $285,430.57 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to complete additional design work at Church and Sunland Avenues in Fresno. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
150 CP 1 HSR 13-06 234 4/4/2019 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: North Ext Supplement 2 - Design $1,142,390.46 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete additional design work in the area known as the "Northern Extension", north of Fresno. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
151 CP 1 HSR 13-06 232 4/4/2019 Tutor Perini / Zachry/Parsons Utility Relocation UNI: AT&T Workaround for Belmont Ave $1,032,551.05 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design work arounds to address delays in AT&T design and construction work of new facility locations. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
152 CP 1 HSR 13-06 188 4/4/2019 Tutor Perini / Zachry/Parsons Third-party Related UNI: UPRR Bridge AREMA Ver. Switch $36,394.49 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is new American Railway Engineering and Maintenance-of-Way Association (AREMA) standards. These standards triggered the re-design of certain future high-speed rail system work. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
153 CP 1 HSR 13-06 122 4/4/2019 Tutor Perini / Zachry/Parsons Third-party Related UNI: Lighting Mod due to UPRR $23,731.75 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is new lighting requirements required by the Union Pacific Rail Road at Blemont and McKinley Avenues in Fresno. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
154 CP 1 HSR 13-06 245 4/3/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: FB-10-0216 Demo Stages Asphalt ($10,006.36) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is a removal of demolition scope from the construction contractor. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
155 CP 1 HSR 13-06 238 4/3/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: FB-10-0256 Demo Credit Fambro ($7,437.94) This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to receive a credit to the Authority from the contractor for a billing error. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
156 CP 1 HSR 13-06 229 2/1/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: GSB Realignment Demo Credit ($975,774.47) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the demolition requirements on a number of Authority-owned properties and to receive a net credit to the Authority from the contractor. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
157 CP 1 HSR 13-06 219 1/17/2019 Tutor Perini / Zachry/Parsons Third-party Related UNI: Kinder Morgan Valve Relo Herndn $569,699.95 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move a Kinder Morgan 12" valve at Herndon Avenue to enable construction of the future high-speed rail system. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
158 CP 1 HSR 13-06 233 1/15/2019 Tutor Perini / Zachry/Parsons Utility Relocation UNI: MVWC Waterline Relocation Rd 27 $149,578.49 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to develop the design to move a water line owned by the Madera Valley Water Company out of the way of the future high-speed rail system. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
159 CP 1 HSR 13-06 133 S2 12/10/2018 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: Ave 12 MSE to CIP Chg - Const. $6,334,334.65 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to incorporate design changes into the construction of Avenue 12. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
160 CP 1 HSR 13-06 225 12/8/2018 Tutor Perini / Zachry/Parsons Utility Relocation UNI: CPUC Conduits Ave 8 & 11 Const. $431,101.80 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to construct conduits and other elements at Avenue 8 and Avenue 11 structures for public utilities. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
161 CP 1 HSR 13-06 6.1 11/26/2018 Tutor Perini / Zachry/Parsons Administrative DRB Expenses - Supplemental $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to increase the amount of funds in Change Order 00006 from $180,000 to $280,000. These funds are used to pay the Authority’s share of Dispute Resolution Board expenses. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
162 CP 1 HSR 13-06 230 10/31/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related FB-10-0219 Remediation Work $308,536.20 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove and dispose of contaminated soils. William Grimsley - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - D-B Oversight Manager
163 CP 1 HSR 13-06 88.6 10/4/2018 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $4,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to provide environmental services to ensure the future high-speed rail system work complies with environmental requirements. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
164 CP 1 HSR 13-06 223 10/2/2018 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications MSE to CIP Abutments at Avenue 7 $2,449,186.70 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to make changes to the bridge at Avenue 7. William Grimsley - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
165 CP 1 HSR 13-06 221 10/2/2018 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Herndon Area Changes - Design $7,942,301.24 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct design related to the alternative designs for the high-speed rail system around Herndon Avenue and related designs to resolve UPRR impacts. Joe Hedges - Cheif Operating Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - D-B Oversight Manager
166 CP 1 HSR 13-06 231 9/18/2018 Tutor Perini / Zachry/Parsons Utility Relocation COF Utility Relocation Changes Part1 $2,343,757.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to meet additional requirements for four locations of water and sewer facilities in the Utility Relocation Cooperative Agreement with the City of Fresno. William Grimsley - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - D-B Oversight Manager
167 CP 1 HSR 13-06 224 9/11/2018 Tutor Perini / Zachry/Parsons Administrative Dispute Review - Executive $- This is a change to a contract for design and construction services in the Central Valley. The reason for this no cost change is to streamline the dispute resolution process. Terry Ogle - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - D-B Oversight Manager
168 CP 1 HSR 13-06 214 8/28/2018 Tutor Perini / Zachry/Parsons Environmental American Avenue Changes $9,497,470.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide a longer bridge over the future high-speed rail system to reach the future high-speed rail maintenance facility. Joe Hedges - Cheif Operating Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - D-B Oversight Manager
169 CP 1 HSR 13-06 222 8/23/2018 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Aesthetic Treatment at Type 1 Struct $1,515,077.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide aesthetic treatment of several future high-speed rail bridges in the Fresno area to make them look consistent. Terry Ogle - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - D-B Oversight Manager
170 CP 1 HSR 13-06 218 8/17/2018 Tutor Perini / Zachry/Parsons Differing Site Conditions FB-10-0235 Unknown Brick Struct Rev $14,489.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay for the contractor to demolish and fill the hole from two unexpected brick structures. These structures are in the way of moving an irrigation line to enable future high-speed rail construction. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Mike Sheffield - DB Oversight Manager
171 CP 1 HSR 13-06 208 7/11/2018 Tutor Perini / Zachry/Parsons Differing Site Conditions SR-180 Phase 2 Differing Site Cond. $16,086.08 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is due to unexpected obstructions that require additional drilling at the tunnel under State Route 180. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
172 CP 1 HSR 13-06 175 S1 6/28/2018 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Flagging And Temp Signal Rd26 Suppl $11,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pave a pedestrian detour route at Club Drive. Steve Milton - Design & Construction Manager Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
173 CP 1 HSR 13-06 216 6/27/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related FB-10-0231 Additional Demolition $51,805.69 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish structures to make way for the future high-speed rail system. Terry Ogle - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
174 CP 1 HSR 13-06 215 6/27/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related PAUC Parichan Farms - Construction $2,466,824.86 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide a crossing under the future high-speed rail system so a property owner can access their property on both sides of the train line. Terry Ogle - Director of Design and Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
175 CP 1 HSR 13-06 213 6/27/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related FB-10-0495 Tulare St. Building PIP $951,400.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to protect the access to a building instead of demolishing the building during construction of the future high-speed rail system. Terry Ogle - Director of Design and Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
176 CP 1 HSR 13-06 48.1 6/11/2018 Tutor Perini / Zachry/Parsons Utility Relocation PG&E & AT&T Facilities Relocation S1 $40,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is provide additional funds for the transfer services from the Authority to the contractor. The transferred services are to manage the design and construction of PG&E and AT&T facilities to move them out of the way of future high-speed rail construction. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Glenn Suitor, D-B Oversight Manager
177 CP 1 HSR 13-06 217 6/7/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related MF-10-0258 Additional Demo $135,662.32 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish structures to make way for the future high-speed rail system. Terry Ogle - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
178 CP 1 HSR 13-06 212 6/7/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related MF-10-0210 Additional Demolition $32,353.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish structures to make way for the future high-speed rail system. Terry Ogle - Director of Design and Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
179 CP 1 HSR 13-06 211 6/7/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related MF-10-0208 and 0209 Additional Demo $57,881.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish structures to make way for the future high-speed rail system. Steve Milton - Design & Construction Manager Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
180 CP 1 HSR 13-06 209 6/7/2018 Tutor Perini / Zachry/Parsons Environmental FB-10-0229 PARC Environmental $44,293.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish an office building to make way for the future high-speed rail system. Terry Ogle - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
181 CP 1 HSR 13-06 201 6/7/2018 Tutor Perini / Zachry/Parsons Third-party Related Kinder Morgan Relocation at McKinley $4,100,988.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design and construct the Kinder Morgan 12 inch petroleum pipeline that is in the way of UPRR’s 3rd track and Centralized Traffic Control improvements. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
182 CP 1 HSR 13-06 210 6/1/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related FB-10-0044-01 Redesign Drainage Sys $27,121.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete redesign work of a drainage system due to a change in right of way availability. Terry Ogle - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
183 CP 1 HSR 13-06 207 5/24/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related CCW FB-10-0001 Additional Demo $43,619.71 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish a building and to make site improvements. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
184 CP 1 HSR 13-06 206 5/24/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related MF-10-0024 6745 N. GSB Add Demo $55,205.02 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish a building and to make site improvements. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
185 CP 1 HSR 13-06 167 5/23/2018 Tutor Perini / Zachry/Parsons Third-party Related Utility Reloc UPRR CTC Sys - Design $244,208.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move utilities due to construction impacts to Union Pacific Railroad Centralized Traffic Control System in various locations. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
186 CP 1 HSR 13-06 70 5/23/2018 Tutor Perini / Zachry/Parsons Third-party Related Fresno St UPRR Bridge Struc - Design $349,138.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to design the Union Pacific Railroad Bridge over Fresno Street. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Glenn Suitor, D-B Oversight Manager
187 CP 1 HSR 13-06 205 5/16/2018 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Painting Fresno Viaduct $80,476.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to apply aesthetic paint to exposed surfaces of the Fresno River Viaduct to make the structure look the same throughout. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
188 CP 1 HSR 13-06 204 5/16/2018 Tutor Perini / Zachry/Parsons Third-party Related Church Ave BNSF & HST OH Structure $176,404.90 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional design at the Church Avenue Grade Separation in Fresno. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
189 CP 1 HSR 13-06 179 5/16/2018 Tutor Perini / Zachry/Parsons Third-party Related Maintain Access to Road 33 at Ave 7 $401,421.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design Avenue 7 overcrossing as a two span bridge instead of a single span bridge and to provide access to Madera County Road 33 west of the future high-speed rail system. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
190 CP 1 HSR 13-06 42.2 5/16/2018 Tutor Perini / Zachry/Parsons Administrative Credit for Addtl Space 1401 Fulton ($2,453.74) This is a change to a contract for design and construction services in the Central Valley. The contractor is leasing office space at 1401 Fulton Street in Fresno to the Authority. A previous change order had provided $50,000 for a five-month lease extension. This change credits the Authority a portion of those costs. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Glenn Suitor, D-B Oversight Manager
191 CP 1 HSR 13-06 200 4/18/2018 Tutor Perini / Zachry/Parsons Third-party Related K. Morgan Relocation - Belmont $2,204,171.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design and construct the Kinder Morgan 12 inch petroleum pipeline that is in the way of the Belmont bridge work. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
192 CP 1 HSR 13-06 197 4/18/2018 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Opaque Solid Test Panels $14,218.00 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is for design and construction of fence test panels. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
193 CP 1 HSR 13-06 7.1 4/18/2018 Tutor Perini / Zachry/Parsons Environmental UNI: CL1/CL2 HazMat Supp1 $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to adjust the Hazardous Waste Removal quantities for the project. Terry Ogle - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Glen Suitor - DB Oversight Manager
194 CP 1 HSR 13-06 199 4/11/2018 Tutor Perini / Zachry/Parsons Third-party Related K. Morgan Relocation - Herndon $5,883,644.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design and construction services to move the Kinder Morgan 12 inch petroleum pipeline that is in the way of the Herndon underpass work. Joe Hedges, Chief Operating Officer Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
195 CP 1 HSR 13-06 88.5 4/11/2018 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $4,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to provide environmental services to ensure the future high-speed rail system work complies with environmental requirements. Joseph Hedges - Chief Operating Officer Ghassan Ariqat, Project Manager/Director Glen Suitor - DB Oversight Manager
196 CP 1 HSR 13-06 192 4/3/2018 Tutor Perini / Zachry/Parsons Third-party Related UPRR Signal House at Herndon Avenue $43,786.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for redesign of the UPRR temporary signal system to avoid moving the UPRR operational facilities near Herndon Avenue and Golden State Boulevard. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
197 CP 1 HSR 13-06 154 4/3/2018 Tutor Perini / Zachry/Parsons Third-party Related DL-0089 Clear Span BNSF ROW $432,025.43 This is a change to the contract for design services in the City of Fresno. The reason for this change is that the bent location of the Downtown Fresno Viaduct needed to be re-designed. Terry Ogle - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Glenn Suitor, D-B Oversight Manager
198 CP 1 HSR 13-06 176 2/9/2018 Tutor Perini / Zachry/Parsons Utility Relocation COF Weber Ave. Realignment Affecting $47,544.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional design work for AT&T facilities between Ashlan and McKinley Avenues in Fresno impacted by the City of Fresno redesign of Webber Avenue. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
199 CP 1 HSR 13-06 142 1/25/2018 Tutor Perini / Zachry/Parsons Third-party Related CHP Escort Reimbursement - COF Reqt. $300,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is a City of Fresno requirement for California Highway Patrol to escort large delivery loads within City of Fresno limits. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
200 CP 1 HSR 13-06 184 1/24/2018 Tutor Perini / Zachry/Parsons Third-party Related BNSF Schmidt Creek Tributary Box $18,382.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design services and third-party coordination to redesign Schmidt Creek Tributary culvert across the future high-speed rail system resulting from movement to the planned rail route. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
201 CP 1 HSR 13-06 183 1/24/2018 Tutor Perini / Zachry/Parsons Third-party Related Accommodate 10' Access Road for UPRR $108,726.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design services and third-party coordination activities to provide a 10-foot wide access road across Herndon Canal for UPRR access. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
202 CP 1 HSR 13-06 180 1/24/2018 Tutor Perini / Zachry/Parsons Third-party Related Westside Shoofly single Track Shift $85,585.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design costs to protect the existing Kinder Morgan pipeline and to modify the UPRR shoefly (rail bypass) at that location. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
203 CP 1 HSR 13-06 141 1/24/2018 Tutor Perini / Zachry/Parsons Third-party Related Intrusion Protection Barrier Design $399,153.64 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to redesign a barrier preventing derailed conventional freight trains intruding into the high-speed rail system and portions of the Fresno Trench to comply with updated design criteria. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
204 CP 1 HSR 13-06 120 1/24/2018 Tutor Perini / Zachry/Parsons Third-party Related General Order and Settlement Aggree $345,531.51 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities out of the way of the future high-speed rail system. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director David Vallejos, DB Oversight Manager
205 CP 1 HSR 13-06 14.1 1/19/2018 Tutor Perini / Zachry/Parsons Administrative Revised Design Variance Request Form $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to an administrative change to revise the form used to request variances to the design criteria used on the project. Steven Milton - Design & Construction Manager Ghassan Ariqat, Project Manager/Director David Vallejos - DB Oversight Manager
206 CP 1 HSR 13-06 127 1/18/2018 Tutor Perini / Zachry/Parsons Third-party Related Downtown HST Track Alignment- Design $360,183.01 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design services to revise the future track allignment and associated facilities at Fresno Station. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director David Vallejos, DB Oversight Manager
207 CP 1 HSR 13-06 182 1/12/2018 Tutor Perini / Zachry/Parsons Third-party Related Relocation of the Kinder Morgan Pipe $1,825,656.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move the Kinder Morgan pipeline near Dry Creek Canal out of the way of the future high-speed rail system. Steve Milton - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
208 CP 1 HSR 13-06 181 12/20/2017 Tutor Perini / Zachry/Parsons Environmental WEF for the Exclusion of CTS $1,607,740.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for new fence material to protect the California Tiger Salamander along the construction zone. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
209 CP 1 HSR 13-06 74 12/20/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Maintain Access to Road 33 at Ave 7 $1,615,455.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to construct a wider bridge to take Avenue 7 over the future high-speed rail system. Terry Ogle, Design & Construction Manager Ghassan Ariqat, Project Manager/Director David Vallejos, D-B Oversight Manager
210 CP 1 HSR 13-06 160 12/19/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Construction Grounding and Bonding $702,843.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional electrical grounding and bonding at intermediate support columns for all bridges over which high-speed trains will travel. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
211 CP 1 HSR 13-06 175 12/7/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Flagging And Temperary Signal Rd.26 $229,159.76 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide temporary flagging and provide and operate a temporary traffic signal at a road intersection as requested by County of Madera during construction activities. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
212 CP 1 HSR 13-06 169 12/7/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Excluded ICE Assessments for Execute $144,088.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional independent engineering assessments that were excluded from several previous change orders, potential change orders, and task order proposals. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
213 CP 1 HSR 13-06 168 12/7/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications DL-00130 R1 AR Fence Reqts - Design $83,683.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay for additional design related to revised design criteria for fence to keep people out of the future high-speed rail system. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
214 CP 1 HSR 13-06 87.2 11/10/2017 Tutor Perini / Zachry/Parsons Third-party Related Top Down Const SR 180 Supplemental 2 $300,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to perform Construction Zone Enhanced Enforcement Program (enhanced traffic mangement using California Highway Patrol) at State Route 180. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director David Vallejos, D-B Oversight Manager
215 CP 1 HSR 13-06 166 11/9/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Drainage Basins at E Muscat - Design $25,459.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to re-design the drainage basins under East Muscat Avenue Viaduct. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
216 CP 1 HSR 13-06 178 10/23/2017 Tutor Perini / Zachry/Parsons Third-party Related Partial Comp. for COF Utility Agrmnt $2,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional construction as a result of the final utility agreement with the City of Fresno. This agreement, executed after the construction contract was awarded included additional work due to update City of Fresno standards. Steve Milton - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
217 CP 1 HSR 13-06 177 10/11/2017 Tutor Perini / Zachry/Parsons Administrative UNI: Transfer Funds from Provisional ($35,000,000.00) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to credit the Authority from the contractor's Utility Provisional Sum and the Construction Contract Work Provisional Sum. Scott Jarvis, Chief Engineer Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
218 CP 1 HSR 13-06 133 10/11/2017 Tutor Perini / Zachry/Parsons Third-party Related Madera Settlement Ave 9,12,13 OH $18,629,963.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design and construct Avenue 9 and Avenue 12 as four-lane bridges and to remove the requirement to construct Avenue 13. Scott Jarvis, Chief Engineer Ghassan Ariqat, Project Manager/Director David Vallejos, DB Oversight Manager
219 CP 1 HSR 13-06 151 9/27/2017 Tutor Perini / Zachry/Parsons Environmental Environmental Scope Reduction ($1,375,000.00) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to credit the Authority for environmental work. This work will be paid under change order 88. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director David Vallejos, DB Oversight Manager
220 CP 1 HSR 13-06 174 9/21/2017 Tutor Perini / Zachry/Parsons Dispute Resolution Settlement of disputed PCO's $383,889.00 This is a change to a contract for design and construction services in the Central Valley. This change concludes negotiations regarding 20 disputed items relating to design services. Steve Milton - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
221 CP 1 HSR 13-06 55 9/19/2017 Tutor Perini / Zachry/Parsons Third-party Related UPRR Boundary Fence $57,266.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to conduct additional work associated with a fence along the east side of land owned by Union Pacific Railroad. Steve Milton, Design & Construction Manager Ghassan Ariqat, Project Manager/Director David Vallejos, D-B Oversight Manager
222 CP 1 HSR 13-06 170.1 9/13/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Shaw Vertical Clearance- Design Supp $44,902.33 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to supplement Change Order number 170 to pay for redesign for the West Shaw Avenue bridge and related road design. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
223 CP 1 HSR 13-06 69 9/13/2017 Tutor Perini / Zachry/Parsons Third-party Related UPRR 10 foot Access Road $128,602.12 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to design an access road along Union Pacific Railroad land. This access road is required by a maintenance agreement between Union Pacific Railroad and the Authority. Steven Milton - Design & Construction Manager Ghassan Ariqat, Project Manager/Director David Vallejos, D-B Oversight Manager
224 CP 1 HSR 13-06 62 9/13/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Methacrylate Overlay - Tuolumne Deck $46,366.06 This is a change to a contract for construction services in the Central Valley. The reason for this change is to apply a protective coating to the Tuolumne Street bridge deck. Steven Milton - Design and Construction Manager Ghassan Ariqat, Project Manager/Director David Vallejos, D-B Oversight Manager
225 CP 1 HSR 13-06 173 8/29/2017 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Addtl Trestle Work SJRV Oberti Farms $1,592,832.40 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to redesign and construct a continuous trestle from the south bank to the north bank of the San Joaquin River to provide access to the San Joaquin River Viaduct. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director John C. Lee DB Oversight Manager
226 CP 1 HSR 13-06 136 8/29/2017 Tutor Perini / Zachry/Parsons Third-party Related Reconfig Stanislaus and Tuolumne St $12,866,824.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design and construct a bridge at Toulumne Street instead of Stanislaus Street and associated road way modifications. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
227 CP 1 HSR 13-06 80.1 8/29/2017 Tutor Perini / Zachry/Parsons Administrative Continued Site Camera Hosting Fees $30,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to continue to provide time-lapse documentation of the construction of the future high-speed rail system at Fresno River Viaduct, Tuolumne Bridge and Starte Route 180 trench. Terry Ogle, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
228 CP 1 HSR 13-06 171 8/23/2017 Tutor Perini / Zachry/Parsons Third-party Related SR-145 Caltrans Project Report $200,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design and construction services required to implement the changes for the State Route 145 bridge from 90 feet to 125 feet 3 inches in length. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director John C. Lee DB Oversight Manager
229 CP 1 HSR 13-06 170 8/14/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: Shaw Vertical Clearance- Design $127,506.17 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to prepare a report to vary the design from the 27-foot vertical clearance requirements in the specification to 24-foot and to redesign the West Shaw Avenue bridge and road design. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director John C. Lee DB Oversight Manager
230 CP 1 HSR 13-06 172 8/10/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Safety and Security Certification $180,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform safety and security planning activities during final design, including revising the plan and providing a certification package prior to work starting. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director John C. Lee DB Oversight Manager
231 CP 1 HSR 13-06 88.4 8/1/2017 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $3,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to provide environmental services to ensure the future high-speed rail system work complies with environmental requirements. Terry Ogle, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
232 CP 1 HSR 13-06 48 6/26/2017 Tutor Perini / Zachry/Parsons Utility Relocation PG&E & AT&T Facilies Relocations $92,804,594.26 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to transfer responsibility of services from the Authority to the contractor. The transferred services are to manage the design and construction of PG&E and AT&T facilities to move them out of the way of future high-speed rail construction. Scott Jarvis, Chief Engineer Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
233 CP 1 HSR 13-06 97.1 6/19/2017 Tutor Perini / Zachry/Parsons Third-party Related Westside Wye Shoofly Alt 1 - Design $269,984.28 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design the railroad detour (shoofly) from the chosen alternative evaluated in contract change order number 97 to make way for the high-speed rail system. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
234 CP 1 HSR 13-06 163 6/13/2017 Tutor Perini / Zachry/Parsons Third-party Related Ventura Street Underpass UPRR Bridge $144,970.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform design required to widen the Union Pacific Railroad Ventura Street underpass to enable the construction of the future high-speed rail system. Terry Ogle - Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
235 CP 1 HSR 13-06 162 6/13/2017 Tutor Perini / Zachry/Parsons Third-party Related Tulare Street Underpass UPRR Bridge $137,189.50 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform design required to widen the Union Pacific Railroad Tulare Street underpass to enable the construction of the future high-speed rail system. Terry Ogle - Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
236 CP 1 HSR 13-06 121 6/13/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Combined Horizontal & Vertical Curve $120,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to redesign the high-speed rail alignment where horizontal and vertical curves overlap and for track infrastructure at the future Fresno station. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
237 CP 1 HSR 13-06 165 6/1/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Solid Barrier on Type 2 Overhead $186,957.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design new barriers on all bridges that span the future high-speed rail system. Terry Ogle - Design and Construction Manager (Acting) Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
238 CP 1 HSR 13-06 132 6/1/2017 Tutor Perini / Zachry/Parsons Utility Relocation HST Drainage Modifications - Design $31,814.96 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide design services to modify designs for drainaige of the future high-speed rail system. Terry Ogle - Design and Construction Manager (Acting) Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
239 CP 1 HSR 13-06 164 5/26/2017 Tutor Perini / Zachry/Parsons Environmental Final Determination of Environmental ($1,082,684.94) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide the Authority credit for settlement of 10 previous change orders. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
240 CP 1 HSR 13-06 128 5/23/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Grounding and Bonding Project Struct $85,280.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide additional design services for electrical grounding and bonding at a bridge. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
241 CP 1 HSR 13-06 158 5/17/2017 Tutor Perini / Zachry/Parsons Utility Relocation BP-12 Road 27 $374,345.62 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities out of the way of the future high-speed rail system at Road 27 in Madera County. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
242 CP 1 HSR 13-06 157 5/17/2017 Tutor Perini / Zachry/Parsons Utility Relocation BP-8 Hardy, Muscat, Central & Ameri $640,033.74 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities out of the way of the future high-speed rail system at Hardy, Muscat, Central and American Avenues in the City of Fresno. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
243 CP 1 HSR 13-06 156 5/17/2017 Tutor Perini / Zachry/Parsons Utility Relocation BP-07 Herndon Canal to Ashlan $7,251,599.50 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay AT&T to move its services out of the way of the future high-speed rail system. This work is coordinated by the general contractor who is responsible for designing and constructing the future system from Herndon Canal to Ashlan Avenue in the City of Fresno. Scott Jarvis, Chief Engineer Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
244 CP 1 HSR 13-06 159 5/16/2017 Tutor Perini / Zachry/Parsons Utility Relocation Belmont Avenue OH - Relocate Column $750,000.00 This is a change to the contract for design services in the Central Valley. The reason for the change is to complete additional design work related to the bridge at Belmont Avenue and the requirements of the Union Pacific Rail Road. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
245 CP 1 HSR 13-06 161 5/15/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Muscat Revised Spans - Design $446,965.80 This is a change to the contract for design services in the Central Valley. The reason for the change is to revise the design for the bridge over the future high-speed rail system at Muscat Avenue. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
246 CP 1 HSR 13-06 126 5/15/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications N. Golden State Realignment - Design $69,006.51 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform design for the movement of Golden State Boulevard. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
247 CP 1 HSR 13-06 153 5/8/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Collision Pushover Analysis for SJRV $42,808.64 This is a change to the contract for design services in the Central Valley. The reason for the change is for additional engineering analysis to evaluate the amount of force the San Joaquin River Viaduct structure can withstand. Terry Ogle, Acting Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
248 CP 1 HSR 13-06 42.1 5/5/2017 Tutor Perini / Zachry/Parsons Administrative Supplemental Addtl Space 1401 Fulton $50,000.00 This is a change to a contract for design and construction services in the Central Valley. The contractor is leasing office space at 1401 Fulton Street in Fresno to the Authority. The reason for this change is to extend the current leasing agreement by five months. Terry Ogle, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
249 CP 1 HSR 13-06 152 5/2/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Olive OH Relocate Column Out of UPRR $413,984.07 This is a change to the contract for design services in the Central Valley. The reason for this change is to complete additional design work related to the bridge at Olive Avenue and the requirements of the Union Pacific Rail Road. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
250 CP 1 HSR 13-06 88.3 5/1/2017 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $3,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to provide environmental services to ensure the future high-speed rail system work complies with environmental requirements. Terry Ogle, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
251 CP 1 HSR 13-06 134 4/26/2017 Tutor Perini / Zachry/Parsons Third-party Related UNI: Permanent Fence at SJRV $27,237.67 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to construct a chain link fence between the future high-speed rail system and Camp Pashayan. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
252 CP 1 HSR 13-06 131 4/26/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: System Site Revisions $33,215.62 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to incorporate underground rail System Site Facility changes into the design. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
253 CP 1 HSR 13-06 147 4/17/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Belmont Overcrossing Design Simulat $12,901.47 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to prepare a design simulation for the West Belmont Avenue Overcrossing to show what it would look like when finished. Terry Ogle - Director of Design and Construction Ghassan Ariqat - Project Manager/Director John C. Lee - DB Oversight Manager
254 CP 1 HSR 13-06 129 4/6/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Train Control Facilities $36,399.87 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design additional Train Control Facility Sites at two locations. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
255 CP 1 HSR 13-06 88.2 3/30/2017 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $1,200,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to perform environmental services as part of the Authority's environmental commitments. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
256 CP 1 HSR 13-06 71 3/22/2017 Tutor Perini / Zachry/Parsons Environmental Building HazMat PS Budget Increase $8,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to increase the budget for the removal of hazardous materials from properties acquired by the Authority. Scott Jarvis - Chief Engineer Chassan Ariqat - Project Manager/Director John C. Lee - DB Oversight Manager
257 CP 1 HSR 13-06 149 3/21/2017 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Const. Electrical Package K $1,535,027.90 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E electrical distribution lines in the County of Fresno and County of Madera, to make way for the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
258 CP 1 HSR 13-06 148 3/21/2017 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Gas Distribution Const. Pkg. J $115,730.87 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E gas distribution lines near Hardy Avenue in the City of Fresno, to make way for the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
259 CP 1 HSR 13-06 68 3/21/2017 Tutor Perini / Zachry/Parsons Third-party Related Grade & Reloc. Pump Stn. at Basin EE $81,080.35 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move storm water infrastructure out of the way of the future high-speed rail system at the Fresno Metropolitan Flood Control District Basin EE. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
260 CP 1 HSR 13-06 63 3/21/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Belmont Avenue Design Refinement $103,900.58 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to do additional roadway design and re-design at Belmont Avenue. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
261 CP 1 HSR 13-06 144 3/20/2017 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related ROW Access Lawson Prop. MF-10-0041 $1,373.06 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move the high-speed train access restricting fence 15 feet east of an acquired parcel to provide access to an adjacent business owner. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
262 CP 1 HSR 13-06 97 3/15/2017 Tutor Perini / Zachry/Parsons Third-party Related Westside Wye Shoofly Design Study $89,697.99 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to evaluate two alternatives for temporary freight rail detours (shoofly) while building the high-speed rail trench in the City of Fresno. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
263 CP 1 HSR 13-06 100 3/14/2017 Tutor Perini / Zachry/Parsons Third-party Related DL-0097 City of Fresno Well Site 162 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move the City of Fresno (COF) well site 162 to to a more secure location then previously agreed. This is a zero-cost change order. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
264 CP 1 HSR 13-06 146 3/10/2017 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Gas Transmission Design Pkg. Z $116,123.57 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E gas transmission utilities in the County of Madera and the City of Fresno to make way for the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
265 CP 1 HSR 13-06 143 3/10/2017 Tutor Perini / Zachry/Parsons Utility Relocation PGE Design Elec Packages S, T and U $693,932.44 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E electrical utilities at three locations in the County of Madera and the City of Fresno to make way for the future high-speed rail system Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
266 CP 1 HSR 13-06 145 3/9/2017 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Design Gas Dist. Pkg. W, X & Y $427,925.36 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E gas utilities at three locations in the County of Madera and the City of Fresno to make way for the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
267 CP 1 HSR 13-06 88.1 2/9/2017 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $3,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to perform environmental services as part of the Authority's environmental commitments. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
268 CP 1 HSR 13-06 124 2/2/2017 Tutor Perini / Zachry/Parsons Utility Relocation COF 24" and 30" Waterline Ventura $26,216.40 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is change is to provide design services to meet the new standards of the City of Fresno to resolve conflicts between Ventura Street and City of Fresno water mains. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
269 CP 1 HSR 13-06 79 2/2/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications GS Blvd 68' Widening(West Ave-SR99) $375,880.19 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to widen Golden State Boulevard and re-design the McKinley bridge over the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
270 CP 1 HSR 13-06 59 2/2/2017 Tutor Perini / Zachry/Parsons Utility Relocation Belmont Ave Final Facilty Plan $72,331.71 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to provide roadway design services on Belmont Avenue. The designs are to include ADA-compliant ramps, accommodate truck deliveries, and modify intersections. Designs are to follow City of Fresno standards. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
271 CP 1 HSR 13-06 57 2/2/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications CuldaSac at East Ave Desig Refinemen $5,462.34 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design a cul-de-sac on East Avenue in accordance with City of Fresno standards. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
272 CP 1 HSR 13-06 137 1/31/2017 Tutor Perini / Zachry/Parsons Utility Relocation Tuolumne Vault Relocation $1,464,552.45 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E electrical distribution lines along Tuolumne Street in the City of Fresno out of the way of the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
273 CP 1 HSR 13-06 13.3 1/31/2017 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related BETP Implementation Cost Komoto Bldg $42,725.84 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct surveys and monitoring of construction activities on the Komoto’s Department Store building in Fresno. Hugo Mejia - Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee - DB Oversight Manager
274 CP 1 HSR 13-06 13.2 1/31/2017 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related BETP Implementation Cost B of A $52,810.41 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct surveys and monitoring of construction activities on the Bank of America building in Fresno. Hugo Mejia - Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee - DB Oversight Manager
275 CP 1 HSR 13-06 72 1/26/2017 Tutor Perini / Zachry/Parsons Utility Relocation ATT BP-04 Ashlan to McKinley $9,694,318.86 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move AT&T facilities out of the way of the future high-speed rial system between Ashlan and McKinley Avenues in Fresno. Scott Jarvis, Chief Engineer Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
276 CP 1 HSR 13-06 51 12/22/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Design Changes for Various CO $613,341.51 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete additional design work at 14 locations. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
277 CP 1 HSR 13-06 94 12/21/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Subcontract with Ferreira Coastal $110,968.69 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is move an AT&T facility out of the way of the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
278 CP 1 HSR 13-06 64 12/21/2016 Tutor Perini / Zachry/Parsons Utility Relocation Installation of an Underground Elect $30,963.46 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities out of the way of the future high-speed rial system at North Golden State Boulevard. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
279 CP 1 HSR 13-06 82.2 12/15/2016 Tutor Perini / Zachry/Parsons Utility Relocation Valverde Construction for Pothole $377,454.46 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to preform potholing to identify a 24 inch PG&E Gas Transmission Line. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
280 CP 1 HSR 13-06 37 12/15/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Golden State Blvd. Widening Design $7,644.97 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design roadway and drainage for Golden State Boulevard in Fresno. Hugo Mejia - Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee - DB Oversight Manager
281 CP 1 HSR 13-06 110 12/13/2016 Tutor Perini / Zachry/Parsons Utility Relocation PGE GT Conflict Designs1-003,005,018 $215,350.25 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to move PG&E facilities out of the way of the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
282 CP 1 HSR 13-06 73 12/13/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications G St Realignment Impacts Design $53,006.53 This is a change to a contract for design and construction services in the Central Valley.The reason for this change is to redesign the future high-speed rail alignment due to changes related to the location of G Street in Fresno. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
283 CP 1 HSR 13-06 123 12/8/2016 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Service Disconnects $3,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay for utility disconnection fees for PG&E and AT&T utilities prior to their removal. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
284 CP 1 HSR 13-06 140 11/23/2016 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Conceptual Design for Eminent Domain $7,644.09 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to relocate a Fresno Metropolitan Flood Control District (FMFCD) storm drain. FMFCD is a public entity that provides flood control and urban storm water services in the City of Fresno. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
285 CP 1 HSR 13-06 99.1 10/12/2016 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Completion Deadline Ex/Res.- Suppl. $13,612,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to accelerate work in the contract by 7 months to recover from delays in buying land. Scott Jarvis - Chief Engineer Ghassan Ariqat, Project Manager/Director
286 CP 1 HSR 13-06 108 10/10/2016 Tutor Perini / Zachry/Parsons Utility Relocation Additional Design Work PGE Conflicts $279,188.75 This is a change to the contract for design services in the Central Valley. The reason for the change is to move PG&E facilities out of the way of the future high-speed rail system at Avenue 17 and Roads 26 and 27 in Madera County. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
287 CP 1 HSR 13-06 103 10/10/2016 Tutor Perini / Zachry/Parsons Utility Relocation PGE Design Package G $444,116.88 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E utilities out of the way of the future high-speed rail system. Hugo Mejia - Design & Construction Manager Ghassan Ariqat - Interim Project Manager/Director John C. Lee - DB Oversight Manager
288 CP 1 HSR 13-06 47 10/10/2016 Tutor Perini / Zachry/Parsons Utility Relocation Project Scoping for the New PG&E $17,250.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to prepare a Planning Information Package for a new PG&E Gas Regulator Station. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
289 CP 1 HSR 13-06 119 9/26/2016 Tutor Perini / Zachry/Parsons Third-party Related Railroad Utility App. License Fees $860,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to acquire utility crossing, right of entry and permit fees to railroads. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
290 CP 1 HSR 13-06 117 9/26/2016 Tutor Perini / Zachry/Parsons Administrative Bond & Insurance Resolution $379,751.28 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is is for additional bonding and insurance costs for previous change orders issued through July 1, 2016. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
291 CP 1 HSR 13-06 116 9/26/2016 Tutor Perini / Zachry/Parsons Third-party Related Signalized Intersection at Olive Ave $34,844.60 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform design required to add a traffic signal at Olive Avenue and Roeding Park Entrance according to City of Fresno requirements. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
292 CP 1 HSR 13-06 115 9/26/2016 Tutor Perini / Zachry/Parsons Third-party Related Ventura Street and F Street Inter. $43,024.31 This is a change to a contract for design services in the Central Valley. The reason for the change is to design the traffic signals at the intersection of Ventura Street and F Street according to City of Fresno requirements. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
293 CP 1 HSR 13-06 113 9/26/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Steel Structures Inc. Building Fire $32,076.00 This is a change to a contract for design services in the Central Valley. The reason for this change is to design fencing to keep people out of the future high-speed rail system at a specific property in Madera County. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
294 CP 1 HSR 13-06 111 9/26/2016 Tutor Perini / Zachry/Parsons Utility Relocation Add Design Work PGE 21 Conflicts $370,082.07 This is a change to a contract for design services in the Central Valley. The reason for the change is to pay Pacific Gas and Electric Company to move its facilities out of the way of the future high-speed rail system. This work is coordinated by the general contractor who is responsible for designing and constructing the future system in the in the City of Fresno. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
295 CP 1 HSR 13-06 60 9/26/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications SE Ave Geometric Changes FB FEIR $14,110.08 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to do additional design for sidewalks and turning lanes on East Belgravia Avenue. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
296 CP 1 HSR 13-06 114 9/23/2016 Tutor Perini / Zachry/Parsons Third-party Related Signalized Intersection at Belmont $34,844.60 This is a change to a contract for design services in the Central Valley. The reason for the change is to design the traffic signals at the intersection of Belmont Street and Stafford Street according to City of Fresno requirements. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
297 CP 1 HSR 13-06 105 9/7/2016 Tutor Perini / Zachry/Parsons Utility Relocation AT&T Ductbank Install Madera Co. $2,287,112.23 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities at Avenues 7, 8, 9, 10, 12, and 13 out of the way of the future high-speed rail system. Terry Ogle - Director of Design and Construction Ghassan Ariqat - Project Manager/Director John C. Lee - DB Oversight Manager
298 CP 1 HSR 13-06 109 9/2/2016 Tutor Perini / Zachry/Parsons Utility Relocation Const. Services ATT Barrel Vault $6,427.79 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities out of the way of the future high-speed rail system at the intersection of Raymond Road and State Route 145 in Madera County. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
299 CP 1 HSR 13-06 112 8/23/2016 Tutor Perini / Zachry/Parsons Utility Relocation ATT Ductbank Muscat Ave $19,509.17 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay AT&T to move its facilities out of the way of the future high-speed rail system. This work is coordinated by the general contractor who is responsible for designing and constructing the future system at Muscat Avenue in the City of Fresno. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
300 CP 1 HSR 13-06 107 7/21/2016 Tutor Perini / Zachry/Parsons Utility Relocation AT&T Duct Bank Installation On Yale $167,826.04 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities out of the way of the future high-speed rail system at Yale Avenue in Fresno. Terry Ogle for Huge Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
301 CP 1 HSR 13-06 106 7/21/2016 Tutor Perini / Zachry/Parsons Utility Relocation ATT Facilities Relocate Rd 27 $166,636.98 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities at Road 27 out of the way of the future high-speed rail system. Hugo Mejia - Design & Construction Manager Ghassan Ariqat - Interim Project Manager/Director John C. Lee - DB Oversight Manager
302 CP 1 HSR 13-06 104 7/21/2016 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Elec 8 Central Malaga America $145,569.55 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move 8 PG&E electrical utilities at Central, Malaga and American Avenues in Fresno out of the way of the of the future high-speed rail system. Hugo Mejia - Design & Construction Manager Ghassan Ariqat - Interim Project Manager/Director John C. Lee - DB Oversight Manager
303 CP 1 HSR 13-06 101 7/21/2016 Tutor Perini / Zachry/Parsons Utility Relocation ATT Vault Relocal Tuolumne OC $129,740.36 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities at the end of the Tuolumne Street Bridge in the City of Fresno, to make way for the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
304 CP 1 HSR 13-06 92 7/21/2016 Tutor Perini / Zachry/Parsons Utility Relocation Design Electrical ET1-5,6,8,9 $671,540.77 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E electrical transmission line services out of the way of the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
305 CP 1 HSR 13-06 83 7/20/2016 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Gas Distribution Relocations $897,162.06 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to relocate PG&E gas distribution lines out of the way of the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
306 CP 1 HSR 13-06 98 7/5/2016 Tutor Perini / Zachry/Parsons Utility Relocation Install Ductbank Clinton & Belmont $26,428,542.16 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T underground utilities at Clinton Avenue to Belmont Avenue, in the City of Fresno, to make way for the future high-speed rail system. Scott Jarvis - Chief Engineer Jim Laing, Project Manager/Director John C. Lee - DB Oversight Manager
307 CP 1 HSR 13-06 29.3 7/1/2016 Tutor Perini / Zachry/Parsons Environmental Extra Work Bio Services $600,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to implement requirements of the California Department of Fish and Wildlife permits as part of the Authority's environmental commitments. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
308 CP 1 HSR 13-06 96 6/22/2016 Tutor Perini / Zachry/Parsons Utility Relocation UNI: UG Duct Bank Ave15 1/2, 15 $2,845,133.50 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T underground utilities at Avenues 11, 15, and 15-1/2, in Madera Count to make way for the future high-speed rail system. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
309 CP 1 HSR 13-06 90 6/21/2016 Tutor Perini / Zachry/Parsons Utility Relocation PGE-Utility Conflict E1-116 Road 1/2 $1,624,717.55 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E underground electrical utilities out of the way of the future high-speed rail system. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
310 CP 1 HSR 13-06 75.1 6/21/2016 Tutor Perini / Zachry/Parsons Utility Relocation UNI: Design PGE Dist. Conflicts $1,031,028.90 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move PG&E utilities out of the way of the future high-speed rail system at 49 locations. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
311 CP 1 HSR 13-06 99 6/14/2016 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Completion Deadline Ext/Resolution $49,900,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to add 17 months and additional budget to the contract to recognize the impact to the contractor caused by delays in buying land. Jeff Morales - Chief Executive Officer Ronald N. Tutor - Managing Partner
312 CP 1 HSR 13-06 82.1 6/8/2016 Tutor Perini / Zachry/Parsons Utility Relocation Additional Services SR 99 Realign $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct surveying and potholing to identify PG&E and AT&T utility locations with the future high-speed rail system. This supplements change order 82 to add the State Route 99 project area. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
313 CP 1 HSR 13-06 91 6/1/2016 Tutor Perini / Zachry/Parsons Utility Relocation Design - PGE Utility Conflict E1 $33,016.50 This is a change to a contract for design and construction services in the Central Valley. The reason for the change to move PG&E electric and gas utilities in Madera County out of the way of the future high-speed rail system. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
314 CP 1 HSR 13-06 93 5/31/2016 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Property Modification Design Only $63,933.20 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide design services for modifications to a property that the Authority has bought. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
315 CP 1 HSR 13-06 44.1 5/31/2016 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Utility Conflict (CO 44) $221,984.44 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move PG&E facilities out of the way of future high-speed rail construction. The designs for these relocations were changed during the PG&E approval process. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
316 CP 1 HSR 13-06 95 5/12/2016 Tutor Perini / Zachry/Parsons Utility Relocation AT&T Design-Underground Ductbank $868,479.70 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T underground utilities from the south of Santa Clara Street to south of East American Avenue in the City of Fresno to make room for the future high-speed rail system. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
317 CP 1 HSR 13-06 2.1 5/4/2016 Tutor Perini / Zachry/Parsons Administrative Partnering Costs Supplemental $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue partnering meetings between the contractor and the Authority for the project. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
318 CP 1 HSR 13-06 87.1 4/29/2016 Tutor Perini / Zachry/Parsons Third-party Related Top Down Const SR 180 Supplmtl $470,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement and perform Construction Zone Enhanced Enforcement Program (enhanced traffic mangement using California Highway Patrol) during construction at State Route 180. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
319 CP 1 HSR 13-06 84 4/20/2016 Tutor Perini / Zachry/Parsons Third-party Related Top of Rail Survey - UPRR $4,866.22 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to survey the top of each Union Pacific Railroad rail on all their mainline tracks between 1000 feet either side of Ashlan and Clinton Avenues to satisfy the conditions of the Authority's agreement with UPRR. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
320 CP 1 HSR 13-06 85 4/19/2016 Tutor Perini / Zachry/Parsons Third-party Related Fresno River VECP ($1,243,975.50) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide a credit to the Authority for incorporation of the Fresno River Value Engineering Change Proposal. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
321 CP 1 HSR 13-06 89 4/7/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications North Extension $153,399,844.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to add approximately 2.72 miles of additional future high-speed rail system to this contract, to the northern boundary. This additional scope is mostly flat and is adjacent to the west side of the Burlington Northern Santa Fe tracks in the County of Madera. Scott Jarvis, Chief Engineer Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
322 CP 1 HSR 13-06 87 4/5/2016 Tutor Perini / Zachry/Parsons Third-party Related Top Down Const SR 180/ Fresno Trench $3,765,141.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design and construct the tunnel under State Route 180 using the Top-Down Construction Method. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
323 CP 1 HSR 13-06 88 4/4/2016 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $1,800,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform environmental services as part of the Authority's environmental commitments. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
324 CP 1 HSR 13-06 86 3/7/2016 Tutor Perini / Zachry/Parsons Utility Relocation AT&T UG Ductbank Relocate Ashlan /SJ $313,454.10 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to contribute to moving AT&T facilities out of the way of the future high-speed rail alignment between Ashlan Avenue and the San Joaquin River. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
325 CP 1 HSR 13-06 54 3/7/2016 Tutor Perini / Zachry/Parsons Utility Relocation Design AT&T Relocation-Madera County $341,291.46 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move AT&T facilities out of the way of the future high-speed rail system at Avenues 7, 8 , 9, 10, 11, 12, 13, 15, 15-1/2. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
326 CP 1 HSR 13-06 38 3/7/2016 Tutor Perini / Zachry/Parsons Utility Relocation ATT Design-Belmont to Santa Clara $245,868.06 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete plans to move AT&T facilities out of the way of the future high-speed rail system. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
327 CP 1 HSR 13-06 81 3/4/2016 Tutor Perini / Zachry/Parsons Utility Relocation PG&E / AT&T Managemt Team/Bid Solic $2,262,678.07 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to transfer responsibility of management services from the Authority to the contractor to move PG&E and AT&T facilities out of the way of future high-speed rail system. PG&E and provides gas and electric services in California. AT&T provides telecommunications services. Terry Ogle, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
328 CP 1 HSR 13-06 56 3/1/2016 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Gas Relocate Kern / F St. $11,039.85 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move PG&E facilities out of the way of the future high-speed rail system. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
329 CP 1 HSR 13-06 82 2/22/2016 Tutor Perini / Zachry/Parsons Utility Relocation Miscellaneous Survey & Pothole Work $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct surveying and potholing to identify PG&E and AT&T utility locations with the future high-speed rail alignment. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
330 CP 1 HSR 13-06 75 2/22/2016 Tutor Perini / Zachry/Parsons Utility Relocation EEI Engineering Design for Unit 2 $508,875.25 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move PG&E utilities out of the way of the future high-speed rail system at West Shaw Avenue, Tuolumne Street, Fresno-Tulare Street, Kern Street, Ventura Street in Fresno County and Avenues 11, 15 and 15 1/2 in Madera County. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
331 CP 1 HSR 13-06 32.1 1/25/2016 Tutor Perini / Zachry/Parsons Environmental Pedestrian Arch Field Surveys $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to perform Pedestrian Archaeological Field Inventory Surveys. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
332 CP 1 HSR 13-06 29.2C 1/22/2016 Tutor Perini / Zachry/Parsons Environmental Extra work Biological Servies for CP1C $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to implement requirements of the California Department of Fish and Wildlife permits as part of the Authority's environmental commitments. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
333 CP 1 HSR 13-06 29.1A 1/22/2016 Tutor Perini / Zachry/Parsons Environmental Extra work Biological Servies for CP1A/1B $300,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to implement requirements of the California Department of Fish and Wildlife permits as part of the Authority's environmental commitments. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
334 CP 1 HSR 13-06 77 1/14/2016 Tutor Perini / Zachry/Parsons Utility Relocation Valverde Const. AT&T Conflict $38,654.27 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move AT&T utilities out of the way of the future high-speed rail system at Raymond Road and State Route 145 in Madera County. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
335 CP 1 HSR 13-06 49 1/14/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications OCS Structural Connections $1,874,151.32 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design and install fittings on bridges into which future high-speed rail system components will be attached. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
336 CP 1 HSR 13-06 43 12/29/2015 Tutor Perini / Zachry/Parsons Environmental EMMA and Sustainability $72,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to authorize the additional level of effort required for entering data into the Environmental Mitigation Management & Assessment database. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
337 CP 1 HSR 13-06 80 12/21/2015 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications CHSR Std. Spec Revision Photographic $50,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to provide time-lapse documentation of the construction of the future high-speed rail system at Fresno River Viaduct, Tuolumne Bridge and Starte Route 180 trench. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
338 CP 1 HSR 13-06 65 12/10/2015 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications OnSite Circulation Analysis FB100079 $7,817.12 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to conduct analysis of tractor/trailer movements on property impacted by the future high-speed rail system. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
339 CP 1 HSR 13-06 78 11/20/2015 Tutor Perini / Zachry/Parsons Utility Relocation Potholing for Caltrans in SR99 ROW $15,706.44 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to identify udnerground energy and telecommunications facilities that are within the project limits of the future high-speed rail system. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
340 CP 1 HSR 13-06 12.2 11/20/2015 Tutor Perini / Zachry/Parsons Environmental Archaeological Field Inventory $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct archaeological field surveys of additional properties. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
341 CP 1 HSR 13-06 50 10/21/2015 Tutor Perini / Zachry/Parsons Third-party Related COF Relocation Agreement $1,161,633.19 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to do additional design identified in the final agreement between the Authority and the City of Fresno. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
342 CP 1 HSR 13-06 53.1 10/13/2015 Tutor Perini / Zachry/Parsons Third-party Related Additional Assessments UPRR Parcels $5,462.09 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to conduct environmental assessment on Union Pacific Railroad owned land. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
343 CP 1 HSR 13-06 34 10/6/2015 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Trackway & Structures - Chapter 12 $589,533.66 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the design requirements for future high-speed rail bridges under 1000 feet in length. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
344 CP 1 HSR 13-06 52 10/1/2015 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications E. American Ave Design Speed Var $63,874.94 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete traffic studies on East American Avenue to prepare a request to the City of Fresno to reduce the speed on East American Avenue from 65 to 45 miles per hour. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
345 CP 1 HSR 13-06 53 9/29/2015 Tutor Perini / Zachry/Parsons Third-party Related Phase 2 Enviro Site Assessmt UPRR $36,723.62 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to conduct environmental assessment on Union Pacific Railroad owned land. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
346 CP 1 HSR 13-06 40 9/8/2015 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related CP 1 Parcel Mgt & Security $56,001.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide property management and site security prior to construction. Michael Leonardo - Acting Director of Design & Construction James Laing - Project Director John C. Lee - DB Oversight Manager
347 CP 1 HSR 13-06 45 9/4/2015 Tutor Perini / Zachry/Parsons Differing Site Conditions Site Specific Response Analysis FRV $55,968.56 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to provide a seismic analysis for the structural design of the Fresno River Viaduct. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
348 CP 1 HSR 13-06 44 8/20/2015 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Raymond Rd & SR 145 $392,495.35 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move electrical distribution facilities out of the way of the future high-speed rail construction over the Fresno River. Mike Leonardo, Acting Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
349 CP 1 HSR 13-06 42 8/19/2015 Tutor Perini / Zachry/Parsons Administrative Additional Space at 1401 Fulton $235,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to provide the Authority with an additional 5,113 square feet of rentable office space at 1401 Fulton Street in Fresno. Mike Leonardo, Acting Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
350 CP 1 HSR 13-06 12.1 7/31/2015 Tutor Perini / Zachry/Parsons Environmental Archaeological Field Inventory $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide additional archeological inventories to meet environmental requirements. Michael Leonardo - Acting Director of Design & Construction James Laing - Project Director John C. Lee - DB Oversight Manager
351 CP 1 HSR 13-06 35.1 7/21/2015 Tutor Perini / Zachry/Parsons Environmental Archaeological Monitoring in 1C $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to perform Archaeological Monitoring and related reporting. Mike Leonardo - Director of Design & Construction James Laing - Project Director John C. Lee - DB Oversight Manager
352 CP 1 HSR 13-06 29.2 7/21/2015 Tutor Perini / Zachry/Parsons Environmental Post Permit Monitoring Efforts 1C $100,000.00 This is a change to a contract for design and construction services in the Central Valley. TThe reason for the change is to continue to implement requirements of the California Department of Fish and Wildlife permits as part of the Authority's environmental commitments. Mike Leonardo - Director of Design & Construction James Laing - Project Director John C. Lee - DB Oversight Manager
353 CP 1 HSR 13-06 29.1 7/21/2015 Tutor Perini / Zachry/Parsons Environmental Post Permit Monitoring Efforts 1A/1B $150,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to implement requirements of the California Department of Fish and Wildlife permits as part of the Authority's environmental commitments. Mike Leonardo - Director of Design & Construction James Laing - Project Director John C. Lee - DB Oversight Manager
354 CP 1 HSR 13-06 28 5/29/2015 Tutor Perini / Zachry/Parsons Environmental 956 China-Additional Scope of Work $11,221.08 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide design services and monitoring for the restoration of the historical building at 956 China Alley in Fresno. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
355 CP 1 HSR 13-06 13.1 5/29/2015 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related BETP Task 2 and Task 3 $60,714.86 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to develop a pland to protect important elements of the built environment identified in the environmental documents. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
356 CP 1 HSR 13-06 41 5/27/2015 Tutor Perini / Zachry/Parsons Differing Site Conditions Ground Penetrating Radar - Kern St $9,567.91 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to provide subsurface images of Kern Street at Ofelia's Barber Shop/Restaurant and Dick's Store in Fresno. Ofelia P. Alcantara, P.E., Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
357 CP 1 HSR 13-06 35 5/4/2015 Tutor Perini / Zachry/Parsons Environmental Archaeological Monitoring in 1C $50,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform Archaeological Monitoring and related reporting. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
358 CP 1 HSR 13-06 31 5/4/2015 Tutor Perini / Zachry/Parsons Environmental Archaeological Monitoring 1A & 1B $500,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform archaeological monitoring services and related reporting. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
359 CP 1 HSR 13-06 30 5/4/2015 Tutor Perini / Zachry/Parsons Environmental Biological Monitoring Services in 1C $50,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform biological monitoring services prior to construction. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
360 CP 1 HSR 13-06 29 5/4/2015 Tutor Perini / Zachry/Parsons Environmental Post Permit Monitoring Efforts 1A/1B $96,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement requirements of the California Department of Fish and Wildlife permits as part of the Authority's environmental commitments. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
361 CP 1 HSR 13-06 39 4/22/2015 Tutor Perini / Zachry/Parsons Differing Site Conditions 1528-1548 Tulare Street $2,791.83 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to prepare a report describing how to repair buildings. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
362 CP 1 HSR 13-06 32 3/26/2015 Tutor Perini / Zachry/Parsons Environmental Pedestrian Arch Field Surveys $150,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform Pedestrian Archaeological Field Inventory Surveys. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
363 CP 1 HSR 13-06 33 3/4/2015 Tutor Perini / Zachry/Parsons Environmental Native American Monitoring for 1C $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform Native American Monitoring and Archaeological Monitoring. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
364 CP 1 HSR 13-06 27 2/26/2015 Tutor Perini / Zachry/Parsons Environmental Biological Monitoring $50,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide biological monitoring services prior to construction. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
365 CP 1 HSR 13-06 26 2/25/2015 Tutor Perini / Zachry/Parsons Environmental Archaeological Monitoring Services $250,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform archaeological monitoring. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
366 CP 1 HSR 13-06 25 2/25/2015 Tutor Perini / Zachry/Parsons Environmental Native American Monitoring $250,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform Native American Monitoring. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
367 CP 1 HSR 13-06 24 2/4/2015 Tutor Perini / Zachry/Parsons Environmental Main Canal Survey Report $12,354.25 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to prepare environmental documents as part of the Authority's environmental commitments. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
368 CP 1 HSR 13-06 23 2/4/2015 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications COF Convert Data Points $14,943.66 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to convert design data prior to submitting designs to the City of Fresno. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
369 CP 1 HSR 13-06 22 2/2/2015 Tutor Perini / Zachry/Parsons Administrative DRB Process Revision $- This is a change to a contract for design and construction services in the Central Valley. The reason for this no cost change is to streamline the dispute resolution process. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
370 CP 1 HSR 13-06 20 1/8/2015 Tutor Perini / Zachry/Parsons Environmental Small Mammal Burrow Excavation $480,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to dig small burrows for mammals by hand, as part of the Authority's environmental commitments. Ofelia Alcantara - Director of Design & Construction James Laing - Project Director John C. Lee - DB Oversight Manager
371 CP 1 HSR 13-06 18 1/8/2015 Tutor Perini / Zachry/Parsons Environmental GIS Habitat Tracking $244,811.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to set up a habitat tracking system as part of the Authority's environmental commitments. Ofelia Alcantara - Director of Design & Construction James Laing - Project Director John C. Lee - DB Oversight Manager
372 CP 1 HSR 13-06 16 10/30/2014 Tutor Perini / Zachry/Parsons Administrative CBA Administrative Addendum 1 $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to update the contract to include revisions to the Community Benefits Agreement. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director PCM DB Oversight Manager
373 CP 1 HSR 13-06 19 10/21/2014 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related DL 00004 - BETP Task 4 $28,662.76 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete histoical architectural surveying work at Belmont Avenue subway. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John Foster - Project Controls Oversight Manager
374 CP 1 HSR 13-06 15 10/21/2014 Tutor Perini / Zachry/Parsons Utility Relocation Design for AT&T Relocation $97,656.76 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities relocation plans at Stanislaus Bridge and Fresno River Viaduct out of the way of the future high-speed rail system. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
375 CP 1 HSR 13-06 14 10/21/2014 Tutor Perini / Zachry/Parsons Administrative Revised Design Variance Request Form $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to an administrative change to revise the form used to request variances to the design criteria used on the project. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John Houseman - DB Oversight Manager
376 CP 1 HSR 13-06 9 10/21/2014 Tutor Perini / Zachry/Parsons Environmental Revised Shear Wave 500-ft Boring $275,227.04 This is a change to a contract for design and construction services in the Central Valley. The reason for the change provides environmental and design services at Fresno and San Joaquin rivers. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John Foster - Project Controls Oversight Manager
377 CP 1 HSR 13-06 17 10/13/2014 Tutor Perini / Zachry/Parsons Administrative Subcontractor Mobilization Expense A $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the language in the contract that determines mobilization requirements of contractor staff to the project. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John Foster - Project Controls Oversight Manager
378 CP 1 HSR 13-06 13 9/4/2014 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related DL 00004 - BETP Task 1 $280,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform pre-construction assessments at 8 properties. Ofelia Alcantara - Director of Design & Construction James Laing - Project Director Rick Stead - DB Oversight Manager
379 CP 1 HSR 13-06 12 9/4/2014 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Archaeological Field Inventory $180,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide archeological inventories to meet the Authority's environmental commitments. Ofelia Alcantara - Director of Design & Construction James Laing - Project Director Rick Stead - DB Oversight Manager
380 CP 1 HSR 13-06 7 9/4/2014 Tutor Perini / Zachry/Parsons Environmental CL1/CL2 HazMat $5,250,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to define the quantity and price for hazardous material removal and disposal in the contract. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
381 CP 1 HSR 13-06 10 8/7/2014 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Weed Abatement - Various Locations $300,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to cleanup vegetation and debris at property owned by the Authority. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
382 CP 1 HSR 13-06 8 8/7/2014 Tutor Perini / Zachry/Parsons Administrative DRB 3rd Member $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change revises the contract language regarding Dispute Resolution Board membership. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
383 CP 1 HSR 13-06 5 8/7/2014 Tutor Perini / Zachry/Parsons Administrative Local/ Long Distance Phone Charges $79,546.85 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay for Authority phone costs at office space provided by the general contractor for Authority's use per the contract. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
384 CP 1 HSR 13-06 6 7/3/2014 Tutor Perini / Zachry/Parsons Administrative DRB Expenses $180,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay the Authority’s share of Dispute Resolution Board costs for the project. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
385 CP 1 HSR 13-06 3 6/30/2014 Tutor Perini / Zachry/Parsons Administrative SP20 Invoicing Changes $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the Special Provisions Section 20 of the contract. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
386 CP 1 HSR 13-06 4 6/19/2014 Tutor Perini / Zachry/Parsons Administrative IBM Rational Doors $7,987.34 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide one IBM Rational Doors authorized user license to the Authority (requirements management software). Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
387 CP 1 HSR 13-06 2 6/19/2014 Tutor Perini / Zachry/Parsons Administrative Partnering Costs $108,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct partnering workshops and meetings between the contractor and the Authority for the project. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
388 CP 1 HSR 13-06 1 6/2/2014 Tutor Perini / Zachry/Parsons Administrative Addition of Copiers and Printer $40,527.99 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide two copiers and a printer for Authority use. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director James Hanningan - Construction Oversight Manager
389 CP 2/3 HSR 13-57 00045.20 6/29/21 Dragados/Flatiron Joint Venture Administrative Escalation Costs - April 2021 $342,772 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for escalation for the month of April 2021 which is calculated pursuant to the formula set forth in Change Order 45.1. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
390 CP 2/3 HSR 13-57 00252 6/29/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Telecommunications_Video Surveillance Services or Equipment $35,404 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the “Video Equipment Replacement Work”, which includes the cost to replace and install video surveillance equipment at project storage yards and office facilities at the following locations: Selma HUB Office, Segment 1 Field Office, Segment 3 Field Office. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
391 CP 2/3 HSR 13-57 00256 6/29/21 Dragados/Flatiron Joint Venture Administrative Costs related to DTSC – Approved Soil Sampling Workplan not covered by CO 115 $60,742 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the soil sampling, testing, and analysis required by the California Department of Toxic Substances (DTSC) for the property located at the former PureGrow Facility in Corcoran, California purchased by the Authority for the project. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
392 CP 2/3 HSR 13-57 00257 R1 6/29/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Sempra - Avenue 24 $1,984,054 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for Directive Letter No. 98 (DL 98) instructing DFJV to design and construct the Avenue 24 undercrossing in Tulare County. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
393 CP 2/3 HSR 13-57 00155.1 6/21/21 Dragados/Flatiron Joint Venture Administrative Additional Bond Costs $11,106,009 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is additional direct costs of performance and payment bond premiums in excess of: (1 ) the $77,000,000 line item in the Signature Document base contract price (FRA Cost Code 40-FC-8005 Mobilization, Insurance, and Bonds), (2) the $14,470,000 paid under Change Order No. 00045.1 for the extension of the revised Substantial Completion Deadline to February 14, 2022 and increase in the contract price to $1,909,641,887. Brian Kelly - CEO Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
394 CP 2/3 HSR 13-57 00240 6/11/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Crotch Bumble Bee Survey $26,113 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is because the Crotch Bumble Bee (CBB) was added to the California Endangered Species List on June 18, 2019, requiring an amendment to the Authority’s Master Streambed Alteration Agreement (MSAA) with the California Department of Fish and Wildlife (CDFW). The Authority subsequently issued Directive Letter 128 (DL 128) instructing DFJV to draft a survey protocol for the CBB to include habitat suitability analysis and survey methodology and to coordinate with the Project Biologist, Randi McCormick, and the Authority and to present the protocol to CDFW for review and approval, collectively the “CBB Protocol Work”. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
395 CP 2/3 HSR 13-57 00168.2 6/4/21 Dragados/Flatiron Joint Venture Environmental Extended Environmental Scope Services $2,992,956 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional costs arising out of delay-related changes to the project schedule addressed by Change Order 45 (CO 45) and Change Order 45.1 (CO 45.1), whereby the Substantial Completion Deadline for the Project was extended from August 19, 2019 to February 14, 2022. As a result of the extension of the Substantial Completion Date, it became necessary to expand the scope of environmental compliance work provided by subcontractor Dudek Environmental Services (Dudek) during construction activities giving rise to a compensable change pursuant to General Provision 17.2(16). Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
396 CP 2/3 HSR 13-57 00249 6/1/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Soft Soils - Segment 3 $212,313 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to carry out all the analyses required to delineate the extent of ground improvements needed for the Segment 3 South embankment footprint south of Avenue 56, including, but not limited to, Flac3D modeling that was performed at the request of the Authority to refine the CVR estimates from the WinSASW analyses and delineate which areas and which soil layers need to be mitigated through ground improvement. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
397 CP 2/3 HSR 13-57 00045.19 5/27/21 Dragados/Flatiron Joint Venture Administrative Escalation Costs - March 2021 $640,128 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the for all the accumulative escalation costs for the month of March 2021 described in and pursuant to executed Change Order 00045.1 Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
398 CP 2/3 HSR 13-57 00045.18 5/21/21 Dragados/Flatiron Joint Venture Administrative Escalation Costs - February 2021 $302,525 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the for all the accumulative escalation costs for the month of February 2021 described in and pursuant to executed Change Order 00045.1 Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
399 CP 2/3 HSR 13-57 00045.17 5/21/21 Dragados/Flatiron Joint Venture Administrative Escalation Costs - January 2021 $500,179 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the for all the accumulative escalation costs for the month of January 2021 described in and pursuant to executed Change Order 00045.1 Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
400 CP 2/3 HSR 13-57 00197.2 4/20/2021 Dragados/Flatiron Joint Venture Third Party Related BNSF Form B Delays $31,232.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the extra costs incurred due to BNSF's cancellations for flaggers and not providing the Form B coverage required for the DFJV's referenced subcontractor to perform the construction Work at Wristen Ditch. The dates of these Form B cancellations are 6/19/2020, 7/20/2020, 7/21/2020, and 7/27/2020. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
401 CP 2/3 HSR 13-57 00250.1 4/16/2021 Dragados/Flatiron Joint Venture Third Party Related Kings County Water District (KCWD) – Improvements at Batti Basin $37,789.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the Work to furnish and install trash racks for the box culvert at the east side of Batti Basin directed by the Authority to implement Kings County Water District (KCWD) new requirement. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
402 CP 2/3 HSR 13-57 00239 4/16/2021 Dragados/Flatiron Joint Venture Third Party Related Cross Creek Clearance $19,750.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design Work to implement the Authority issued “Directive Letter No. 00121 Cross Creek North/South Side Access” in accordance with Corcoran Irrigation District’s (Corcoran ID) access requirements for the North/South Side Access to Cross Creek. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
403 CP 2/3 HSR 13-57 00197.1 4/16/2021 Dragados/Flatiron Joint Venture Third Party Related BNSF Form B Delays $18,122.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the extra costs incurred due to BNSF's cancellations for flaggers and not providing the Form B coverage required for the DFJV's referenced subcontractor to perform the construction Work at Conejo Ave. The dates of these Form B cancellations are 7/17/2020, and 07/23/2020. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
404 CP 2/3 HSR 13-57 00197.3 4/16/2021 Dragados/Flatiron Joint Venture Third Party Related BNSF Form B Delays $56,485.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the for the extra costs incurred due to BNSF's cancellations for flaggers and not providing the Form B coverage required for the DFJV's referenced subcontractor to perform the construction Work at Mountain View Ave. The dates of these Form B cancellations are 07/24/2020, 7/27/2020, and 7/28/2020. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
405 CP 2/3 HSR 13-57 00250 4/14/2021 Dragados/Flatiron Joint Venture Third Party Related Kings County Water District – Batti Basin Trash Racks $58,460.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional Work to design the trash racks for the box culvert at Batti Basin directed by the Authority per Kings County Water District new requirement. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
406 CP 2/3 HSR 13-57 00024.20 4/16/2021 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Hazardous Materials – 9909 Ponderosa Rd $24,596.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the demolition Work for the concrete slab removal and disposal of Asbestos containing hazardous materials located at 9909 Ponderosa Road. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
407 CP 2/3 HSR 13-57 00243 4/16/2021 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Fresno County Design Exceptions/Betterments $438,757.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the design, preparation of exhibits, coordination, and conceptual submittals for Fresno County in order to address out of scope and betterment requests regarding design speeds, criteria, and applicable standards. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
408 CP 2/3 HSR 13-57 00232 4/16/2021 Dragados/Flatiron Joint Venture Changes to Plans and Specifications IPB Redesign to Eliminate Retaining Wall $842,934.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the cost of the additional design Work to revise the design for the Intrusion Protection Barrier (IPB) requirements per the Authority issued Directive Letter No. 00043.4 and Request for Information (RFI) No.771.1 which represents a change to Third Party Standards, Directive Drawings, and Design Criteria Manual requirements. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
409 CP 2/3 HSR 13-57 00245 3/3/21 Dragados/Flatiron Joint Venture Environmental Segment 3 South Additional Geophysical Testing $82,897.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the Work is for additional geophysical testing for Segment 3 - South. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
410 CP 2/3 HSR 13-57 00244 3/3/21 Dragados/Flatiron Joint Venture Environmental Soil Sampling, Analysis & Reporting for HSRA / DTSC at 6505 Nevada Ave. $40,639.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the Soil Sampling, Analysis & Reporting for HSRA/DTSC at 6505 Nevada Ave. (Former Pure Gro Facility Site). Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
411 CP 2/3 HSR 13-57 00238 3/3/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Asphalt Grindings/Dust Control at Holt Property $82,366.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the Work to furnish, place, and maintain asphalt grindings as dust control measures so that DFJV could utilize the Holt property (FB-16-0459) to access the test piles on the south side of Cross Creek. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
412 CP 2/3 HSR 13-57 00248 3/3/21 Dragados/Flatiron Joint Venture Third Party Related Revised Track Embankment $660,243.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform extra design modification/construction work related to the Alpaugh Irrigation District’s (“AID”) Reservoir Nos. 2 & 3 levees and Deer Creek Viaduct area pursuant to HSRA’s issuance of three Directive Letters (DLs) #’s 00111, 00111.1 and 00111.2. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
413 CP 2/3 HSR 13-57 00229 3/3/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Harlan Stevens (Winery) – Vent Modification Study $9,556.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the vent design modification study directed by HSRA for the Harlan Stevens Ditch at the Vie Del Winery property. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
414 CP 2/3 HSR 13-57 00247 3/3/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Conejo IPB RFC Wall Plans $13,225.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design Work per the Authority issued Directive Letter Nos. 43 through 43.5 for submittal and preparation for a separate IPB Ready for Construction (RFC) Wall plan set for two retaining walls (T110 and T112) adjacent to the Conejo Viaduct structure. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
415 CP 2/3 HSR 13-57 00241 3/3/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Segment 3 Settlement $298,620.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design Work for the evaluation of settlement time periods in Segment 3 South and the development of schedule mitigation measures for four affected structures related to settlement: Stoil Spur, station 3675+98, Avenue 24, and Deer Creek. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
416 CP 2/3 HSR 13-57 00246 3/3/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Extra Work / Expansion of Precast Yard $3,774,352.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional construction Work to be performed as outlined in Construction Memo No. 227, dated September 11, 2020. DFJV is to clear and grub the excess land and for the expansion of the precast yard to develop the EBC Farms property adjacent to its precast yard to increase storage capacity. This Change Order is a schedule mitigation measure. Work to be performed at the following parcels FB-16-0440-1,-2,-4,-5 and FB-16-0119-1. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
417 CP 2/3 HSR 13-57 00231 3/1/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Nevada OH Elimination, Irrigation, and Access Road Revisions $71,693.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the redesign Work per the Authority issued Directive Letter No. 00099 “ Revise Select Kings County Locations per Settlement Agreement.” Per the Directive Letter, Nevada Avenue is to be closed at the High-Speed Rail (HSR) alignment and DFJV is to address impacts due the overpass elimination. Nevada Avenue east of HSR alignment will be closed by cul-de-sac and the intersection of SR-43 and Nevada Avenue will be closed to the east. The scope of services required by the implementation of DL 00099 shall include the addition of a Cul-De-Sac for Nevada Avenue and associated design associated with the roadway and drainage. Ben Ruiz - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
418 CP 2/3 HSR 13-57 00242 2/19/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Out of Sequence Work – Dover Avenue $1,493,542 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the out of sequence construction Work to build the embankment on East/West Dover and South 8th Avenue. In accordance with the Project Schedule, the roadway embankments at Dover Avenue and South 8th Avenue were to be constructed during concurrent with the guideway embankment that took place between June 2020 and October 2020. Due to late removal of the interfering PG&E utilities, the roadway embankments could not be constructed as originally planned by DFJV. The scope of this Change Order covers the following additional scope of work as a result of the inability to construct as originally planned. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
419 CP 2/3 HSR 13-57 00045.16 2/19/21 Dragados/Flatiron Joint Venture Administrative Escalation Costs - December 2020 $879,147 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the for all the accumulative escalation costs for the month of December 2020 described in and pursuant to executed Change Order 00045.1 Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
420 CP 2/3 HSR 13-57 00206 2/19/21 Dragados/Flatiron Joint Venture Administrative PG&E Provisional Sum Task Order 30.4 – Addendum to Task Order 30.Bldg.Rental $104,908 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the payment for the rental Building 76 located at 1775 Park Street, Selma, CA, which is an addition to the office space required per Book 1, Part B.1 – 13 of the Special Provisions. The payment will be paid for the rental period starting on April 1, 2020 through March 31, 2022. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
421 CP 2/3 HSR 13-57 00176 2/19/21 Dragados/Flatiron Joint Venture Third Party Related South Avenue Temporary PG&E Line Conflict $384,678 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for a specialty crane (MLC300 385-ton crawler crane) and associated crane mats, additional crane de-mobilization and mobilizations required to cross the BNSF track, as required to avoid a conflicting PG&E power line. This Work was performed to mitigate schedule delays. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
422 CP 2/3 HSR 13-57 00218 2/19/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Tied Arch Bridge 1H-03 Highland – CAWF 42 Girders and Isolation Bearings $1,870,088 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction Work to fabricate and deliver the concrete precast floor beams (CAWF 42 Girders) and the Isolation Bearings for the SR43 Concrete Tied Arch Bridge. This is a supplemental Change Order for the super-structure portion of the SR43 Concrete Tied Arch Bridge while the super-structure is being finalized. An adjustment to the costs will be made accordingly in the final Change Order for the super-structure. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
423 CP 2/3 HSR 13-57 00234 2/9/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Placed Shoulder Backing $203,284 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional construction Work per the Authority issued “Directive Letter No. 00136 Placed Shoulder Backing,” which requires DFJV to place shoulder backing material, 3-feet, on both shoulders of Cedar Avenue between Elkhorn Avenue and Conejo Avenue in Fresno County, in accordance with specifications in Section 19-9 “Shoulder Backing” of the Caltrans 2015 Standards Specifications. The Authority has elected to use the low-price proposal (Papich Construction) submitted by the DFJV and acknowledges that the pricing assumes that the material generated onsite will meet the Shoulder Backing specification noted above. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
424 CP 2/3 HSR 13-57 00137.1 1/29/21 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Storage Issues at Pre-Cast Yard $4,943,442 This is a change to a contract for design and construction services in the Central Valley. The reason is for the relocation of the Tub Girder production for the bridges listed below to Authority right-of-way near Cole Slough: Kings River Bridge, Dutch John Cut Bridge, Cole Slough Bridge, Conejo Bridge Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
425 CP 2/3 HSR 13-57 00233 1/29/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Sweeper Civil Works $570,580 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional cost and design Work for the Type 1 structures required per the Authority issued “Directive Letter (DL) No. 00105 Sweeper Civil Work”, with the exclusion of item 1 (design of the stairways) in DL 00105. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
426 CP 2/3 HSR 13-57 00168.1 1/26/21 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Extended Environmental Scope (Dudek Invoices) $2,579,837 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is additional environmental compliance Work resulting from the Right-of-Way (ROW) delays. These costs are from April 1st, 2020 to July 31st, 2020. Additional costs beyond these dates will be evaluated in accordance with the Contract. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
427 CP 2/3 HSR 13-57 00227 1/26/21 Dragados/Flatiron Joint Venture Third Party Related Kings County Utility Agreement $108,230 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to redo all design submittal packages to Kings County due to the Kings County Utility Agreement executed on June 8, 2020, which requires DFJV/Jacobs to resubmit all design submittal packages which were previously approved by the Authority on majority of the Kings County crossings submittals. This change incurred due to the Authority issued “Directive Letter No. 00006 Project Submittals to Kings County and Directive Letter No. 00055 Use of Zumwalt Hanson and Associate as Kings Co. Representative”. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
428 CP 2/3 HSR 13-57 00230 1/20/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Caltrans Pavement 40 Year Design Life $6,693 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design Work to update the pavement design life for Roadway Pavements to 40 years per Caltrans Highway Design Manual (HDM) 2018 revisions which changed pavement design life from 20 to 40 years. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
429 CP 2/3 HSR 13-57 00045.15 1/20/21 Dragados/Flatiron Joint Venture Administrative Escalation Costs - November 2020 $908,783 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for all the accumulative escalation costs for the month of November 2020 described in and pursuant to executed Change Order 00045.1 Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
430 CP 2/3 HSR 13-57 00194 1/20/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Provide Sand for Stuber Property FB-16-0243 $13,441 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to supply sand to the property owner of FB-16-0243 per the Authority issued “Directive Letter No. 00107 Diaz Property FB-16-0144, FB-16-0145 and Stuber Property FB-16-0243”. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
431 CP 2/3 HSR 13-57 00213 1/20/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Pure Grow (DTSC) HazMat Stockpile/Disposal $666,678 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction Work for excavation, stockpiling, transportation, and disposal of Non-RCRA materials currently known at this time, approximately 5990.29 tons for the previously unidentified pesticide laden hazardous materials at the Pure Grow site and will haul it to Clean Harbors, a cost-effective disposal facility that will accept this material at the Buttonwillow location in California. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
432 CP 2/3 HSR 13-57 00202 1/20/21 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related BNSF CP Bowles Remobilization $700,568 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the three additional mobilizations for the construction Work to complete the CP Bowles Work to mitigate delays in Right-of-Way delivery. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
433 CP 2/3 HSR 13-57 00224 1/20/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Demolition at Gray Property at Ponderosa $9,416 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction Work for remobilization and trucking disposal of materials at a private property structure on FB-16-0132 located at the Ponderosa Subdivision. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
434 CP 2/3 HSR 13-57 00225 1/20/21 Dragados/Flatiron Joint Venture Third Party Related Priority Irrigation Packages $143,760 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design Work resulting from preparing separate design submittals to mitigate Right-of-Way (ROW) delays for the following irrigation facilities: Consolidated Irrigation District (CONSID) - Priority 2, Fresno Irrigation District (FID) - Priority 2, Kings County Water District (KCWD) - Priority 2, Peoples Ditch Company (PDC) - Priority 2, Lakeside Ditch Company (LDC) - Priority 2, JG Boswell (JGB) - Segment 3 - Priority 2, Corcoran Irrigation District (CORCID) - Segment 3 Priority 1, Corcoran Irrigation District (CORCID) - Segment 3 Priority 2 Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
435 CP 2/3 HSR 13-57 00226 1/20/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Nebraska Multiple Span Addition $456,562 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design Work to extend the bridge at Nebraska Avenue by three additional spans and add retaining walls to support the roadway embankment to the east of the structure. In addition to designing the new bridge spans and retaining wall configuration, Jacobs must reevaluate and revise the roadway embankment, drainage system, and utilities in and adjacent to the revised structure footprint per the Authority issued “Directive Letter No. 61.2 Nebraska Multiple Span Addition”. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
436 CP 2/3 HSR 13-57 00228 1/20/21 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Harlan Steven Winery $45,425 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design Work and scope change as part of the ongoing coordination with the Vie-Del Winery, DFJV shall modify the standpipe design and the concrete collar connection to the east of the BNSF mainline tracks for the Harlan Stevens Ditch - North Pipe design package. These modifications to the standpipe connection east of BNSF are required to allow for the future redevelopment of the winery facilities and the operation of truck traffic over and across the planned Corcoran Irrigation District (CID) project improvements for the Harlan Stevens (Winery) Irrigation Canal per the Authority issued “Directive Letter No. 00125 Harlan Stevens Ditch - North Pipe Standpipe Modification”. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
437 CP 2/3 HSR 13-57 00193 1/7/21 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Settlers Branch RCB Shoring- Hanford Armona $176,117 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional construction Work to install shoring to mitigate delays due to delays in right of way acquisitions necessary for PG&E overhead lines relocations. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
438 CP 2/3 HSR 13-57 00217 12/29/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Track Packages_NDCs $76,518 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design work to provide the “Track Package Notice of Design Changes (NDCs) design submittal packages, due to Delayed Geotech Data to support the advancement of RFC Track packages by defining what portions of the package have the final geotechnical information that is available to proceed to construction. The NDCs were prepared as a mitigation measure in order to advance the design per Directive Letter (DL) No. 00042 “Use of Geotechnical Baseline Report for Bid”. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
439 CP 2/3 HSR 13-57 00220 12/29/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Impact due to Design Hold at the 90% $149,272 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design Work per the Authority issued “Directive Letter (DL) No. 00042 Use of Geotechnical Baseline Report for Bid” provided direction to advance the design to a pre-RFC stage utilizing the GBR-B and other geotechnical information provided to the DFJV during bid phase for areas where access has not been available to perform geotechnical exploration activities. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
440 CP 2/3 HSR 13-57 00191 12/29/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Wildlife Entrap Ramp Irrigation $40,908 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the Final design Work to design (11) wildlife escape ramps within irrigation district facilities as described in the Authority issued “Directive Letter No. 00106 CDFW – Escape Ramps” Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
441 CP 2/3 HSR 13-57 0024.19 12/29/20 Dragados/Flatiron Joint Venture Environmental Hazardous Materials – 2742 8 ½ Ave. and Cairo Ave. $76,084 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the cost of the remediation Work to be performed on a Time and Material Basis (T&M) for the abatement of hazardous waste materials of the asbestos and lead contamination at 2742 8 ½ Avenue and Cairo Avenue. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
442 CP 2/3 HSR 13-57 00223 12/22/20 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Additional Field Exploration $2,297,312 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional costs incurred (between April 15, 2018 and July 24, 2020) associated with the geotechnical field exploration program due to delayed delivery of the Right-of-Way (ROW) per the Right-of-Way Acquisition Plan (ROWAP). Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
443 CP 2/3 HSR 13-57 00199 12/22/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Critical Velocity 3D Validation/Modeling $755,453 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the design work and computer software to implement a numerical modelling for the CP2-3 embankment design using 3D FEM. The design work includes submittal of technical Report (Geo-Dynamic 3D Modelling of Track Bed and Rail Embankment), technical analysis of the soft soil Segment 3 South area (SEG3S) conditions, and the technical collaborative effort necessary to issue DL 074, DL 109, 109.1, and 110. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
444 CP 2/3 HSR 13-57 00221 12/21/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Use of GBR-B for GEDR/GDR’s to Advance Design $2,079,682 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design Work to develop multiple Geotechnical Engineering Design Reports (GEDRs) using the Geotechnical Baseline Report — Bid (GBR-B) to advance the Design and updating the GEDRs and Geotechnical Data Report (GDR) as new geotechnical data is available from field investigation as a mitigation measure per the Authority issued Directive Letter No. 00042 “Use of Geotechnical Baseline Report for Bid”. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
445 CP 2/3 HSR 13-57 00219 12/18/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Additional GEDR Revisions $387,569 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design Work for developing multiple Geotechnical Engineering Design Reports (GEDRs) using the Geotechnical Baseline Report – Bid (GBR-B) to advance the Design and updating the GEDRs and Geotechnical Data Report (GDR) as soon as new geotechnical data is available from the field investigation. The additional GEDR revisions are per the Authority issued Directive Letter No. 00042; “Use of Geotechnical Baseline Report for Bid”. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
446 CP 2/3 HSR 13-57 00045.14 12/17/20 Dragados/Flatiron Joint Venture Administrative Escalation Costs - October 2020 $914,233 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the for all the accumulative escalation costs for the month of October 2020 described in and pursuant to executed Change Order 00045.1 Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
447 CP 2/3 HSR 13-57 00185 12/17/20 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related AT&T Temporary Relocation at Elkhorn $150,996 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction Work for a temporary AT&T relocation for mitigation due to the ROW delays on the start of the Elkhorn civil structure. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
448 CP 2/3 HSR 13-57 00204 12/17/20 Dragados/Flatiron Joint Venture Third Party Related BNSF East Access Road $264,789 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design Work to implement the changes requested by BNSF on the track realignment packages for CP Bowles, CP Monmouth, and Conejo Siding. Jacobs will design an east side access road and create additional CPUC exhibits to show accessibility to the proposed overhead structures along the BNSF corridor. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
449 CP 2/3 HSR 13-57 00205 12/17/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Tule River SR 43 Detour Change $145,659 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design work to revise the Tule River SR43 Detour MOT Plan. This bypass is a mitigation measure to allow the construction of the bridges to progress sooner and to prevent the compaction of work activities associated with the schedule critical path. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
450 CP 2/3 HSR 13-57 00207 12/17/20 Dragados/Flatiron Joint Venture Third Party Related Irrigation Phased Construction Plans $51,035 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design Work for the phased construction plans for the Fresno Irrigation District (FID) crossing the BNSF ROW in the northern most six miles of the alignment for CP 2-3 due to the lack of a Relocation and Construction (R&C) agreement between the Authority and BNSF. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
451 CP 2/3 HSR 13-57 00208 12/17/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Dias and Stuber Property $57,799 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional costs incurred due to the Authority issued “Directive Letter (DL) No. 00107 Dias and Stuber Property” to perform testing of the HSR embankment for human waste from STA 1867+10 to STA 192+00at 200 feet intervals. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
452 CP 2/3 HSR 13-57 00211 12/17/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications H&H Reports $262,569 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design Work and cost incurred in creating and processing Hydrology & Hydraulics (“H&H”) sub-Reports due to related ROWs not being delivered in the manner and timeframes as indicated in the Contract. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
453 CP 2/3 HSR 13-57 00222 12/17/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Intrusion Protection Barrier (IPB) Part 3 $1,235,242 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design Work to revise the design for the Intrusion Protection Barrier (IPB) requirements per the Authority issued “Directive Letter No. 00043.4 Intrusion Protection Barrier” and Request for Information (RFIs) Nos.715 and 716 which represents a change to Third Party Standards, Directive Drawings, and DCM requirements. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
454 CP 2/3 HSR 13-57 00173 11/25/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Unforeseen Field Conditions - Unknown $22,493 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the additional construction Work for the removal of unforeseen irrigation line buried below subgrade at four separate locations. Station S604+50: Removal of unforeseen Irrigation Line buried below subgrade. Station S681+50: Removal of unforeseen Irrigation Line buried below subgrade. Station 707+00 to 709+10: Removal of unforeseen Irrigation Line buried below subgrade. Station S897+00: Removal of unforeseen Irrigation Line buried below subgrade. FB-10-0385-3 Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
455 CP 2/3 HSR 13-57 00186 11/24/20 Dragados/Flatiron Joint Venture Administrative BNSF Westside Access Road $79,593 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for all Final Design Work effort required to revise the BNSF West Side Access Road plans resulting from the issuance of Directive Letter 43.4 and RFI 715. Directive Letter 43.4 changed the design of the Intrusion Protection Barrier. The changes in turn impacted the BNSF West Side Access Road plans, which required revisions. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
456 CP 2/3 HSR 13-57 00200 11/24/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications CIDH Piles at Tule River Viaduct $537,373 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the extra costs incurred for the stand-by costs for the specialized Drilling Equipment (Bauer BG 45 Rotary Drilling Rig Drill and SCC Crane) between March 24, 2020 and October 16, 2020 (146 Working days), due to the Authority failure to deliver the Right-of-Way (ROW) by March 1, 2020, specifically the parcels necessary for the western alignment of the Tule River Viaduct, which resulted in further delays in the relocation of several utilities (PG&E power lines, Gas and Water lines) that interfere with the construction activities and use of the specialized equipment. Supplemental costs will be evaluated in accordance with the Contract. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
457 CP 2/3 HSR 13-57 00201 11/24/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications CIDH Remobilization – Tule River Viaduct $316,407 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction Work at Tule River Viaduct. DFJV and its subcontractor will erect equipment for drilling CIDH piles at bents 3E thru 6E will re-mobilize the CIDH equipment on the east side of the Tule River over to the west side of the Tule River as a mitigation measure due to the Right-of-Way (ROW) delays. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
458 CP 2/3 HSR 13-57 00197 11/20/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications BNSF Form B Delays $132,736 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for extra costs incurred due to BNSF’s cancellations for flaggers and not providing the Form B coverage required for the DFJV’s referenced subcontractor to perform the construction Work. The dates of these Form B cancellations are 9/20/19, 9/26/19, 9/27/19, 10/3/19, 10/4/19, 10/18/19 and 10/28/19. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
459 CP 2/3 HSR 13-57 00198 11/20/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Intrusion Protection Barrier - DESIGN ONLY Part 2 $2,011,079 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional Part 2 design Work to revise the design for the Intrusion Protection Barrier requirements along railroad corridors in the Design Criteria Manual per the Authority issued Directive Letter 43.3 Intrusion Protection Barrier. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
460 CP 2/3 HSR 13-57 00203 11/20/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Taylor Ditch - DESIGN ONLY $311,144 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for final design Work to redesign the Taylor Ditch irrigation facility that requires modification as part of incorporating a maintenance access road on the western edge of the BNSF existing and future rights-of-way per the issued Authority Directive Letters (DL)00078/78.1 "Jack & Bore Irrigation Facilities Impacted by BNSF Westside Road”. This Change Order also compensates DFJV for incorporation of the design of pipe collars into the current design plans for Taylor’s Ditch design per issued Authority Directive Letter No. 00118. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
461 CP 2/3 HSR 13-57 00050.2 11/19/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications AAAT Bike – Pedestrian Underpass - DESIGN ONLY $2,825,675 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction Work to construct a bikeway and pedestrian underpass for Atwell Island/Atwell/Allensworth Trail (AAAT) at Station 3809+66 of the HSR alignment per Authority issued Directive Letter Nos. 63 and 63.1 and per RFC plan set 1 002 029. Civil work includes grading and access restriction fencing work. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
462 CP 2/3 HSR 13-57 00179 11/19/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Areas Available to Work — Out of Sequence S3 $3,956,911 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the out of sequence Work for installation of guideway embankment between Station 3729+00 to 3753+50 (Area A), and Station 4013+50 to 4045+55 (Area K) “Phase I” as shown on Exhibit 1 (GE-A0007-S3P2). This out of sequence work is a mitigation measure to the ROW procurement delays due to late ROW delivery, delayed third party relocations and environmental clearances. This Change Order will allow potential early construction starts with modified sequence. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
463 CP 2/3 HSR 13-57 00188 11/19/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Lawrence Ditch - DESIGN ONLY $86,001 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is for the additional design Work to incorporate Lower Tule River Irrigation District (LTRID) request for design changes at Lawrence Ditch. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
464 CP 2/3 HSR 13-57 00212 11/19/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Lansing Avenue Underpass $4,952,329 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction Work of the Lansing Avenue Wreden Ranch (Agricultural) Underpass at HSR Station S2, 2462+13.14, per the Authority issued “Directive Letter No. 00075.1 Agricultural Underpass at Lansing Avenue.” DFJV will construct the underpass as shown on plan set 1 002 072_Pre-A_S1134_RFC_Seg2_Lansing Ave UP Plans dated Mar 29, 2019. The DFJV has anticipated constructing this Work in one continuous operation and no phasing is included in the price. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
465 CP 2/3 HSR 13-57 00215 11/19/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications DOORS Architecture $1,535,917 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for technical and administrative Work to restructure the Requirement Management (RM) database according to Directive Letter No. 00104 DOORS ARCHITECTURE. Except as modified by Directive Letter No. 00104. No Verification and Validation or other CP2-3 contract requirements are eliminated or superseded. This Change Order compensates SENER for Time and Materials (T&M) work through August 31, 2020 and the remaining Lump Sum work for both SENER and the DFJV through the Revised Substantial Completion Deadline as noted in CCO No. 0045.1. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
466 CP 2/3 HSR 13-57 00214 11/18/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Salvador Ditch North $2,399,592 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for construction Work at Salvador Ditch North as revised due to the construction of Lansing Avenue Wreden Ranch (Agricultural) Underpass at HSR Station S2, 2462+13.14. DFJV will construct the Canal improvements as shown on plan set 1 001 4 32_NDC138_S0494_IRR_JGB_P2-S2_Salvador_For_District_Approval Plans as prepared by Jacobs dated 5/28/2020 per the new requirement from JG Boswell. The DFJV has anticipated constructing this Work in one continuous operation and no phasing is included in the price. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
467 CP 2/3 HSR 13-57 00045.13 11/12/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Escalation Costs – September 2020 $903,757 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the accumulative escalation costs for the month of September 2020 described in and pursuant to executed Change Order 00045.1. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
468 CP 2/3 HSR 13-57 00177 11/2/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Pacific Rim Dairy Ponds – Increased Earthwork Quantities $2,257,120 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for construction Work for the changed conditions at Pacific Rim Dairy Ponds. Increasing Earthwork Quantities in the amount of 70,892 cubic yards due to configuration changes per “Directive Letter No. 00062 Te Velde Canal” and from HSRA ROW /parcel acquisition delays, as depicted in the Lower Tule Irrigation District plans and cross-sections attached. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
469 CP 2/3 HSR 13-57 0086.12 11/2/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Private Irrigation Crossing Segments 1&2 $720,558 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for final construction efforts required to install steel casings in the trackway embankment for crossings of privately owned irrigation facilities. The location and quantity of casings have been confirmed through Requests For Information (RFI). Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
470 CP 2-3 HSR 13-57 86.13 10/31/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Private Irrigation Crossing Segments 2 $919,540.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for all final construction efforts required to install steel casings in the trackway embankment for crossings of privately owned irrigation facilities. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
471 CP 2-3 HSR 13-57 45.12 10/27/20 Dragados/Flatiron Joint Venture Administrative Escalation Costs - August 2020 $1,000,635 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for all the accumulative escalation costs for the month of August 2020 described in and pursuant to executed Change Order 00045.1. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
472 CP 2-3 HSR 13-57 174 10/23/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Agricultural Debris – FB 10-0446 $11,648 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction Work per direction of the Authority for the removal and disposal of agricultural debris from the remaining property that the landowner placed onto the acquired Project Right-of-Way (ROW) (FB-10-0446). Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
473 CP 2-3 HSR 13-57 183 10/16/20 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Silveira Box Culvert Ave 156 DESIGN $56,287 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional design Work to revise the dimensions of the box culvert structure at FB-54-0201, Silveira. The size of the three season undercrossing at approximately Sta 2983+00 shall be revised to a 15’ x 25’ box culvert structure per the Authority issued Directive Letter (DL) No. 00059.1 “Silveira Box Culvert Increased Height”. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
474 CP 2-3 HSR 13-57 178 10/12/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Salvador South Irrigation Crossing - DESIGN $109,020 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the redesign Work per the new requirement from JG Boswell to redesign the Salvador South irrigation crossing from a 60” reinforced concrete pipe (RCP) to a 5’ x 5’ reinforced concrete box culvert (RCBC). at Flint Avenue. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
475 CP 2-3 HSR 13-57 184 10/12/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Corcoran Hatching - DESIGN $95,984 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the design work to resequence for Corcoran Irrigation District facilities. This added scope of work is a mitigation measure implemented in order to advance the design to construction. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
476 CP 2-3 HSR 13-57 187 10/13/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Tied Arch Bridge Pt. 2 - DESIGN $1,066,898 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional design Work not included in prior Change Order 00105. These additional costs are for the structures design progression at (IH-03) SR43 Tied Arch Bridge-90% through RFC Design & Prior to Final Design (PFD) Packages, Roadway MOT Plans per Directive Letter (DL) 82, Redesign per DL 42 & Submittals, Comment Resolution & Third-Party Coordination. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
477 CP 2-3 HSR 13-57 86.11 10/12/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Private Irrigation Crossing Segments 2 $1,548,756 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the all final constructionb efforts required to install steel casings in the trackway embankment for crossings of privately owned irrigation facilities. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
478 CP 2-3 HSR 13-57 171 10/12/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Cairo Ave. Kings County Settlement - DESIGN $142,703 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for redesign Work and construct the Cairo Avenue structure and roadway that removes any curves from the Cairo Avenue roadway and extends the Cairo Avenue structure to maintain a 32-foot clear roadway at Cairo Avenue per Authority issued Directive Letter (DL) No. 00099 “Revise Select Kings County Locations per Settlement Agreement”. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
479 CP 2-3 HSR 13-57 172 10/12/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Early Start Work – Discing First 6 Miles $613,164 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is for the construction Work to start the Early Start scope of work, discing for the north 6 miles of Segment 1, weeding, and maintaining the parcels to begin construction of the HSR alignment within the first six miles per Authority direction. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
480 CP 2-3 HSR 13-57 164 10/5/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Hanford Viaduct – Precast Plant Additional Forms/Modifications $7,206,869 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction Work for the additional forms and modifications to the precast plant in preparation for the Hanford Viaduct. Elias Mahfoud - Director of Design and Construction Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
481 CP 2-3 HSR 13-57 92 10/2/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications GTC – Drive Piles at Excelsior Avenue $238,150 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is additional equipment mobilization at Excelsior Avenue to perform the precast pile installation, this change on equipment size was necessary due to the changes to the embankment slope caused by interfering utilities. The pile installation is part of the overall effort to accelerate construction of the foundation piles at Excelsior Overhead Structure prior to completion of the roadway embankment as a mitigation measure due to the delay in delivery of the Right-of-Way (ROW). Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
482 CP 2-3 HSR 13-57 168 10/5/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Extended Environmental Scope (Dudek Invoices) $4,930,386 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional environmental compliance Work resulting from the Right-of-Way (ROW) delays. These costs are from August 1, 2019 through March 31, 2020. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
483 CP 2-3 HSR 13-57 175 10/8/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Hanford Viaduct - DESIGN $5,089,302 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for final design Work, to design the 6400-foot-long Hanford Viaduct Structure at the Kings/Tulare Regional Station in the vicinity of HSR overcrossing SJVR rail line to replace current at grade HSR track section design, including associated design work for irrigation, roadway, drainage, utilities, geotechnical, and redesign of the Grangeville Blvd. UP. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
484 CP 2-3 HSR 13-57 182 10/8/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Additional Efforts GBRC - DESIGN ONLY $2,765,276 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional Final Design Work to provide multiple GBR-C reports as a pre-requisite for the Ready for Construction (RFC) design submittal package. The multiple GBR-C reports were prepared as a mitigation measure in order to advance the design per Directive Letter (DL) No. 00042 “Use of Geotechnical Baseline Report for Bid”. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
485 CP 2-3 HSR 13-57 157 9/28/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Bevins Lateral Irrigation $805,245.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction Work to furnish and install all required material to relocate the Bevins Lateral Irrigation Facility as well as install the steel casing and carrier pipe at Floral Avenue per the issued Authority Directive Letter No. 00078.1 “Jack & Bore" Irrigation Facilities Impacted by BNSF Westside Road” per plan set 1 001 636 RFC 1 S0698 S1 CID P1D Bevins PLANS. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
486 CP 2-3 HSR 13-57 163 9/28/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Lawrence Ditch $5,375,264.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction work to install 48” RGRCP pipe and to tie into original Lawrence Ditch in new junction structure – bore and jack installation under BNSF using Jack-and-Bore methodology per the Authority Directive Letter No. 00062 “Te Velde Canal” and Directive Letter No. 00078.1 “Jack & Bore Irrigation Facilities impacted by BNSF Westside Road”. Elias Mahfoud - Director of Design & Construction Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
487 CP 2-3 HSR 13-57 180 9/28/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Modify OH Widths Flint,Fargo,Idaho $172,914.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for all final design Work effort required to redesign the Flint Avenue, Fargo Avenue and Idaho Avenue Overhead widths to 32’.The revisions to the widths of the three overheads were a result of the settlement agreement between the Authority and Kings County and the DFJV was given direction through Directive Letter (DL) No. 00099 to perform the design revisions. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
488 CP 2-3 HSR 13-57 189 9/28/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Lawrence Ditch Temp Bypass $98,939.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design Work for a temporary bypass drainage system at Lawrence Ditch in order to advance construction and a permanent detour structure that will facilitate construction at Flint Avenue. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
489 CP 2-3 HSR 13-57 150 9/25/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Caltrans SPR5 SR43_Corcoran HWY Pkg. $9,199.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design required by Caltrans at SR43 and Corcoran Highway Intersection (Work beyond Project Footprint, but within Caltrans sphere of influence). Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
490 CP 2-3 HSR 13-57 165 9/25/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Jackson Avenue Embankment $713,663.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction work at Jackson Avenue. DFJV will re-sequence the embankment operation to utilize on-highway haul to truck the material on-road down the alignment to the Jackson Avenue bridge embankment as a mitigation measure in order to meet the dates currently shown on the draft Revised Baseline Schedule under review by the Authority. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
491 CP 2-3 HSR 13-57 166 9/25/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Sweet Canal $266,315.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction Work to install the reinforced box culvert at the Sweet Canal. DFJV will perform the work in two phases as a mitigation measure due to the delays associated with the ROW delivery needed to perform the entire Sweet Canal relocation. Then DFJV will follow back to complete the RCBC and irrigation shift after complete delivery of ROW (Phase 2) not included in this Change Order. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
492 CP 2-3 HSR 13-57 170 9/25/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Daily Site Security and Maintenance Checks $222,013.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the Work for providing daily site security and maintenance checks to the Right-of-Way (ROW) parcels due to the delay of delivery for the ROW from April 14, 2017 to September 10, 2018 . It was agreed between DFJV and CHSRA that a daily inspection program is necessary and DFJV implemented a rotating inspection program to record the condition of delivered parcels and assigned one individual to visit all delivered parcels to identify any required actions, for safety, security, or general maintenance during the ongoing ROW delay. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
493 CP 2-3 HSR 13-57 45.11 9/25/2020 Dragados/Flatiron Joint Venture Administrative Escalation Costs - July 2020 $792,547.00 This is a change to the contract for design and construction services in the Central Valley. The reason for this change is for all the accumulative escalation costs for the month of July 2020 described in and pursuant to Executed Change Order 00045.1 Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
494 CP 2-3 HSR 13-57 167 9/23/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Davis SW Quadrant Shared Driveway $59,052.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the final design Work to update the design at Davis Avenue Roadway to incorporate the location of the “shared driveway” to be shifted from the current location per the Authority’s direction in Directive Letter No. 00102 “Revision to Davis Avenue Roadway Plans”. Ben Ruiz- Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
495 CP 2-3 HSR 13-57 151 9/14/2020 Dragados/Flatiron Joint Venture Administrative PGE Provisional Sum $90,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to increase the PG&E Provisional Sum by the amount of $90,000,000 from the original amount of $160,000,000 to $250,000,000. Joe Hedges - Chief Operating Officer Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
496 CP 2-3 HSR 13-57 162 8/26/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Tule River Detour/Bypass $3,076,896.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction Work to install and completely remove a temporary detour/bypass around the bridge construction at the Tule River location. This bypass is a mitigation measure to allow the construction of the bridges to progress sooner and to prevent the compaction of work activities associated with the schedule critical path. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
497 CP 2-3 HSR 13-57 45.10 8/21/2020 Dragados/Flatiron Joint Venture Administrative Escalation Costs - June 2020 $599,785.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for all the accumulative escalation costs for the month of June 2020 described in and pursuant to executed Change Order 00045.1. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
498 CP 2-3 HSR 13-57 161 8/21/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Shoring on People's Ditch at Flint Avenue - Design Only $5,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design Work per the Authority’s direction to implement the shoring design for the work on People’s Ditch Company (PDC) at Flint Avenue. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
499 CP 2-3 HSR 13-57 158 8/21/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Alpaugh Well Removal - Design Only $14,418.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the redesign Work per the direction of the Authority for the well removal at Alpaugh Irrigation District west of SR-43 and north of Avenue 56. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
500 CP 2-3 HSR 13-57 153 8/10/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Loss of Ditch Excavation-Subsidence $61,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is construction work for loss of ditch excavation per Directive Letters (DL) Nos. 00035, 00069 and Contract Change Order (CCO) 00097. This Change Order covers all costs for the additional import, haul, and placement of embankment materials needed along the HSR alignment for the embankment construction in the areas as described in Change Order Proposal (COP) No. 35.3 and for the import, haul, and placement of additional HSR embankment material necessary to mitigate subsidence along the mainline track required in areas where the design could not be modified to mitigate the effects of subsidence occurring between 2011 and 2015 (as reflected in the 2015 Lidar survey performed in accordance with DL-00012 and CCO 00005, the “2015 Lidar Survey”) Joe Hedges - Chief Operating Officer Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
501 CP 2-3 HSR 13-57 160 8/5/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Hanford HST Access Road - Design Only $66,953.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the design Work to design the Hanford HST Access Road alignment, profile and design a new intersection between the HST Access Road and Hanford-Armona Road. Ben Ruiz - Acting Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
502 CP 2-3 HSR 13-57 149 7/28/2020 Dragados/Flatiron Joint Venture Administrative Additional Project Biologist Coordination CDFW $30,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to facilitate expedited approvals of preconstruction deliverables to the California Department of Fish and Wildlife (CDFW). Through this Change Order, The California High-Speed Rail Authority (Authority) is directing Dragados/Flatiron Joint Venture (DFJV) to make their Project Biologist, Ms. Randi McCormick, available to participate in weekly meetings with CDFW. Ben Ruiz for Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
503 CP 2-3 HSR 13-57 159 7/27/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Intrusion Protection Barrier Yield Line Theory Analysis $35,770.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the revised design Work per direction of the Authority for DFJV to use the Yield Line Theory Analysis for the design of the Intrusion Protection Barrier. For development and Quality Control (QC) calculation for use in the IPB redesign going forward, presenting the results to the Authority and incorporate their comments and update plans to include the revised design. Ben Ruiz for Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
504 CP 2-3 HSR 13-57 155 7/23/2020 Dragados/Flatiron Joint Venture Administrative Insurance Costs $18,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for certain additional direct costs of insurance premiums in excess of: (1) the $77,000,000 line item in the Signature Document base contract price (FRA Cost Code 40-FC-8005 Mobilization, Insurance, and Bonds), and (2) the $14,470,000 paid under Change Order No. 00045.1 to extend coverage for the time extension and increase in Contract price therein. The insurance costs shall be paid on a direct, dollar-for-dollar pass-through basis as incurred. Joe Hedges - Chief Operating Officer Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
505 CP 2-3 HSR 13-57 86.10 7/16/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Private Irrigation Crossings - Segment 2 $538,820.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for all final construction Work efforts required to install steel casings in the trackway embankment for crossings of privately owned irrigation facilities. Ben Ruiz for Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
506 CP 2-3 HSR 13-57 156 7/16/2020 Dragados/Flatiron Joint Venture Administrative Fresno County - Concurrent Roadway Closure at Adams/South Avenue $1,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional permitting costs pursuant to General Provisions (G.P.) Section 49.4.10, due to a change in the terms of the Cooperative Agreement with the County of Fresno. The additional permitting costs being imposed by County of Fresno are for impacts caused by the public traffic delays resulting from the concurrent closures of Adams and South Avenues. The concurrent roadway closure at Adams and South Avenues is planned for 270 days for the construction operation at Adams and South Avenues. The closure will facilitate construction of overcrossing at Adams and South Avenues over the existing BNSF railroad and the future High-Speed Rail alignments concurrently. Ben Ruiz for Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
507 CP 2-3 HSR 13-57 154 7/16/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Tule River Relocate Gas Line $314,058.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction Work to Relocate the gas line at the Tule River Viaduct to be completed in 2 Phases, north of Tule River and under Tule River. Ben Ruiz for Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
508 CP 2-3 HSR 13-57 45.9 7/9/2020 Dragados/Flatiron Joint Venture Administrative Escalation Costs - May 2020 $441,274.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for all the accumulative escalation costs for the month of May 2020 described in and pursuant to executed Change Order 00045.1 Ben Ruiz for Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
509 CP 2-3 HSR 13-57 24.18 7/9/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications HazMat — Asbestos/Transite Pipe Segment 3@ Various Locations $121,170.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction Work to be performed on a Time and Material (T&M) basis for the abatement of hazardous waste materials to remove and dispose of the Asbestos/Transite Pipe at various locations, Newark Avenue, Van Dorsten Avenue and Corcoran Highway in Segment 3. Ben Ruiz for Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
510 CP 2-3 HSR 13-57 148 6/22/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Hanford Viaduct Substructure and Grangeville Blvd. Underpass $99,114,327.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for all the construction Work at Hanford Viaduct Substructure and the Type 1 structure at Grangeville Boulevard. Joe Hedges - Chief Operating Officer Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
511 CP 2-3 HSR 13-57 45.8 6/19/2020 Dragados/Flatiron Joint Venture Administrative Escalation Costs_April 2020 $1,900,511.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for all the accumulative escalation costs for the month of April 2020 described in and pursuant to executed Change Order 00045.1. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
512 CP 2-3 HSR 13-57 140 6/16/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Tied Arch Bridge - 1H-03 Highland $1,785,616.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for all the the identified substructure portion of Work related to Bridge 1H‐03 "Tied Arch." A subsequent Contract Change Order will be issued to DFJV for all remaining superstructure work for this bridge. Cost items in this substructure change include: Piles (assumed lengths), Abutment Footings, Wing Walls, and Back wall as well as the portion of costs related to substructure for Maintenance of Traffic (MOT), SWPPP, Survey, QC/QA. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
513 CP 2-3 HSR 13-57 145 6/11/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Lawrence Canal BNSF Jack and Bore $132,520.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the Final Design Work to revise the design to extend Lawrence irrigation canal east underneath the BNSF tracks utilizing jack-and-bore methods. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
514 CP 2-3 HSR 13-57 147 6/4/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Fowler Ave. Detour/Bypass for Elkhorn and Davis Avenues $1,532,877.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the design and construction work to install and the complete removal of the temporary detour/bypass around the bridge construction at Fowler, Elkhorn and Davis Avenues locations as a mitigation measure to construct the bridges to progress work sooner and to prevent the compaction of work activities later with other critical path activities. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
515 CP 2-3 HSR 13-57 146 6/4/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications BNSF CAD Standards for Irrigation Pkgs. Davis/Elkhorn Ditch $23,359.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the Final Design Work to resubmit the design drawings for Elkhorn Ditch and Davis Ditch to BNSF CAD Standards for Irrigation Packages. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
516 CP 2-3 HSR 13-57 128 6/4/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications BNSF Track Work $4,429,498.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the construction Work to move the BNSF track storage from the RFP proposed Conejo track storage sidings, which are located approximately between milepost (MP) 981 and 982 to the Bowles relocation area between MP 987 and 990. This directive work shall include shifting of the sidings to reduce impacts at Manning Avenue grade separation and modify the South Avenue grade separation per the issued Authority Directive Letter No. 00047 – BNSF Coordination Solutions at Conejo Siding and per plan set drawings 1 001 328_PRE_C_S0390_BNSF_CPBOWLES. western edge of the BNSF existing and future rights-of-way Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
517 CP 2-3 HSR 13-57 144 5/14/2020 Dragados/Flatiron Joint Venture Third Party Related Jack and Bore Irrigation Facilities - Design Only $531,533.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the Final Design Work to redesign the (8) Irrigation facilities that require modification as part of incorporating a maintenance access road on the western edge of the BNSF existing and future rights-of-way Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
518 CP 2-3 HSR 13-57 45.7 5/14/2020 Dragados/Flatiron Joint Venture Administrative Escalation Costs - March 2020 $1,171,420.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for all the accumulative escalation costs for the month of March 2020 described in and pursuant to executed Change Order 00045.1. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
519 CP 2-3 HSR 13-57 45.6 5/14/2020 Dragados/Flatiron Joint Venture Administrative Escalation Costs - February 2020 $1,388,381.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for all the accumulative escalation costs for the month of February 2020 described in and pursuant to executed Change Order 00045.1. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
520 CP 2-3 HSR 13-57 45.5 5/6/2020 Dragados/Flatiron Joint Venture Administrative Escalation Costs - January 2020 $1,646,117.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for all the accumulative escalation costs for the month of January 2020 described in and pursuant to executed Change Order 00045.1. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
521 CP 2-3 HSR 13-57 142 5/5/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Jackson Avenue and Idaho Avenue Detour/Bypass $1,180,909.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the install and for the complete removal of the temporary detour/bypass for the construction of Jackson Avenue and Idaho Avenue bridges as a mitigation measure to construct the bridges to progress work sooner and to prevent the compaction of work activities later with other critical path activities. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
522 CP 2-3 HSR 13-57 135 5/4/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Kie Con Pile Storage Fees-Adams Avenue $31,030.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the costs of the storage fees to store the concrete pile for the Adams Avenue Bridge. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
523 CP 2-3 HSR 13-57 24.1.3 4/29/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications HazMat Abatement UST/NAC Disposal FB-10-0388 $8,455.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the added scope resulting from remediation costs associated with abatement of hazardous materials due to an underground storage tank (UST), located at 2287 E. Floral Avenue, Fresno, CA (FB-10-0388), as identified in property assessment on September 1, 2017 and the Moore Twining lab tests for the UST and surrounding soils taken on August 31, 2018 and for the disposal of the Vac Tank Contents and UST disposal. The UST identified needed to be rinsed and removed from the site. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
524 CP 2-3 HSR 13-57 139 4/29/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Elimination of Iona Avenue Overcrossing - DESIGN ONLY $9,000.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the elimination of Iona Avenue Overcrossings and to design cul-de-sacs on each side of the High-Speed-Rail Tracks on Iona Avenue as required per Authority Directive Letter No.00073, Elimination of Iona Avenue Overcrossing. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
525 CP 2-3 HSR 13-57 10.11 4/29/2020 Dragados/Flatiron Joint Venture Third-Party Related Ave. 136 Extension East to SR 43 - DESIGN ONLY $34,470.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is because of Avenue 136 extending east to SR 43 per RFI 00587 response “Tulare County Utility Agreement that 0.43 miles is the length of the roadway improvements that the improvements shall extend east to SR 43”. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
526 CP 2-3 HSR 13-57 129 4/28/2020 Dragados/Flatiron Joint Venture Third-Party Related BNSF Westside Maintenance Road - DESIGN ONLY $1,375,913.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is to design and prepare construction plans for the BNSF Westside Access Road in reference to the Authority's Directive Letter No. 00078, Implementation of BNSF Westside Access Maintenance Road within BNSF right-of-way. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
527 CP 2-3 HSR 13-57 24.17 4/28/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications HazMat – Treated Wood Waste at Hwy.43/FB-10-0479 $194,174.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the added scope resulting from remediation costs associated for the abatement of hazardous waste materials to remove and dispose of the Treated Wood Waste at Hwy. 43 and (FB-10-0479). Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
528 CP 2-3 HSR 13-57 143 4/27/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Reduce Impact to Dairy @ Houston Ave. - DESIGN ONLY $87,393.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design a 300-foot-long retaining wall on the southeast quadrant of the Houston Avenue Grade Separation per Authority Directive Letter No. 00071.1 to Reduce Impact to Dairy at Houston Avenue Grade Separation. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
529 CP 2-3 HSR 13-57 24.16 4/27/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications HazMat - Treated Wood Waste at Davis Avenue $49,637.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the added scope resulting from remediation costs associated for the abatement of hazardous waste materials to remove and dispose of the Treated Wood Waste at Davis Avenue (FB-10-0474-1, -3, -4, -6, -7). Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
530 CP 2-3 HSR 13-57 141 4/24/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Kings River Complex Trestle $4,796,474.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the construction work to install, maintain and the complete removal of the temporary Trestle for the construction of the Kings River Viaduct as a mitigation measure to construct the viaduct in less time than originally anticipated. Construction impacts, if any, associated with the construction of the Kings River Viaduct from the temporary Trestle are not included in this Change Order. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
531 CP 2-3 HSR 13-57 65.1 4/7/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications GTC - Flint Avenue $995,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is because of the impact on the construction of the bridge structures. DFJV will construct the west side embankment and to start the bridge settlement period. DFJV will remobilize to complete the west embankment once the utility has been relocated and will construct the remaining embankment. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
532 CP 2-3 HSR 13-57 113 3/30/2020 Dragados/Flatiron Joint Venture Third-Party Related Flow Capacity at Wristen Ditch $5,739,371.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is a change in law to require doubling the flow capacities at several areas by the Consolidated Irrigation District (CID) resulting in an increase in the scope of the contract. Elias Mahfoud, Director of Infrastructure Delivery (CEA B) Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
533 CP 2-3 HSR 13-57 121.1 3/28/2020 Dragados/Flatiron Joint Venture Administrative Hanford Viaduct Reallocation $0.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for reallocation of budgets within the contract amount. This is a net zero cost change order. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
534 CP 2-3 HSR 13-57 136 3/26/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications GTC - Embankment Const Nevada-Ave144 $14,666,140.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the additional costs to utilize on road trucking and additional mobilizations to complete the construction work for constructing the embankment from Nevada Avenue to Avenue 144. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
535 CP 2-3 HSR 13-57 109.1 3/26/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Project Floodplain Limit Increases $22,283,480.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is because there was a change in the limits of the FEMA floodplain within the project limits resulting in an increase in the scope of the contract. Joe Hedges, COO, CHSRA Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
536 CP 2-3 HSR 13-57 131 3/20/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications South Ave. Jack Bore RC Agrmnt TM $42,055.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is because BNSF had not executed a Relocation and Construction Agreement (“R&C”). This change compensates the Contractor for additional mobilization costs incurred due to the delay in execution of the R&C Agreement. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
537 CP 2-3 HSR 13-57 138 3/20/2020 Dragados/Flatiron Joint Venture Administrative Secondary Pre-Cast Girders Storage -- Police Escorts. $652,000.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change work for Police escorts required to transport the Project precast elements from the existing precast yard location to the secondary precast storage yard through Fresno County to be paid on a Time and Material (T&M) basis as costs are incurred. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
538 CP 2-3 HSR 13-57 137 3/20/2020 Dragados/Flatiron Joint Venture Administrative Precast Girders Storage $4,925,000.00 This is a change to a contract for design and construction services in the Central Valley. This change was executed as a mitigation to on-going project delays, to develop a secondary storage area for the Project precast girder elements (467 each), including transportation of these precast girder elements from an existing precast yard to a secondary storage area, and unloading of these girders at the secondary storage area. This change allows the Contractor to continue production of precast elements for the project. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
539 CP 2-3 HSR 13-57 133 3/20/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Barcelos Water Service Connection $375,236.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is to furnish and install up to 3,200 linear feet of 16in diameter permanent PVC water line adjacent to the existing basin within Parcels HSR# FB-54-0003-2 and 0003-3 and to backfill and compact 1,100 linear feet of existing irrigation ditch as needed. The property owner north of Avenue 144 requires a private water service connection to a private irrigation ditch. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
540 CP 2-3 HSR 13-57 132 3/20/2020 Dragados/Flatiron Joint Venture Administrative ROI Acquisition Addtl ROW Utl. Reloc $387,272.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional work associated with the Report of Investigation (ROI) Reports for ROW Utility Relocations. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
541 CP 2-3 HSR 13-57 127 3/20/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Maintenance Access Roads Under Type 2 Structures $2,100,413.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is because of the requirement for a maintenance access ramp and a maintenance access bench at the Type 2 Bridge Structures, a change in the requirements from the Directive Drawings, resulting in an increase in scope of the contract. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
542 CP 2-3 HSR 13-57 126 3/20/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications 10" HDPE Level 3 Overholser-Kamm Ave $492,048.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is BNSF changed its pre-bid requirements, requiring casings for utilities crossing the BNSF right-of-way, resulting in an increase in the scope of the contract. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
543 CP 2-3 HSR 13-57 125 3/20/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications 10" HDPE Level 3 - Conejo Avenue $189,428.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is BNSF changed its pre-bid requirements, requiring casings for utilities crossing the BNSF right-of-way, resulting in an increase in the scope of the contract. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
544 CP 2-3 HSR 13-57 124 3/20/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications 10" HDPE Level 3 Sumner-Huntsman Avenues $606,248.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is BNSF changed its pre-bid requirements, requiring casings for utilities crossing the BNSF right-of-way, resulting in an increase in the scope of the contract. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
545 CP 2-3 HSR 13-57 80.1 3/20/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Unidentified Additional Waterline at 4 1/2 Avenue $377,858.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for an unidentified additional waterline that was not shown in the RFP documents. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
546 CP 2-3 HSR 13-57 45.4 3/20/2020 Dragados/Flatiron Joint Venture Administrative Escalation Costs_December 2019 $412,220.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to resolve delay related escalation costs for the month of December 2019 due to late delivery of the Project right-of-way by the Authority. CO 45.1 allowed for payment of escalation costs beginning August 1, 2019 thru the end of the project.” Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
547 CP 2-3 HSR 13-57 10.10 2/12/2020 Dragados/Flatiron Joint Venture Third-Party Related TCO Ave 24 Redsgn GW Above Elevation $306,448.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional out of scope design work for the Avenue 24 Underpass. This change order is pursuant to an Authority agreement with Tulare County to add an underpass at Avenue 24. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
548 CP 2-3 HSR 13-57 120 2/12/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications New Caltrans Requirements for ITS , Barrier and Traffic Lines $35,310.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is a revision in Caltrans design standards for ITS, Traffic Barriers, and Traffic Lines. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
549 CP 2-3 HSR 13-57 119 2/12/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Wristen Ditch - Design $105,037.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design work resulting from a change in design standards due to new legislation regarding groundwater sustainability. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
550 CP 2-3 HSR 13-57 117 2/12/2020 Dragados/Flatiron Joint Venture Third-Party Related Corcoran Design Speed Reduction $74,900.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design costs resulting from a change in local agency design standards for local agency roadways. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
551 CP 2-3 HSR 13-57 94 2/12/2020 Dragados/Flatiron Joint Venture Environmental Conejo Viaduct CIDH Test Pile $1,031,196.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the inefficiencies associated with the Authority directed early installation of three test piles at the Conejo Viaduct within the restricted area of the incidental take permit footprint. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
552 CP 2-3 HSR 13-57 45.3 2/12/2020 Dragados/Flatiron Joint Venture Administrative Escalation Costs_November 2019 $1,427,172.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to resolve delay related escalation costs for the month of November 2019 due to late delivery of the Project right-of-way by the Authority. CO 45.1 allowed for payment of escalation costs beginning August 1, 2019 thru the end of the project.” Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
553 CP 2-3 HSR 13-57 45.2 2/12/2020 Dragados/Flatiron Joint Venture Administrative Escalation Costs_Aug Sept Oct 2019 $2,509,853.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to resolve delay related escalation costs for the months of August, September and October 2019 due to late delivery of the Project right-of-way by the Authority. CO 45.1 allowed for payment of escalation costs beginning August 1, 2019 thru the end of the project.” Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
554 CP 2-3 HSR 13-57 86.9 2/8/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Private Irrigation Crossings Segment 2, Parcel FB-16-0006 $165,385.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is addition in scope to install steel casings in the trackway embankment for the crossings of privately owned irrigation facilities at Parcel FB-16-0006. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
555 CP 2-3 HSR 13-57 24.15 2/8/2020 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement - FB-10-0398 $23,315.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the added scope resulting from remediation costs associated with abatement of hazardous materials as identified in an Asbestos and Lead Survey report (ASR). The ASR identified lead based paint in the structure to be demolished, requiring lead abatement. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
556 CP 2-3 HSR 13-57 86.8 1/30/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Private Irrigation Crossing Segment 2, Parcel FB-16-0063 $106,930.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is required to install steel casings in the trackway embankment for crossings of privately owned irrigation facilities at Parcel FB-16-0063. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
557 CP 2-3 HSR 13-57 86.6 1/30/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Private Irrigation Crossing Segments 1, 2, and 3 $468,392.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is required to install the steel casings in the trackway embankment for the crossings of privately owned irrigation facilities.. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
558 CP 2-3 HSR 13-57 60.1 1/30/2020 Dragados/Flatiron Joint Venture Administrative Alpaugh Irrigation District Permit $80,000.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is to allow the Contractor access to complete work in coordination with the Alpaugh Irrigation District. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
559 CP 2-3 HSR 13-57 121 12/14/2019 Dragados/Flatiron Joint Venture Administrative Hanford Viaduct Reallocation of Activity ID's Budgeted Amount. $0.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for reallocation of Activity ID's Budgeted Amount. This is a net zero cost change order. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
560 CP 2-3 HSR 13-57 86.7 12/6/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Private Irrigation Crossing Segment 1 $244,872.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for relocation of privately owned irrigation facilities. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
561 CP 2-3 HSR 13-57 86.5 12/6/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Private Irrigation Crossings Design $255,685.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the design for Private Irrigation Crossings Casings per the Authority’s Construction Memos. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
562 CP 2-3 HSR 13-57 10.9 12/6/2019 Dragados/Flatiron Joint Venture Third-Party Related Tulare County Roadway Improvement in compliance with Sub-Utility Agreement $1,343,756.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the construction costs related to Avenue 24 reconstruction Work from Road 72 to Road 80 as part of Tulare County Sub-Utility Agreement 1.07. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
563 CP 2-3 HSR 13-57 116 12/5/2019 Dragados/Flatiron Joint Venture Third-Party Related Davis Avenue Ancillary Redesign $40,219.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is to accommodate relocating the Pacific Gas and Electric relocation within the existing right-of-way. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
564 CP 2-3 HSR 13-57 111 12/5/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications State Route 43 Crossing near Tule River-3H-17 $1,123,500.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the design work as required to revise the design (change in law) to meet Caltrans future expansion of State Route 43 crossing near the Tule River (Bridge 3H-17). Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
565 CP 2-3 HSR 13-57 106 12/5/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Caltrans Median Study $133,750.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is Caltrans changed both its Standard Specifications and Transportation Concept Report after the Proposal Deadline. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
566 CP 2-3 HSR 13-57 118 11/23/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Hanford Viaduct Precast Concrete Piling Order $2,898,450.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is a time and material change of precast conrete pile to be used for construction of the Hanford Viaduct structure. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
567 CP 2-3 HSR 13-57 45.1 11/20/2019 Dragados/Flatiron Joint Venture Administrative Agreement for Settlement, Release and Waiver for (1) Time Impacts and Delays Through July 31, 2019; (2) Certain Disputes $133,930,912.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change order is to resolve delays, delay related impacts and specific disputes with the contractor. Please see the change order for an explicit listing of resolved disputes. Joe Hedges - Chief Operating Officer Jose Luiz Mendez - President, Dragados/Flatiron Alberto Lopez - State Senior Contract Manager
568 CP 2-3 HSR 13-57 114 10/12/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Ancillary Facility Site Changes $137,214.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the design work for the modified ancillary facility locations, as well as the additional design effort to finalize the ancillary facility locations. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
569 CP 2-3 HSR 13-57 105 9/27/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications State Route 43 Crossing Kings River (1H-03) $791,800.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for redesign work. Caltrans issued the State Route 43 Ultimate Transportation Concept Report (TCR) which included implications for the design of California High Speed Rail Authority Bridge 1H-03 after Dragados/Flatiron Joint Venture (DFJV) was awarded the project. A study was performed by DFJV to determine the specific impacts of the TCR at the Kings River (DFJV Bridge 1H-03). The optimum Alternative identified in the DFJV study that facilitated the required Caltrans 62’ median width at this location and did not affect the California High Speed Rail profile was a single span concrete tied arch bridge type. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
570 CP 2-3 HSR 13-57 115 9/23/2019 Dragados/Flatiron Joint Venture Third-Party Related Department of Toxic Substance Control Reimbursement Agreement $13,876.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for reimbursement of paid services to the Department of Toxic Substances Control . Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
571 CP 2-3 HSR 13-57 109 9/6/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Project Floodplain Limit Increases $18,809,463.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is because there was a change in the limits of the floodplain within the project limits and this change occurred well after Contractor could have planned it into its original scope of work. Joe Hedges - Chief Operating Officer Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
572 CP 2-3 HSR 13-57 10.8 9/6/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Tulare County Avenue 136 - Concrete Box Structure and Roadway $5,846,353.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for redesign for a new box structure undercrossing for the High-Speed Rail alignment at Avenue 136 in Tulare County. Joe Hedges - Chief Operating Officer Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
573 CP 2-3 HSR 13-57 24.1.2 9/2/2019 Dragados/Flatiron Joint Venture Environmental Credit from Change Order 24.1 ($2,412.04) This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for remediation costs associated with the abatement of hazardous materials located at 2310 E. Floral Avenue, Selma, CA (FB-10-0708), as identified in the Asbestos Survey Report (ASR) for subject property. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
574 CP 2-3 HSR 13-57 110 9/2/2019 Dragados/Flatiron Joint Venture Utility Relocation CTC FB160291 10" Carrier Pipe $28,355.00 This is a change to the contract for design and construction services in the Central Valley. The change order allows for the installation of a pipe on a specific property. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
575 CP 2-3 HSR 13-57 108 9/2/2019 Dragados/Flatiron Joint Venture Utility Relocation CID 200pct Flow - Iowa Ditch $1,431,274.00 This is a change to the contract for design and construction services in the Central Valley. The change order allows for the relocation of an irrigation facility out of the way of the future high-speed rail system. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
576 CP 2-3 HSR 13-57 107 9/2/2019 Dragados/Flatiron Joint Venture Utility Relocation CID 200pct Flow - Davis Ditch $844,191.00 This is a change to the contract for design and construction services in the Central Valley. The change order increases the size of an irrigation facility under the future high-speed rail system. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
577 CP 2-3 HSR 13-57 103 9/2/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Fargo Redsgn Due Rev ROW Acq. Limits $33,170.00 This is a change to the contract for design and construction services in the Central Valley. The change order fits the design for Fargo Avenue within new land constraints. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
578 CP 2-3 HSR 13-57 24.12.1 8/30/2019 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement Conc. Slab Removal $30,998.00 This is a change to a contract for design and construction services in the Central Valley. The change order allows for the removal of hazardous materials located on high-speed rail right of way Oregon Avenue and Road 19 near Corcoran, CA. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
579 CP 2-3 HSR 13-57 112 8/30/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications South Ave. Grade Separation $982,667.00 This is a change to a contract for design and construction services in the Central Valley. The change order changes the shoulder width of the South Avenue bridge over the high-speed rail system in accordance with Authority’s Directive Letter number 65. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
580 CP 2-3 HSR 13-57 104 8/30/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Type 2 Structure Concrete Barrier $839,950.00 This is a change to the contract for design and construction services in the Central Valley. This change order allows for a re-design of a concrete barrier to a new specification. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
581 CP 2-3 HSR 13-57 101 8/30/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Dover Intersection Sight Distance $42,800.00 This is a change to the contract for design and construction services in the Central Valley. The change order is to design the North 8th Avenue Connector Road to Dover Avenue to miss and protect a tree located along the road. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
582 CP 2-3 HSR 13-57 100 8/30/2019 Dragados/Flatiron Joint Venture Utility Relocation Elkhorn Ditch Relocation Final Dsgn $165,850.00 This is a change to the contract for design and construction services in the Central Valley. The change order is to move an irrigation ditch out of the way of the future high-speed rail system. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
583 CP 2-3 HSR 13-57 95 8/30/2019 Dragados/Flatiron Joint Venture Third-Pary Related Doubling Flow Capacity of Consolidated Irrigation District at Elkhorn Ditch $4,460,874.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is change in law to require doubling the flow capacities to facilities of the Consolidated Irrigation District (CID), which resulted in additional scope to the contract. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
584 CP 2-3 HSR 13-57 24.14 8/30/2019 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 0088.14 $98,094.00 This is a change to a contract for design and construction services in the Central Valley. The change order allows for the removal of hazardous materials from buildings located on high-speed rail right of way on E. Clarkson Avenue and Elkhorn Avenue in the city of Fresno. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
585 CP 2-3 HSR 13-57 24.11 8/30/2019 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement FB-10-0398 $17,969.18 This is a change to a contract for design and construction services in the Central Valley. The change order allows for the removal of hazardous materials from buildings located on high-speed rail right of way on E. Nebraska Avenue in the city of Fresno. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
586 CP 2-3 HSR 13-57 102 8/27/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications City Corcoran Increased Dsgn Speed $124,950.00 This is a change to the contract for design and construction services in the Central Valley. The change order allows for the design of new connector roadways at County roads 5 1/2 Avenue to Niles Avenue; and 5th Avenue to Orange Avenue to comply with the change in criteria for a higher vehicle speed limit. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
587 CP 2-3 HSR 13-57 99 8/27/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications SR43 Ave 88 Struct.Dsgn CALTRANS UTC $84,263.00 This is a change to a contract for design and construction services in the Central Valley. The change order incorporates the 2015 update to the Caltrans Standard Specifications and the Transportation Concept Report for State Route 43 into the construction contract for the design of the Avenue 88 bridge. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
588 CP 2-3 HSR 13-57 98 8/27/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications SR43 Hesse Ave Dsgn Struct.CT UTC $84,263.00 This is a change to a contract for design and construction services in the Central Valley. The change order incorporates the 2015 update to the Caltrans Standard Specifications and the Transportation Concept Report for State Route 43 into the construction contract for the design of the Hesse Avenue bridge. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
589 CP 2-3 HSR 13-57 87 8/27/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications E. Lincoln Ave Grade Separation $58,088.16 This is a change to a contract for design and construction services in the Central Valley. The change order develops a design for an underpass for Lincoln Avenue in accordance with Authority’s Directive Letter number 28. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
590 CP 2-3 HSR 13-57 73 7/25/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Primary Type 2 Open Abutments-Const $30,773,032.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change order is to implement new design requirements for bridges over the future high-speed rail system. Joe Hedges - Chief Operating Officer Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
591 CP 2-3 HSR 13-57 97 7/17/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Engineering Solutions to Stay within ROW $1,712,000.00 This is a change to a contract for design and construction services in the Central Valley. This change order allows for completion of the design of trackway drainage, intrusion protection barriers and utility relocations based on revised standards in Directive Letter no. 00035 (DL 35) to stay within Authority's right-of-way. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
592 CP 2-3 HSR 13-57 86.3 7/17/2019 Dragados/Flatiron Joint Venture Third-party Related Segment 2 - Private Irrigation Cross $2,285,989.00 This is a change to a contract for design and construction services in the Central Valley. This change order pays for installation of steel casings to protect private irrigation pipes that cross under the future high-speed rail system. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
593 CP 2-3 HSR 13-57 10.5.1 7/16/2019 Dragados/Flatiron Joint Venture Third-party Related Tulare Co.Force Account Fees $100,000.00 This is a change to a contract for design and construction services in the Central Valley. This change order is for design services and third-party coordination to provide roadway improvements at Avenue 120 and Avenue 24, and reconstruction of a waterline in Tulare County. The work is coordinated by the general contractor in Wasco responsible for designing and constructing the future system. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
594 CP 2-3 HSR 13-57 91 7/16/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Undertrack Conduits $255,291.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design undertrack conduits and implement revised standards in Directive Letter no. 00091 (DL 91). Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
595 CP 2-3 HSR 13-57 81 7/16/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Kings Co. Underpasses at Cairo & 9th $38,520.00 This is a change to a contract for design and construction services in the Central Valley. This change order provides roadway design services for underpasses at Cairo Avenue and 9th Avenue. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
596 CP 2-3 HSR 13-57 78 7/16/2019 Dragados/Flatiron Joint Venture Third-party Related Traffic Studies at Mountain View $4,225.00 This is a change to a contract for design and construction services in the Central Valley. This change order allows for completion of traffic studies on Mountain View Avenue Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
597 CP 2-3 HSR 13-57 70 7/16/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications GTC - Kent & Kansas E/W Embankment $459,495.00 This is a change to a contract for design and construction services in the Central Valley. The change order allow for completion of construction on the embankment between Kent Avenue and Kansas Avenue in Kings County for the future high-speed rail system. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
598 CP 2-3 HSR 13-57 90 5/27/2019 Dragados/Flatiron Joint Venture Utility Relocation UG Ductbanks-Manholes System Sites $236,924.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to complete the design of ductbanks and manholes for the future high-speed rail system. Alberto Lopez, Senior Contract Manager Vicente Alberola, Project Director Patrick E. Jolly, PCM Design-Build Oversight Manager
599 CP 2-3 HSR 13-57 86.4 5/22/2019 Dragados/Flatiron Joint Venture Third-party Related Segment 1, 2, 3 - Private Irrigation $1,055,726.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to construct 10 steel casings to protect private irrigation pipes that cross under the future high-speed rail system. Alberto Lopez, Senior Contract Manager Vicente Alberola, Project Director Patrick E. Jolly, PCM Design-Build Oversight Manager
600 CP 2-3 HSR 13-57 80 5/22/2019 Dragados/Flatiron Joint Venture Utility Relocation Add'l Waterline at 4 1/2 Ave -Design $32,100.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to for additional design associated with an unexpected water line. Alberto Lopez, Senior Contract Manager Vincente Alberola - Project Director Patrick Jolly - DB Oversight Manager
601 CP 2-3 HSR 13-57 89 5/9/2019 Dragados/Flatiron Joint Venture Third-party Related Caltrans 2015-16 6th Edition Update $17,883.00 This is a change to a contract for final design services in the Central Valley. The reason for the change is to complete the design work to implement updates to design required by the 2015 and 2016 changes to the 6th Edition of the Caltrans Highway Design Manual. Alberto Lopez, Senior Contract Manager Vicente Alberola, Project Director Patrick E. Jolly, PCM Design-Build Oversight Manager
602 CP 2-3 HSR 13-57 93 5/3/2019 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related GTC - HOUSTON/IONA TO LANSING $4,700,329.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to complete construction on the embankment between Iona Avenue and Lansing Avenue in Kings County for the future high-speed rail system. Alberto Lopez, Senior Contract Manager Vicente Alberola, Project Director Patrick E. Jolly, PCM Design-Build Oversight Manager
603 CP 2-3 HSR 13-57 77 4/24/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Maint. Access Under Type2 Structures $339,242.43 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete the design of maintenance access for future high-speed rail under bridges. William Grimsley - Director of Design & Construction Vincente Alberola - Project Director Patrick Jolly - DB Oversight Manager
604 CP 2-3 HSR 13-57 76 4/24/2019 Dragados/Flatiron Joint Venture Third-party Related GTC - Wristen Ditch Bypass $392,924.00 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to complete the design and construction work to build a temporary bypass for a drainage ditch to allow construction of a bridge embankment. William Grimsley - Director of Design & Construction Vincente Alberola - Project Director Patrick Jolly - DB Oversight Manager
605 CP 2-3 HSR 13-57 75 4/24/2019 Dragados/Flatiron Joint Venture Third-party Related Special Trk Work Crossover Turnouts $60,545.28 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete the design of track work based on revised standards for train speeds in areas not on the main line track. William Grimsley - Director of Design & Construction Vincente Alberola - Project Director Patrick Jolly - DB Oversight Manager
606 CP 2-3 HSR 13-57 50.1 4/24/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications AAAT Bike Pedestrian U/P Design $413,483.31 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to finalize the design of the bike and pedestrian underpass at the White River crossing. William Grimsley - Director of Design & Construction Vicente Alberola - Project Director Patrick E. Jolly, P.E.- PCM Design Build Oversight Manager
607 CP 2-3 HSR 13-57 24.13 4/24/2019 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.17-FB100876 $11,431.43 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove asbestos in one of the structures to be demolished for the construction of high-speed rail. William Grimsley - Director of Design & Construction Vicente Alberola - Project Director Patrick E. Jolly, P.E.- PCM Design Build Oversight Manager
608 CP 2-3 HSR 13-57 85 4/18/2019 Dragados/Flatiron Joint Venture Differing Site Conditions Subsidence Impacts Various Locations $989,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to purchase, haul and place additional embankment materials to address subsidence at specific locations. William Grimsley - Director of Design & Construction Vincente Alberola - Project Director Patrick Jolly - DB Oversight Manager
609 CP 2-3 HSR 13-57 44.1 3/12/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Increase One Span at Nebraska Ave $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the design of the Nebraska Avenue overcrossing to make it longer. The costs for this change order, $134,426.51, were paid in change order number 48. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick E. Jolly, P.E.- PCM Design Build Oversight Manager
610 CP 2-3 HSR 13-57 1.1 3/12/2019 Dragados/Flatiron Joint Venture Administrative DFJV-HSRA Partnering Costs $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the Authority to meet their contractual obligations to pay 50% of the costs associated with partnering activities. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick E. Jolly, P.E.- PCM Design Build Oversight Manager
611 CP 2-3 HSR 13-57 88 3/9/2019 Dragados/Flatiron Joint Venture Third-party Related Minnewawa Ave. RDWY Improvements $48,150.00 This is a change to a contract for final design services in the Central Valley. The reason for the change is to complete the design of a roadway based on revised standards in Directive Letter no. 00093 (DL 93) to improve Minnewawa Avenue Roadway. Alberto Lopez, Senior Contract Manager Vicente Alberola, Project Director Patrick E. Jolly, PCM Design-Build Oversight Manager
612 CP 2-3 HSR 13-57 86.2 3/4/2019 Dragados/Flatiron Joint Venture Third-party Related Segment 3 - Private Irrigation $469,325.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay for installation of steel casings to protect private irrigation pipes that cross under the future high-speed rail system. William Grimsley, Director of Design & Construction Michael Costa, Project Director Patrick E. Jolly, PCM Design-Build Oversight Manager
613 CP 2-3 HSR 13-57 86.1 3/1/2019 Dragados/Flatiron Joint Venture Third-party Related Segment 2 - Private Irrigation $3,082,679.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay for installation of steel casings to protect private irrigation pipes that cross under the future high-speed rail system. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
614 CP 2-3 HSR 13-57 86 3/1/2019 Dragados/Flatiron Joint Venture Third-party Related Segment 1 - Private Irrigation $1,014,708.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay for installation of steel casings to protect private irrigation pipes that cross under the future high-speed rail system. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
615 CP 2-3 HSR 13-57 83 2/20/2019 Dragados/Flatiron Joint Venture Differing Site Conditions Undisclosed Dump Site $370,446.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete removal and disposal of debris from a dump site that was discovered after the contract was executed. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
616 CP 2-3 HSR 13-57 10.5 2/20/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Ave 120 and Ave 24 Reconstruction $4,679,109.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete construction of road improvements in the County of Tulare. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick E. Jolly, P.E.- PCM Design Build Oversight Manager
617 CP 2-3 HSR 13-57 72 2/8/2019 Dragados/Flatiron Joint Venture Third-party Related CID 200% of Existing Flow Capacity $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete the design of irrigation facilities based on revised standards for flow capacity. The costs for this change order, $34,233, were paid in Change Order number 48. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
618 CP 2-3 HSR 13-57 62 2/8/2019 Dragados/Flatiron Joint Venture Environmental BNSF Bowles Re-Exam $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete the work required to environmentally clear a change to the design negotiated with BNSF. The costs for this change order, $36,916, were paid in Change Order number 48. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
619 CP 2-3 HSR 13-57 53.1 2/8/2019 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Lawrence (Te Velde) Canal $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to finalize the design for the realignment of the Lawrence (Te Velde) canal through the Te Velde Dairy property. The costs for this change order, $179,602.92, were paid in change order number 48. 1 William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick E. Jolly, P.E.- PCM Design Build Oversight Manager
620 CP 2-3 HSR 13-57 41.1 1/31/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Install Spare Conduits_CONSTRUCTION $3,943,136.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to install spare conduits for future use by communication companies. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick E. Jolly, P.E.- PCM Design Build Oversight Manager
621 CP 2-3 HSR 13-57 63 1/16/2019 Dragados/Flatiron Joint Venture Environmental Rare Plant Salvage $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to comply with environmental requirement to preserve and store plant seeds for replanting after the construction. The costs for this change order, $7,500, were paid in Change Order number 48. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
622 CP 2-3 HSR 13-57 71 1/15/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications GTC - CP Bowles Embankment $285,686.00 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to move BNSF railroad track out of the way of the future high-speed rail track. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
623 CP 2-3 HSR 13-57 24.6.1 11/1/2018 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 0088.10.1 $24,399.92 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials from a property acquired by the Authority. William Grimsley - Interim Deputy Director of Infrastructure Delivery Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
624 CP 2-3 HSR 13-57 24.10 11/1/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Haz Mat Abatement COP 88.14, 2 Sites $98,713.19 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the added scope resulting from remediation costs associated with abatement of hazardous materials as identified in an Asbestos and Lead Survey report (ASR). The ASR identified lead based paint in the structure to be demolished, requiring lead abatement. William Grimsley, Director of Infrastructure Delivery (CEA B) Michael Cost Project Manager Patrick E Jolly, PE DB Oversight Manager
625 CP 2-3 HSR 13-57 74 10/16/2018 Dragados/Flatiron Joint Venture Utility Relocation PG&E Facility Work Settlement CO $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to finalize negotiations of disputes regarding PG&E work, specifically regarding sub contractor coordination fees (mark ups), insurance costs and liability, including delays that would impact the contractor's ability to finish on time. William Grimsley - Interim Deputy Director of Infrastructure Delivery Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
626 CP 2-3 HSR 13-57 24.10.1 9/11/2018 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.1 $32,074.62 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous waste from a property owned by the Authority and make the sites safe for work. William Grimsley - Director of Design and Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
627 CP 2-3 HSR 13-57 24.12 9/11/2018 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 0088.16 $60,050.70 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials from a property acquired by the Authority. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
628 CP 2-3 HSR 13-57 24.4.1 7/20/2018 Dragados/Flatiron Joint Venture Environmental HazMat Lead Abatement COP 88.7.1 $286,431.52 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials from a property acquired by the Authority. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
629 CP 2-3 HSR 13-57 24.1.1 7/20/2018 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.9 - 1 Site $15,120.39 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials from a property acquired by the Authority. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
630 CP 2-3 HSR 13-57 67 7/20/2018 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related GTC-Avenue 88 E/W Embankments $1,858,935.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to bring in material for construction at Avenue 88 by a longer route with additional trucking costs. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
631 CP 2-3 HSR 13-57 66 7/20/2018 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related GTC-Fargo Avenue East Embankment $1,715,322.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to bring in material for construction at Fargo Avenue by a longer route with additional trucking costs. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
632 CP 2-3 HSR 13-57 65 7/20/2018 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related GTC-Flint Avenue East Embankment $1,126,716.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to bring in material for construction at Flint Avenue by a longer route with additional trucking costs. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
633 CP 2-3 HSR 13-57 64 7/20/2018 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related GTC-Excelsior Ave E/W Embankments $3,299,700.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to bring in material for construction at Excelsior Avenue by a longer route with additional trucking costs. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
634 CP 2-3 HSR 13-57 60 7/20/2018 Dragados/Flatiron Joint Venture Third-party Related Alpaugh Irrigation District Permit $75,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to finalize negotiations with Alpaugh Irrigation District. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
635 CP 2-3 HSR 13-57 59 7/20/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Study Shift Avenue 56 GS Alignment $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct an impact study of moving the Avenue 56 bridge further south. The costs for this change order, $26,665.39, were paid in Change Order number 48. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
636 CP 2-3 HSR 13-57 58 7/18/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Manning Expressway Cross slope Rev $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to allow future road widening at Manning Avenue. The costs for this change order, $184,681.26, were paid in Change Order number 48. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
637 CP 2-3 HSR 13-57 57 5/9/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Access Restriction Fencing $81,385.04 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to modify the design for fencing to keep people out of the future high-speed rail system. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
638 CP 2-3 HSR 13-57 56 5/9/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Lansing Ave Undercrossing - Design $637,520.35 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design a new crossing under the future high-speed rail system at Lansing Avenue. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Patrick Jolly - DB Oversight Manager
639 CP 2-3 HSR 13-57 55 5/9/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Silveria Box Structure - Design $446,267.02 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design a new crossing under the future high-speed rail system at Avenue 156. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Patrick Jolly - DB Oversight Manager
640 CP 2-3 HSR 13-57 54 5/9/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Hormel Feed Mill Horz Wly Main Shift $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to modify the final route in the vicinity of Hormel Feed Mill to avoid impacts to the mill. The costs for this change order, $285,499.23, were paid in Change Order number 48. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
641 CP 2-3 HSR 13-57 52.1 5/9/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Houston Ave - Fire Station Drvwys $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to modify the design at Houston Avenue to reduce impacts to Kings County Fire Station 4. The costs for this change order, $150,368.02, were paid in Change Order number 48. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
642 CP 2-3 HSR 13-57 35.2 5/3/2018 Dragados/Flatiron Joint Venture Third-party Related Caltrans IQA - Phase 2 ROW ($640,000.00) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement the agreement between the Authority and Caltrans for Caltrans to bill their services on the project directly to the Authority. This change order provides the Authority a credit for removing these activities from the contract. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Patrick Jolly - DB Oversight Manager
643 CP 2-3 HSR 13-57 52 4/24/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Houston Ave Grade Sep Span Reduction $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design the Houston Avenue bridge as a shorter structure. The cost for this work, $147,244.45, is included in change order number 48. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Patrick Jolly - DB Oversight Manager
644 CP 2-3 HSR 13-57 35.1 4/19/2018 Dragados/Flatiron Joint Venture Third-party Related Caltrans IQA - Construction Phase ($4,130,000.00) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement the agreement between the Authority and Caltrans for Caltrans to bill their services on the project directly to the Authority rather than through the general contractor. This change order provides the Authority a credit for removing these activities from the contract. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Patrick Jolly - DB Oversight Manager
645 CP 2-3 HSR 13-57 53 4/10/2018 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Design for Te Velde Dairy (Ave 136) $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete the design for avoidance of the TeVelde Dairy. The cost of this work, $535,010.36 is included in change order number 48. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture
646 CP 2-3 HSR 13-57 36.2 4/3/2018 Dragados/Flatiron Joint Venture Utility Relocation Deductive Change Order - Unilateral ($922,883.00) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to rescind change order numbers 36 and 36.1. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture
647 CP 2-3 HSR 13-57 24.9 3/21/2018 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.13 -5 Sites $116,755.47 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at five properties bought by the Authority. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
648 CP 2-3 HSR 13-57 24.8 2/20/2018 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.12, 1 Site $10,528.77 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at one property in Hanford bought by the Authority. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
649 CP 2-3 HSR 13-57 24.7 2/13/2018 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.11, 2 Sites $26,156.60 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at two properties on E. Floral Avenue in Fresno bought by the Authority. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
650 CP 2-3 HSR 13-57 51 12/29/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications OCS Strcl Conn to Type 1 Aerial Strc $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design future high-speed rail overhead electrical system connections to bridges. Some of the work ($113,555.24) was paid via change order number 48. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
651 CP 2-3 HSR 13-57 50 12/29/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Prepare AAAT Bike/Ped Design Concept $21,379.43 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to prepare the AAAT Bike/Pedestrian Design Concept. Scott Jarvis - Chief of Engineering Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
652 CP 2-3 HSR 13-57 45 12/20/2017 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Time Extension No. 1 $50,750,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to settle and resolve all time delays and impacts prior to August 31, 2017. Thomas Fellenz - Interim Chief Executive Officer Rishard Grabinski - Senior Vice President, Western Region Roy Hill - Chief Program Officer
653 CP 2-3 HSR 13-57 24.6 12/19/2017 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.10 - 1 Site $51,896.64 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at two properties bought by the Authority on E. Floral Avenue in Fresno. Glady Guzman - Design & Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
654 CP 2-3 HSR 13-57 24.5 12/19/2017 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.8 - 1 Site $11,984.72 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove a hazardous underground storage tank on a perperty bought by the Authority. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
655 CP 2-3 HSR 13-57 10.7 12/15/2017 Dragados/Flatiron Joint Venture Environmental Small Mammal Trapping $347,339.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct small mammal trapping as part of the Authority's environmental commitments. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
656 CP 2-3 HSR 13-57 49 12/6/2017 Dragados/Flatiron Joint Venture Environmental Costs Associated with BVLOS $18,785.82 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to protect the Buena Vista Lake ornate shrew as part of the Authority's environmental commitments. Jorge Granados - Design & Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
657 CP 2-3 HSR 13-57 17.1 10/23/2017 Dragados/Flatiron Joint Venture Third-party Related Jurisdictional Waters Add'l Work $11,199.37 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to finish the report authorized in change order number 17 based on additional Authority comments. The report details which permiting agency has jurisdiction over water resources in the Kings River Complex. Glady Guzman - Design & Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
658 CP 2-3 HSR 13-57 36.1 10/12/2017 Dragados/Flatiron Joint Venture Utility Relocation Rescinded - PGE-DFJV Staffing $669,168.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to design and construct the relocation of PG&E facilities to move them out of the way of the future high-speed rail system. Glady Guzman - Design & Construction Manager Michael Costs - Dragados / Flatiron Joint Venture Carlo Sanders - DB Oversight Manager
659 CP 2-3 HSR 13-57 44 10/10/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications DL061, Nebraska Ave GS Design Concep $33,425.55 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide design for a bridge at Nebraska Avenue. Glady Guzman - Design & Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
660 CP 2-3 HSR 13-57 48 10/9/2017 Dragados/Flatiron Joint Venture Administrative Administrative Change Order $2,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement a partnering agreement between the Design-Builder and the Authority. Glady Guzman - Design & Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
661 CP 2-3 HSR 13-57 43 10/9/2017 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related DL 56, Richards, Singh, Bettencourt $49,417.42 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design services at a property impacted by the future high-speed rail system. Glady Guzman - Design & Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
662 CP 2-3 HSR 13-57 42 10/9/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications DL 065, 8' Shoulders South Avenue GS $60,231.21 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design roadway shoulders to a new standard at South Avenue Grade Separation. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
663 CP 2-3 HSR 13-57 41 10/9/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications DL 20.1, Spare Conduits, Design Cost $199,535.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform design and construction of utility conduits under the future high-speed rail system. Gladys Guzman - Design and Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole N Sanders - DB Oversight Manager
664 CP 2-3 HSR 13-57 30.1 10/9/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Open Abutment Supplemental - DL 44.1 $504,587.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to do geotechnical investigations at 28 bridge sites due to a design change. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
665 CP 2-3 HSR 13-57 15.1 10/9/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Early Work Bridge Design Supplement $343,946.68 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform early design work on a bridge. It includes a $1,094,775.39 credit to the Authority for work authorized in change order number 15. Glady Guzman - Design & Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
666 CP 2-3 HSR 13-57 24.4 9/14/2017 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement, COP 88.7, 7 Sites $273,069.13 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at 7 sites. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
667 CP 2-3 HSR 13-57 24.3 9/14/2017 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement, COP 88.6 - 2 Site $120,993.61 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at 3 sites. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
668 CP 2-3 HSR 13-57 40 8/8/2017 Dragados/Flatiron Joint Venture Environmental Increase in required BNLL Surveys $352,490.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide environmental surveys and reports for Blunt Nose Leopard Lizard on additional areas. Gladys Guzman - Acting Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
669 CP 2-3 HSR 13-57 10.6 8/8/2017 Dragados/Flatiron Joint Venture Environmental Tulare Co. Review Cost for Sub-Utili $85,727.76 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to fulfill Tulare County Sub-Utility Agreement 1.01. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
670 CP 2-3 HSR 13-57 24.2 7/13/2017 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement, COP 88.5 - 3 Prop $98,208.59 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at 3 sites. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Michael COsts - Project Director
671 CP 2-3 HSR 13-57 38 7/11/2017 Dragados/Flatiron Joint Venture Environmental Early Work Environmental Re-Exam $218,788.21 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete environmental re-examination and permit amendments associated with advanced designs. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
672 CP 2-3 HSR 13-57 15 7/11/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Early Start Design - 8 Bridges $1,094,775.39 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide proposals to accelerate work. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
673 CP 2-3 HSR 13-57 39 7/7/2017 Dragados/Flatiron Joint Venture Environmental Bio Precon Surveys (ITP) for Geotech $200,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide biological pre-construction clearance surveys in accordance with the Authority's environmental commitments. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
674 CP 2-3 HSR 13-57 33 7/7/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Design Study for DL59, Dover & Silve $9,334.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide design drawings for 8th and Dover and Silveira property. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
675 CP 2-3 HSR 13-57 37 7/3/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Design Study, DL 60, Flood Property $4,927.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide design drawings for Flood Property. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
676 CP 2-3 HSR 13-57 32 7/3/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Design Study for DL57, Elkhorn Ditch $35,739.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide design drawings for Elkhorn Ditch for an alternative route for the future high-speed rail system. Gladys Guzman for Jorge Granados - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
677 CP 2-3 HSR 13-57 29.1 6/12/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Dudek's Early Start Staffing $57,138.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide environmental services to accelerate the start of construction. Jorge Granados, P.E. - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
678 CP 2-3 HSR 13-57 24.1 5/24/2017 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.3 and 88.4 $142,712.55 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials from a property acquired by the Authority. Jorge Granados - Design & Construction Manager Michael Costa - Project Director Charlie Guess - DB Oversight Manager
679 CP 2-3 HSR 13-57 36 5/10/2017 Dragados/Flatiron Joint Venture Utility Relocation Rescinded - PG&E Provisional Sum $253,715.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide management and support of activities to move PG&E facilities out of the way of the future high-speed rail system. Jorge Granados - Design & Construction Manager Michael Costa - Project Director Charlie Guess - DB Oversight Manager
680 CP 2-3 HSR 13-57 30 5/5/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications DL 44.1 - Open Abutments Type 2 Stru $2,782,471.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement new design requirements for bridges over the future high-speed rail system. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Charlie Guess, DB Oversight Manager
681 CP 2-3 HSR 13-57 28 5/5/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications RAM Reporting and Analysis $1,200,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide plans, reports, manuals and tests related to the Reliability, Availability and Maintainability requirements. Jorge Granados, P.E. - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
682 CP 2-3 HSR 13-57 27 5/5/2017 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Utility Disconnects $2,700,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to disconnect utilities from structures planned for demolition. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Charlie Guess, DB Oversight Manager
683 CP 2-3 HSR 13-57 19 5/5/2017 Dragados/Flatiron Joint Venture Differing Site Conditions Adjust Design Grade for Subsidence $2,527,630.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to update the design to reflect new survey data. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Charlie Guess, DB Oversight Manager
684 CP 2-3 HSR 13-57 10.4 5/5/2017 Dragados/Flatiron Joint Venture Environmental Ave 24 - 4 Seasons Crossing Design $698,625.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design Avenue 24 as a four-season undercrossing beneath the future high-speed rail system due to the high groud water in Tulare County. Jorge Granados, P.E. - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
685 CP 2-3 HSR 13-57 10.3 5/5/2017 Dragados/Flatiron Joint Venture Environmental Tulare Co Item 1.08 Road 24 Overlay $660,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform construction work on Road 24 to fulfil commitments made to Tulare County Jorge Granados, P.E. - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
686 CP 2-3 HSR 13-57 34 4/26/2017 Dragados/Flatiron Joint Venture Differing Site Conditions Unforseen Field Conditions T&M $150,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to address unexpected conditions. Jorge Granados, P.E. - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
687 CP 2-3 HSR 13-57 31 4/26/2017 Dragados/Flatiron Joint Venture Environmental Inefficiency with using EMMA 1.0 $290,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement the Authority's environmental requirements tracking software. Jorge Granados, P.E. - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
688 CP 2-3 HSR 13-57 35 4/25/2017 Dragados/Flatiron Joint Venture Third-party Related Deductions for Caltrans IQA Design ($4,800,000.00) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to amend the contract to remove the Caltrans quality assurance scope from the contractor and to give it to the Authority. Caltrans provide quality assurance on high-speed rail design affecting the state highway system. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Charlie Guess, DB Oversight Manager
689 CP 2-3 HSR 13-57 26 3/8/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Aesthetic Treatments on Type 1 Struc $560,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide consistent aesthetic treatment on future high-speed rail bridges to make them look the same as those bridges. Jorge Granados - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
690 CP 2-3 HSR 13-57 29 1/25/2017 Dragados/Flatiron Joint Venture Administrative DFJV Early Start Staffing $4,100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to advance design to accelerate the start of construction activities. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Charlie Guess, DB Oversight Manager
691 CP 2-3 HSR 13-57 20 1/24/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications South Ave to Adams Clear and Grub $12,290.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to construct irrigation pipe protection in various locations where irrigation crosses the future high-speed rail system. Jorge Granados, P.E. - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
692 CP 2-3 HSR 13-57 23 12/22/2016 Dragados/Flatiron Joint Venture Environmental Reexam Fowler Elkhorn Clovis Davis $67,018.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to prepare additional environmental analysis at the Fowler, Elkhorn, Clovis and Davis bridges. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
693 CP 2-3 HSR 13-57 24 10/14/2016 Dragados/Flatiron Joint Venture Environmental Material Abatement COP 88,88.1,88.2 $528,610.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at 26 sites. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
694 CP 2-3 HSR 13-57 22 10/14/2016 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Storage of Foundation Piles $7,500.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to store construction elements prior to installation. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
695 CP 2-3 HSR 13-57 18 9/26/2016 Dragados/Flatiron Joint Venture Third-party Related Washington IC, People's, Lakeside $117,662.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide plans for interpretive, educational materials and photography for Washington Irrigated Colony and Peoples Ditch as well as plants to screen the Lakeside Cemetery. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
696 CP 2-3 HSR 13-57 17 9/26/2016 Dragados/Flatiron Joint Venture Third-party Related Jurisdictional Delineation $138,266.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide environmental work within the Kings River Complex of rivers. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
697 CP 2-3 HSR 13-57 10.2 9/26/2016 Dragados/Flatiron Joint Venture Environmental Tulare Co Landowner ROW (Design) $331,167.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to develop alternative design solutions to accommodate landowner facilities near Avenues 88 and 24. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
698 CP 2-3 HSR 13-57 21 9/16/2016 Dragados/Flatiron Joint Venture Administrative Additional Allowable Stored Material $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the Special Provisions section 8.2, Unincorporated Materials, to include a list of specific materials. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
699 CP 2-3 HSR 13-57 16 8/22/2016 Dragados/Flatiron Joint Venture Environmental Cultural Mitigation of Two Buildings $92,778.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide cultural mitigation evaluations of buildings in Fresno as part of the Authority's environmental commitments. Jorge Granados, P.E. - Design & Construction Manager Drew Erickson - Third Party Manager Charlie Guess, DB Oversight Manager
700 CP 2-3 HSR 13-57 13 8/15/2016 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Design CP 2-3 to meet CP1 profile $77,446.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to coordinate the design between Construction Package 1 and Construction Package 2-3 at the point where they meet. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
701 CP 2-3 HSR 13-57 10.1 7/18/2016 Dragados/Flatiron Joint Venture Environmental Tulare Co Overlay No. 1.09 $1,596,855.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform road construction work on Road 40 to fulfil commitments made to Tulare County. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
702 CP 2-3 HSR 13-57 14 6/30/2016 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Orthographic Photography $8,160.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide high resolution pictures and maps of the project area. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
703 CP 2-3 HSR 13-57 12 5/13/2016 Dragados/Flatiron Joint Venture Environmental Abatement of Hazardous Materials $456,905.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at 13 properties owned by the Authority. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
704 CP 2-3 HSR 13-57 10 5/11/2016 Dragados/Flatiron Joint Venture Environmental Tulare County Agreement - Design $1,899,482.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design and develop final construction cost estimates for Tulare County's requirements at 18 roads and associated land acquisition activities. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
705 CP 2-3 HSR 13-57 11 5/5/2016 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Start Bridge Construction $327,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to assess the potential risks and benefits associated with early bridge construction. This included assembling a team to review the Contract Baseline Schedule, design processes, permitting processes, Right-of-Way availability, attend briefings, prepare a cost estimate and schedule analysis, and present the findings and recommendations to Authority staff. Jorge Granados - Design & Construction Manager Lloyd Neal - Project Manager Charlie Guess - DB Oversight Manager
706 CP 2-3 HSR 13-57 9 5/4/2016 Dragados/Flatiron Joint Venture Differing Site Conditions Analysis of Subsidence Survey Data $20,954.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to prepare a digital terrain model. Jorge Granados - Design & Construction Manager Lloyd Neal - Project Manager Charlie Guess, DB Oversight Manager
707 CP 2-3 HSR 13-57 8 4/7/2016 Dragados/Flatiron Joint Venture Utility Relocation Evaluation of PG&E Provisional Sum $105,891.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to estimate the scale of work to move all PG&E facilities out of the way of the future high-speed rail system. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
708 CP 2-3 HSR 13-57 7 4/4/2016 Dragados/Flatiron Joint Venture Environmental Tribal Monitoring $130,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct daily Tribal Monitoring during the Authority’s pre-construction phase. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
709 CP 2-3 HSR 13-57 4.1 3/23/2016 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Supplemental ROW Delineators $2,932.50 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to buy, install and maintain more poles to show the limit of property bought by the Authority. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
710 CP 2-3 HSR 13-57 4 3/1/2016 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Right-of-Way Delineators $107,467.50 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to buy, install and maintain poles to show the limit of property bought by the Authority. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
711 CP 2-3 HSR 13-57 5 1/29/2016 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Subsidence Survey $335,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to survey the gradual caving in or sinking of an area of land (subsidence). This scope of work includes data collection, planning and reporting with remote sensing technology (LIDAR). Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
712 CP 2-3 HSR 13-57 2 1/4/2016 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Hormel Feed Mill Alignment Study $29,963.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to re-design the route of the future high-speed rail system to avoid the Hormel Feed Mill. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
713 CP 2-3 HSR 13-57 3 11/12/2015 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Early Start Analysis Staff $120,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is the addition of two contractor management staff to assist the Authority in evaluating the effort needed to start early construction. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
714 CP 2-3 HSR 13-57 1 7/31/2015 Dragados/Flatiron Joint Venture Administrative Partnering & DRB $270,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to account for the partnering and Dispute Resolution Board (DRB)expenses the Authority shares with the contractor. The Authority is responsible for 50% of the Partnering and DRB costs over the planned four year duration. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
715 CP 4 HSR 14-32 97 6/23/2021 California Rail Builders Third-Party Related Sempra Additional Costs to CO-0056 - SR46 Roundabout $266,281.40 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders for costs imposed by Southern California Gas Company (Sempra) related to the relocation(s) of Sempra facilities required in conjunction with the future construction of a new roundabout on SR46. Steven Milton Antonio Canete Robert Kennah
716 CP 4 HSR 14-32 98 6/23/2021 California Rail Builders Third-Party Related Kern County Reimbursement to Vacate Roads $42,800.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate CRB for the actual costs paid by CRB to Kern County associated with the processing of applications for roadway vacations. Steven Milton Antonio Canete Robert Kennah
717 CP 4 HSR 14-32 101 6/30/2021 California Rail Builders Administrative Insurance Premium Costs $519,674.81 This is a change to a contract for construction services in the Central Valley. The reason for the change is to reimburse California Rail Builders for actual costs of insurance premiums. Steven Milton Antonio Canete Robert Kennah
718 CP 4 HSR 14-32 88 2/9/2021 California Rail Builders Changes to Plans and Specifications Installation of Irrigation Casings at McCombs Ave $1,356,245.99 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders for the design and construction of four irrigation casings at McCombs Avenue on the western side of the grade separation. Steven Milton Antonio Canete Robert Kennah
719 CP 4 HSR 14-32 89 2/24/2021 California Rail Builders Right-of-Way (ROW) Related Landowner Reimbursement (DL-00081) $165,357.69 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders for having provided payment to Wasco Real Properties I, LLC for costs associated with modifying/reconnecting the property's (FB-15-0352) drainage to accomodate CP4. Steven Milton Antonio Canete Robert Kennah
720 CP 4 HSR 14-32 39R3 1/29/2021 California Rail Builders Changes to Plans and Specifications Design and Construction of Intrusion Protection Barrier (IPB) with Sheet Piling Wall from STA 15391+03.27 to STA 15414+07.27 $5,819,801.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders for all costs and expenses associated with the design and construction of the berms and partial berms for use as intrusion protection barriers on the CP4 project between stations STA 15391+03.27 and STA 15414+07.27. Joe Hedges Antonio Canete Robert Kennah
721 CP 4 HSR 14-32 39R4 1/28/2021 California Rail Builders Changes to Plans and Specifications Drainage for Intrusion Protection Barrier(s) located between station 15426+88.18 and station 15664+00 $8,430,000.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders for the cost increases in the construction of the drainage system for the intrusion protection barriers between station 15426+88.18 and station 15664+00 resulting from the Authority directives altering design criteria, standards, and specifications for intrusion protection barrier(s). Joe Hedges Antonio Canete Robert Kennah
722 CP 4 HSR 14-32 32r1 12/24/2020 California Rail Builders Dispute Resolution Delay Damages due to Extension of Project Completion Deadlines $11,025,974.70 This is a change to a contract for construction services in the Central Valley. The reason for the change is to account for delays caused by the Authority which caused, contributed to, or resulted in the extension of the substantial completion deadline to December 15, 2021 and the final acceptance deadline to February 17, 2022. Joe Hedges Antonio Canete Robert Kennah
723 CP 4 HSR 14-32 84 12/30/2020 California Rail Builders Changes to Plans and Specifications Quality Milestone Data Pack Structure and Content $1,000,000.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders for adherence to additional requirements related to Quality Milestone Data Pack (QMDP) structure and content as applicable to construction verification and validation. Steven Milton Antonio Canete Robert Kennah
724 CP 4 HSR 14-32 78 11/30/2020 California Rail Builders Third-Party Related Poso Ave Encroachment Permit Requirements $400,000 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders for the reimbursement of additional and unforeseen permit costs associated with the City of Wasco. Steven Milton Antonio Canete Robert Kennah
725 CP 4 HSR 14-32 82 11/30/2020 California Rail Builders Changes to Plans and Specifications Construction Specifications and RAM Deliverable $2,190,031.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders for modifications to requirements related to the additional documents and management of technical contract requirements. Steven Milton Antonio Canete Robert Kennah
726 CP 4 HSR 14-32 86 11/30/2020 California Rail Builders Third-Party Related Sempra Additional Costs #2 $104,349.54 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders for additional costs imposed by Sempra and to be paid by CRB related to relocations of Sempra facilities. Steven Milton Antonio Canete Robert Kennah
727 CP 4 HSR 14-32 87 11/30/2020 California Rail Builders Environmental Environmental Monitoring Additional Cost July - Sept $813,357.10 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to compensate CRB for additional environmental monitoring costs from July to September 2020, due to delays in the acquisition of project-required Right of Way. Steven Milton Antonio Canete Robert Kennah
728 CP 4 HSR 14-32 76 10/30/2020 California Rail Builders Third-Party Related Canal 9-26 Mitigation Measures Construction of Temporary Bypass $469,685.88 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders for the construction of a temporary by-pass at Canal 9-26 and its subsequent removal upon completion of the relocation of Canal 9-26. Steven Milton Antonio Canete Robert Kennah
729 CP 4 HSR 14-32 81 10/7/2020 California Rail Builders Changes to Plans and Specifications SR46 CIDH Piling Resequencing $250,783.60 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders to move the CIDH pile drilling operation once to SR-46 HSR Bridge Abutment 3 to perform Contract work. Steven Milton Antonio Canete Robert Kennah
730 CP 4 HSR 14-32 83 10/29/2020 California Rail Builders Third-Party Related Additional Mitigation Girders Installation $623,712.78 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders for the direct costs associated with the out of sequence works related to ROW delays in delevery of PG&E Conflict 12079. Steven Milton Antonio Canete Robert Kennah
731 CP 4 HSR 14-32 77 9/29/2020 California Rail Builders Changes to Plans and Specifications Merced Abutment and Earthwork Resequencing $449,219.17 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders for efforts related to the Get to Work initiative at the Merced Overpass. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
732 CP 4 HSR 14-32 72 9/28/2020 California Rail Builders Third-Party Related Frontier Unknown Utility Conflict 2003 Relocation $906,149.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders to relocate the Frontier Communications line identified as Conflict #2003. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
733 CP 4 HSR 14-32 18R5 9/28/2020 California Rail Builders Environmental Additional Environmental Surveys & Investigations R5 $2,100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to increase the Not-to-Exceed (NTE) amount of Change Order 18 to $7,222,556.20. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
734 CP 4 HSR 14-32 80 9/25/2020 California Rail Builders Environmental Environmental Monitoring Additional Cost February to July 2020 $2,414,634.88 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders for additional Environmental Monitoring Costs from February to July 2020. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
735 CP 4 HSR 14-32 43R1 9/18/2020 California Rail Builders Right-of-Way (ROW) Related Landowner Reimbursement #2 $80,250.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders to make an immediate payment to Mr. Steve Brock of Land Value Farms, Fresno, California. This payment is for additional modifications to the farm’s irrigation system made and paid for by Mr. Brock to accommodate the CP-4 and are reimbursable to Mr. Brock and Land Value Farms by the Authority. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
736 CP 4 HSR 14-32 51R1 8/31/2020 California Rail Builders Environmental Claim Settlement for DL-00058 Additional Dedicated Wildlife Crossing $5,444,957.80 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to pay California Rail Builders for the installation of additional dedicated wildlife crossings as required by CDFW. Elias Mahfoud Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
737 CP 4 HSR 14-32 75 8/28/2020 California Rail Builders Third-Party Related PGE Conflict Out of Sequence #3 $968,522.57 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to compensate California Rail Builders for direct costs associated to out of sequence works related to PG&E conflicts 12030 and 12033-12036 , as part of the Get-to-Work initiative. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
738 CP 4 HSR 14-32 74 8/28/2020 California Rail Builders Third-Party Related Mitigation Measures Semitropic Conflicts $3,531,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to compensate California Rail Builders for out of sequence works relating to 14 Semitropic conflicts, due to delays in land rights agreements and Semitropic relocation delays. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
739 CP 4 HSR 14-32 73 8/27/2020 California Rail Builders Changes to Plans and Specifications Kimberlina and Merced Access Road $42,016.58 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to compensate California Rail Builders for additional design work associated to the reconfiguration of the Kimberlina and Merced access roads. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
740 CP 4 HSR 14-32 68 8/27/2020 California Rail Builders Third-Party Related Lighting at McCombs and Merced Overpassing $1,510,728.93 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to compensate California Rail Builders for the installation of safety lighting at the McCombs and Merced overpasses and SR-43 crossings, as required by Kern County. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
741 CP 4 HSR 14-32 71 8/20/2020 California Rail Builders Changes to Plans and Specifications RAM Deliverables Accelerated Costs $36,191.65 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to compensate California Rail Builders for the additional effort involved in the acceleration of delivery of RAM deliverables, including Maintenance Concept, Maintenance Manuals, and the Maintainability Demonstration Test Plan and Procedure. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
742 CP 4 HSR 14-32 70 8/12/2020 California Rail Builders Environmental Additional Costs to Keep Active Zones Environmentally Cleared $1,171,185.66 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to compensate California Rail Builders for keeping active zones environmentally cleared, active while waiting for property acquisition or land rights to be secured by the Authority. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
743 CP 4 HSR 14-32 69 7/31/2020 California Rail Builders Environmental Environmental Monitoring Additional Costs up to Jan 2020 $2,701,092.97 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to compensate CRB for additional environmental monitoring costs through January 2020, due to delays in the acquisition of project-required Right of Way. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
744 CP 4 HSR 14-32 61 7/31/2020 California Rail Builders Right-of-Way (ROW) Related McCombs Overpass Construction - Schedule Mitigation Measures $2,027,317.69 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to compensate CRB for out of sequence works/mitigation measures at McCombs overpass and other roadworks. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
745 CP 4 HSR 14-32 64 7/16/2020 California Rail Builders Third-Party Related PG&E Conflicts Out of Sequence Work #2 $1,628,345.78 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to compensate CRB for out of sequence works related to PG&E conflict 12077 MSE Wall and CIP Wall. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
746 CP 4 HSR 14-32 59 7/16/2020 California Rail Builders Changes to Plans and Specifications McCombs CIDH Piling Resequencing $382,517.88 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is to move the CIDH pile drilling operation to McCombs Rd Bridge Abutment 4 to perform contract work for an expedite fee for hoops and revised rebar, plus stand-by charges. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
747 CP 4 HSR 14-32 67 7/14/2020 California Rail Builders Administrative Daily Sanitizing Porter Service $57,780.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to provide daily porter services for the Wasco High Speed Rail offices, as a proactive measure to protect the staff against COVID-19 Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
748 CP 4 HSR 14-32 65 7/14/2020 California Rail Builders Third-Party Related Wasco Amtrak Station Security $10,523.92 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to provide security for the Wasco Amtrak station during the placement of girders. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
749 CP 4 HSR 14-32 63 7/14/2020 California Rail Builders Right-of-Way (ROW) Related Parcel FB-15-0028 Iafrati Farms Landowner Reimbursement $14,245.58 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to provide payment to Iafrati Farms, owner of Parcel FB-15-0028, for the cost of reconnection of their irrigation system to the Semitropic Water Storage District system. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
750 CP 4 HSR 14-32 62 7/14/2020 California Rail Builders Right-of-Way (ROW) Related Poso Ave Underpass Construction - Schedule Mitigation Measures $3,922,875.11 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to compensate CRB for the direct costs associated with the out of sequence works/mitigation measures at the Poso Ave. underpass. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
751 CP 4 HSR 14-32 60 7/6/2020 California Rail Builders Right-of-Way (ROW) Related Mitigation Measures for Wasco Viaduct - Drilled Shafts $601,385.66 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to compensate CRB for out of sequence work related to various PG&E conflicts. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
752 CP 4 HSR 14-32 57 7/6/2020 California Rail Builders Administrative Electrostatic Disinfection Services $43,206.60 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to provide electrostatic disinfection services for the Wasco High Speed Rail offices, as a proactive measure to protect the staff against COVID-19. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
753 CP 4 HSR 14-32 58 6/23/2020 California Rail Builders Third Party PG&E Conflicts Out of Sequence $4,368,775.71 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to compensate CRB for out of sequence work related to various PG&E conflicts. Steven Milton Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
754 CP 4 HSR 14-32 56 5/29/2020 California Rail Builders Third-Party Related So Cal Gas (Sempra) Additional Costs $9,798,912.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to finalize negotiations of a dispute regarding So Cal Gas (Sempra) work. Joe Hedges - Chief Operating Officer Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
755 CP 4 HSR 14-32 18 R4 5/19/2020 California Rail Builders Environmental Add'l Survey & Investigation $2,147,556.20 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to increase the Not-to-Exceed (NTE) amount of Change Order 18, executed on June 19,2017 for $400,000, previously increased under Change Order 18R2 executed on May 2, 2018 by $700,000, by Change Order 18R3 executed on Dec. 3, 2019 for $1,875,000 and by this CO for $2,147,556.20 to $5,122,556.20. The reason for change order number 18 is a delay in the release of land to the general contractor to begin construction. Joe Hedges - Chief Operating Officer Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
756 CP 4 HSR 14-32 55 4/21/2020 California Rail Builders Roadway Modifications Peterson Road Bridge Extension Mitigation Measure $4,998,981.43 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to redesign and construct an extension to the previously planned bridge at Peterson Road in Wasco, California. Elias Mahfoud Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
757 CP 4 HSR 14-32 39 R2 3/5/2020 California Rail Builders Track Structure: At-grade track IPB Remaining Berm Viaduct Mod Const $15,872,287.58 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to initiate construction of a portion of the Intrusion Protection Barrier berm on the project. Joe Hedges - Chief Operating Officer Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
758 CP 4 HSR 14-32 53 2/28/2020 California Rail Builders Environmental Removal of Two Underground Storage Tank's and Two Concrete Vaults at G Street $71,211.60 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to compensate for the removal of underground facilities tanks in Wasco, California. Elias Mahfoud Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
759 CP 4 HSR 14-32 51 2/27/2020 California Rail Builders Environmental Claim Settlement for DL-00058 Dedicated Wildlife Crossing $11,938,500.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to pay California Rail Builders for the installation of Dedicated Wildlife Crossings on the project. Joe Hedges - Chief Operating Officer Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
760 CP 4 HSR 14-32 11 R1 2/18/2020 California Rail Builders Contract Upgraded Site Office Internet Bandwidth $41,275.08 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to increase internet speed for the Authority's utilization.This Change Order shall fully compensate California Rail Builders (CRB) to provide an upgrade the Authority’s Wasco Office internet from 10 Mbps to 20 Mbps internet connection with fiber optic. Elias Mahfoud Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
761 CP 4 HSR 14-32 52 2/18/2020 California Rail Builders Roadway Modifications Merced CIDH Piling Resequencing $121,364.75 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to pay California Rail Builders for mitigation costs due to PG&E delays. Elias Mahfoud Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
762 CP 4 HSR 14-32 50 1/14/2020 California Rail Builders Environmental Mitigation Costs Reimbusement for Zones 12-15 $1,914,162.87 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to pay California Rail Builders for mitigation costs due to right-of-way acquisition delay in Wasco. Elias Mahfoud Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
763 CP 4 HSR 14-32 39 R1 12/10/2019 California Rail Builders Track Structure: At-grade track IBP Last Mile $13,977,559.30 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to initiate construction of a portion of the Intrusion Protection Barrier berm on the project. Joe Hedges - Chief Operating Officer Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
764 CP 4 HSR 14-32 49 12/10/2019 California Rail Builders Site Utiltiies Relocation Water Service at Parcel FB-15-00-28 $83,978.62 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to install a 24-inch casing and 12-inch PVC water line to enable existing water service restoration to a parcel in Wasco. Elias Mahfoud Antonio Canate Berenguer - Project Director and CEO of CRB Robert Kennah - DB Oversignt Manager
765 CP 4 HSR 14-32 48 12/4/2019 California Rail Builders Changes to Plans and Specifications Kimberlina CIDH Piling Work Resequencing $265,860.94 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is to move the pile drilling operation twice to install and remove additional CMP liners at Kimberlina Abutment 2. Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
766 CP 4 HSR 14-32 18 R3 12/3/2019 California Rail Builders Environmental Additional Environmental Surveys and Investigations $1,875,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to increase the Not-to-Exceed (NTE) amount of Change Order 18, executed on June 19,2017 for $400,000 and previously increased under Change Order 18R2 executed on May 2, 2018 by $700,000. The NTE ceiling is now increased by $1,875,000 to $2,875,000. The reason for change order number 18 is a delay in the release of land to the general contractor to begin construction. Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
767 CP 4 HSR 14-32 47 11/22/2019 California Rail Builders Utility Relocation Sempra Relocation at State Route 46 Conflict 10003 Design $459,722.86 This is a change to a contract for design services in the Central Valley. The reason for the change is to fully compensate California Rail Builders for the design of the relocation of utility conflict #10003, a gas line at State Route 46 owned by Sempra Energy, (“Sempra”, also known as SoCalGas). Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
768 CP 4 HSR 14-32 46 11/5/2019 California Rail Builders Right-of-Way (ROW) Related Mitigation Cost Reimburse Zones 1-5 $2,800,000.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is mitigation costs incurred due to the delay in right-of-way (ROW) acquisition in the north area of CP-4 (Zones 1-5). Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
769 CP 4 HSR 14-32 45 10/28/2019 California Rail Builders Changes to Plans and Specifications Intrusion Protection Barrier Design Modifications $1,300,000.00 This is a change to a contract for design services in the Central Valley. The reason for the change is required design revisions due to updates to the Intrusion Protection Barrier standards ordered under Directive Letters (DL) 0007, 0024, 0024R1, 0024R3, and 0024R4. Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
770 CP 4 HSR 14-32 44 10/8/2019 California Rail Builders Changes to Plans and Specifications Work Separation of HSR Alignment from State Route 46 at BNSF Crossing $68,821.33 This is a change to a contract for design and construction services in the Central Valley. This reason for the change is to fully compensate the Contractor for work performed under Directive Letter (DL)-00054 of April 8, 2019, Separation of Work of HSR Alignment form SR 46 at BNSF Crossing. This work includes evaluations of conceptual options to resolve the conflict between the current BSNF shoofly design at SR 46 and the requirement of DL-00054 to finish the construction of the HSR Alignment by the Substantial Completion Date and then complete the other work of SR 46 at BNSF Crossing at a date to be determined. Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
771 CP 4 HSR 14-32 43 10/8/2019 California Rail Builders Right-of-Way (ROW) Related Landowner Reimbursement $125,688.67 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders to make an immediate payment to Mr. Steve Brock of Land Value Farms, Fresno, California. This payment is for modifications to the farm’s irrigation system made and paid for by Mr. Brock to accommodate the CP-4 and are reimbursable to Mr. Brock and Land Value Farms by the Authority. Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
772 CP 4 HSR 14-32 42 10/3/2019 California Rail Builders Changes to Plans and Specifications Resume Original Merced Avenue Alignment Design $601,641.77 This is a change to a contract for design services in the Central Valley. The reason for the change is to fully compensate California Rail Builders to cease all design work for the Merced Avenue Overhead and Roadway Realignment as defined in Directive Letter (DL) DL-00025, DL-00025R1, and Change Order (CO) CO-00021, and to resume and complete the design work for the original Contract alignment. Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
773 CP 4 HSR 14-32 41 9/24/2019 California Rail Builders Changes to Plans and Specifications Revise Realignment of Canal 9-22 Design $180,657.04 This is a change to a contract for design services in the Central Valley. The reason for the change is to fully compensate California Rail Builders to revise the design of the realignment of Canal 922. Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
774 CP 4 HSR 14-32 39 8/29/2019 California Rail Builders Changes to Plans and Specifications IPB Last Mile $5,500,000.00 This is a change to a contract for design and construction services in the Central Valley. The change order is to construct a protective barrier to separate the high-speed rail alignment from the adjacent freight railroad as modified by the Authority’s Directive Letter 24R3. Joe Hedges - Chief Operating Officer Antonio Canete - Project Director and CEO Stephen Lowry - Design-Build Oversignt Manager
775 CP 4 HSR 14-32 27 R1 8/28/2019 California Rail Builders Utility Relocation Design SR-46 Pumping Station to RFC $242,102.40 This is a change to a contract for design and construction services in the Central Valley. The change order is to design a replacement for the Caltrans pumping station at State Route 46 to move it out of the way of the high-speed rail alignment. Elias Mahfoud - Senior State Contract Manager Antonio Canete - Project Director and CEO Stephen Lowry - Design-Build Oversignt Manager
776 CP 4 HSR 14-32 40 8/26/2019 California Rail Builders Utility Relocation Un-ID'd Frontier Utility Conflicts $25,879.00 This is a change to a contract for design and construction services in the Central Valley. The change order moves Frontier Communications facilities out of the way of the high-speed rail alignment. Elias Mahfoud - Senior State Contract Manager Antonio Canete - Project Director and CEO Stephen Lowry - Design-Build Oversignt Manager
777 CP 4 HSR 14-32 38 8/15/2019 California Rail Builders Changes to Plans and Specifications CO 38 BNSF Access Roads $3,717,579.65 This is a change to a contract for design and construction services in the Central Valley. The change order is to design and construct BNSF access roads where access is impacted by the high-speed rail project. Elias Mahfoud - Senior State Contract Manager Antonio Canete - Project Director and CEO Stephen Lowry - Design-Build Oversignt Manager
778 CP 4 HSR 14-32 35 8/6/2019 California Rail Builders Environmental CO 35 Reimburse Specific CDFW Fees $73,053.62 This is a change to a contract for design and construction services in the Central Valley. The change order allows for the acquisition of the required environmental permits for construction at 5 locations on the high-speed rail right of way. Elias Mahfoud - Senior State Contract Manager Antonio Canete - Project Director and CEO Mike Barbour - Design-Build Oversignt Manager
779 CP 4 HSR 14-32 37 7/25/2019 California Rail Builders Utility Relocation SoCal Edison Relocation at Peterson Road $324,862.51 This is a change to a contract for design and construction services in the Central Valley. The change order moves Edison Overhead Distribution line out of the way of the future high-speed rail system at Peterson Road in Kern County. Elias Mahfoud - Senior State Contract Manager Antonio Canete - Project Director and CEO Mike Barbour - Design-Build Oversignt Manager
780 CP 4 HSR 14-32 36 7/25/2019 California Rail Builders Third-party Related City of Wasco Additional Utility Casings-Increase Amount $4,998,220.99 This is a change to a contract for design and construction services in the Central Valley. The change order pays for installation of 9 utility casings and design of 1 utility casing for the City of Wasco. Elias Mahfoud - Senior State Contract Manager Antonio Canete - Project Director and CEO Mike Barbour - Design-Build Oversignt Manager
781 CP 4 HSR 14-32 34 5/20/2019 California Rail Builders Differing Site Conditions City of Wasco Well #13 Test Well $297,900.28 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay the City of Wasco, the local governing body, to move its services out of the way of the future high-speed rail system. This work is coordinated by the general contractor in Wasco responsible for designing and constructing the future high-speed rail system. Elias Mahfoud - Senior State Contract Manager Antonio Canete, Project Director and CEO of CRP Mike Barbour, Design-Build Oversight Manager
782 CP 4 HSR 14-32 33 3/21/2019 California Rail Builders Administrative CO 33 Un-ID Frontier Con 2000-2002 $190,962.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay Frontier Communications, a telecomunications company, to move its services out of the way of the future high-speed rail system. This work is coordinated by the general contractor in Wasco responsible for designing and constructing the future system. William Grimsley, Acting Director of Design & Construction Antonio Canete, Project Director and CEO of CRP Mike Barbour, Design-Build Oversight Manager
783 CP 4 HSR 14-32 32 3/4/2019 California Rail Builders Dispute Resolution CO 32 Settlement/ Release/Wavier $40,459,152.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to account for delays caused by the Authority from the start of work until January 31, 2019. This change order allows the general contractor more time and additional budget to complete the delayed work (as documented in Time Impact Analyses 1 through 5). In addition to the additional budget, a contract extension of 525 working days was given to the contractor. Joe Hedges - Chief Operating Officer Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
784 CP 4 HSR 14-32 28 2/8/2019 California Rail Builders Dispute Resolution CO 28 Dispute Review-Executive $- This is a change to a contract for construction services in the Central Valley. This change eliminates the Dipute Resolution Board from the dispute resolution procedures. The reason for the change is to improve dispute resolution process. Joe Hedges, Chief Operating Officer Antonio Canete, Project Director and CEO of CRP Mike Barbour, Design-Build Oversight Manager
785 CP 4 HSR 14-32 30 11/28/2018 California Rail Builders Environmental CO 30 BNSF ROE Permits Renewal-2018 $17,988.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to secure permits to enter BNSF proprety to conduct work. William Grimsley - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
786 CP 4 HSR 14-32 29 10/31/2018 California Rail Builders Dispute Resolution CO 29 Privately-Own Irrigation Line $1,819,676.47 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to relocate private irrigation lines to move them out of the way of the future high-speed rail system. William Grimsley - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
787 CP 4 HSR 14-32 27 9/5/2018 California Rail Builders Third-party Related CO 27 SR46 @ BNSF Crossing Design $1,158,550.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design the BNSF bridge at State Route 46 and the State Route 46 roadway. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
788 CP 4 HSR 14-32 18 R2 6/26/2018 California Rail Builders Environmental CO 18R2 Enviro Surveys & Invest R2 $700,000.00 This is a change to a contract for design and construction services in the Central Valley. This is a supplemental to change order number 18 to increase the cost for the work by an additional $700,000 taking the total to $1,100,000. The reason for change order number 18 is a delay in the release of land to the general contractor to begin construction. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
789 CP 4 HSR 14-32 26 6/21/2018 California Rail Builders Third-party Related CO 26 Pile Rig Standby Costs $171,200.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct pile load tests and to pay for unused equipment due to lack of land on which to conduct the tests. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
790 CP 4 HSR 14-32 25 6/21/2018 California Rail Builders Third-party Related CO 25 Kimberlina Crossing @BNSF&SR43 $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to incorporate the revised design to the Kimberlina Avenue crossing. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
791 CP 4 HSR 14-32 24 5/9/2018 California Rail Builders Administrative CO 24 MultiMonth Schedule 12/17-3/18 $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the requirements for updates to the schedule from December 2017 through March 2018. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
792 CP 4 HSR 14-32 23 4/17/2018 California Rail Builders Third-party Related CO 23 Caltrans Reimbursement ($3,530,000.00) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement the agreement between the Authority and Caltrans for Caltrans to bill their services on the project directly to the Authority. This change order provides the Authority a credit for removing these activities from the contract. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
793 CP 4 HSR 14-32 22 1/31/2018 California Rail Builders Third-party Related CO 22 BNSF ROE Insurance Renewal $26,165.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to extend insurance policies required by BNSF for entry onto their property. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
794 CP 4 HSR 14-32 21 1/31/2018 California Rail Builders Third-party Related CO 21 Merced Ave Realignment Design $300,199.06 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design a bridge alternative at the Merced Avenue overpass. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
795 CP 4 HSR 14-32 20 8/15/2017 California Rail Builders Changes to Plans and Specifications CO 20 Ductbank Ext. to System Site $296,356.31 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to construct underground duct banks for the future high-speed rail system. Benjamin Camarena - Design & Construction Manager Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
796 CP 4 HSR 14-32 19 7/31/2017 California Rail Builders Administrative CO 19 McCombs Avenue Options Study $40,732.72 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to study three options for the design at McCombs Avenue. Benjamin Camarena - Design & Construction Manager Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
797 CP 4 HSR 14-32 12 6/20/2017 California Rail Builders Differing Site Conditions CO 12 Prelim Enviro&Geotech Inv Work $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete the remaining environmental and geotechnical investigations. Benjamin Camarena - Design & Construction Manager Antonio Canete - Project Directo and CEO of CRB Claudio Dallavalle - Design-Build Oversight Manager
798 CP 4 HSR 14-32 18 6/1/2017 California Rail Builders Differing Site Conditions CO 18 Add'l Survey & Investigation $400,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is a delay in the release of land to the general contractor to begin construction. Benjamin Camarena - Design & Construction Manager Antonio Canete - Project Directo and CEO of CRB Claudio Dallavalle - Design-Build Oversight Manager
799 CP 4 HSR 14-32 15 5/15/2017 California Rail Builders Right-of-Way (ROW) Related CO 15 ROW Delay Notices & TIA Sub. $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to clarify the Right-of-Way delay notification and time impact analysis processes in the contract. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Claudio Dallavalle - Design-Build Oversight Manager
800 CP 4 HSR 14-32 13 4/13/2017 California Rail Builders Administrative CO 13 Multimonth Progress Updates $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the requirements for updates to the schedule to bring the schedule baseline up to date. Benjamin Camarena - Design & Construction Manager Antonio Canete - Project Directo and CEO of CRB Claudio Dallavalle - Design-Build Oversight Manager
801 CP 4 HSR 14-32 11 3/17/2017 California Rail Builders Administrative CO 11 Authority Wasco Internet Upgra $32,492.88 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to install an internet connection to the Authority office in Wasco. Benjamin Camarena - Design & Construction Manager Antonio Canete - Project Directo and CEO of CRB Claudio Dallavalle - Design-Build Oversight Manager
802 CP 4 HSR 14-32 10 2/17/2017 California Rail Builders Administrative CO 10 Admin Correction to CO No. 02 $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to correct an error on change order number 2. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Claudio Dallavalle - Design-Build Oversight Manager
803 CP 4 HSR 14-32 9 2/7/2017 California Rail Builders Third-party Related CO 9 Additional BNSF Insurance $3,450.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to obtain right of entry permits from BNSF. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
804 CP 4 HSR 14-32 8 1/17/2017 California Rail Builders Third-party Related CO 8 Partnering Services-Ongoing $237,150.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to establish a fund for partnering costs, which are shared between the Authority and the contractor. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
805 CP 4 HSR 14-32 7 11/14/2016 California Rail Builders Dispute Resolution CO 7 Disputes Resolution Board $250,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to establish a fund for the Dispute Resolution Board and dispute resolution training. Costs are shared between the Authority and the contractor. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
806 CP 4 HSR 14-32 6 10/17/2016 California Rail Builders Third-party Related CO 6 Partnering Services $9,900.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct partnering workshops between the Authority and the contractor. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
807 CP 4 HSR 14-32 2 8/22/2016 California Rail Builders Dispute Resolution CO 2 Tribal Monitoring $74,557.60 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct tribal monitoring as part of the Authrities environmental requirements. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
808 CP 4 HSR 14-32 5 8/12/2016 California Rail Builders Administrative CO 5 Addition of Griffith to Bonds $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to modify the contract with Griffith Company becoming a 20% member of the general contractor. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
809 CP 4 HSR 14-32 4 7/19/2016 California Rail Builders Dispute Resolution CO4 BNSF Timeframe Clarification $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to record a new commitment regarding work to be completed by BNSF from 24 to 12 months. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
810 CP 4 HSR 14-32 3 7/19/2016 California Rail Builders Administrative CO3 Form I Update $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to modify the contract based on updated data regarding bonding, insurance and mobilization costs. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
811 CP 4 HSR 14-32 1 3/24/2016 California Rail Builders Third-party Related CO 1 Bonding and Insurance Increase $1,359,570.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to cover increases in bonding and insurance costs associated with an increase in work related to moving public utilities out of the way of the future high-speed rail system. Terry Ogle - Director of Design & Construction Jose Baraja - Authorized Representative Claudio Dallavalle - PCM Oversight Manager
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment